From: Sibenac, Mark [sib@mbari.org] Sent: Tuesday, December 23, 2003 12:41 PM To: Thomas, Hans Subject: Meeting Notes with Schedule from 23-Dec-2003 23-December-2003 AUV Mapping Meeting 10:00-12:30 Surface Commons Reson bottle should show up on 30-Dec-2003. - Side-scan and sbp will run and log in 7k format - Jury-rigged power system Software: - Rich to track down Nathaniel for a 6046 driver - 15 days of work to integrate and run sbp and sss (8 msgs) - Rich to finish ctd driver. Needs to test against real hw (5 days) - PSA916 driver done, assuming terminal server hookup - Rob: gps driver needs to be modified to pull data from INS Reasons to test at sea from Zephyr in Jan/Feb: 1) Perception to management 2) Reson bottle will be here 3) Pushed other Zephyr users out of the way, so we better use it! Personnel out of office: Drew - 12/22-1/2 Robert - 12/31-1/14 Andy - 12/31-1/9 Mark - 12/24-1/9 Mark - 2/17-2/27 Bill - 12/22-1/9 Farley - 12/24, 1/2 Hans - 1/2 MIT here: 1/9-1/18 Bluefin here: February DMO out to sea with AUV-CTD on 7 and 8 January 2004. Mid-Section Testing Schedule ---------------------------- 12/30 - Initial power-up/test with reson bottle 1/5-1/8 - Test fit bottle in mid-section - Test fit cable lengths 1/9 - Lifting frame complete 1/13 - Trim and ballast in tank 1/14-1/16 - Electrical test of mid-section in tank - Build 40' wet test cable with MHDL 1/20-1/23 - SW testing/batt testing with nose and mid-section in air 1/26-1/30 - In-tank test with nose and mid-section 2/2-2/6 - Electrical test with tail - Mech test with Rx/INS alignment 2/9-2/13 - Margin 2/17 - Ship bottle+Rx head to Reson Question - does RESON want the complete body, or can we strip the necessary components out and only give them the bottle, projector, and RX head? Nose Testing Schedule --------------------- 12/23 - Get one 2kWh battery from DMO 12/23 - Test fit 2kWh battery 12/23 - Locate access port for charging tether 1/16 - Test completed JBox 1/16 - Two Bluefin 2kWh batteries show up 1/20 - Float/trim check 1/20-1/23 - SW test of PSA916 and FastCat 1/26-1/30 - In-tank test of batt nose with mid-section 2/2-2/6 - Electrical test with tail components 2/9-2/13 - Margin Integrated Vehicle Testing Schedule ----------------------------------- 2/26 - Integrate nose+midsec+tail - Order dummies for xducer cabling - Borrow rx ring simulator or fab one ourselves 3/1-3/5 - Tank test of nose+midsec+tail - Single point lift test - Drop-weight testing - Margin 3/8-3/12 - Acomms+LBL test in harbor 3/15-3/18 - Zephyr at sea tests with nose+midsec+tail - Deploy xponder at sea