MOOS mooring 2/22/02 meeting NOTES
Present: Lance, Ed, Mark C. (notes)
Update on project status
|
ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
|
3 |
power system prelim. design & diagram - In progress. |
8.33 days |
Tue 2/12/02 |
Fri 2/22/02 |
Mellinger Ed[60%] |
|
4 |
Battery system 10W |
79 days |
Fri 2/22/02 |
Thu 6/13/02 |
|
|
5 |
chemistry review - Batteries are specified, Jon and Ed working are working on installation location and housing design. Jon cannot complete the tower/float design until the battery housings are completely defined. |
3 days |
Fri 2/22/02 |
Wed 2/27/02 |
Mellinger Ed[60%] |
|
10 |
Solar power system |
77 days |
Tue 2/12/02 |
Wed 5/29/02 |
|
|
11 |
size panels to available tower area - Panel sizes are specified. |
8.33 days |
Tue 2/12/02 |
Fri 2/22/02 |
Mellinger Ed[60%] |
|
12 |
design panel mounts and tower access - In progress. |
5 days |
Fri 2/22/02 |
Fri 3/1/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
|
29 |
controller and RF communications - Lance McBride is in charge of the controller system design and hardware. Also in charge of RF link issues. |
76.67 days |
Mon 2/11/02 |
Tue 5/28/02 |
unassigned EE[60%] |
|
30 |
temporary controller requirements specified - Draft controller requirements distributed. |
8.33 days |
Mon 2/11/02 |
Thu 2/21/02 |
unassigned EE[60%] |
|
31 |
wave/acceleration instrument specified TBD |
5 days |
Mon 2/11/02 |
Fri 2/15/02 |
Chaffey Mark[60%] |
|
32 |
wave/acceleration instrument on order TBD |
50 days |
Mon 2/18/02 |
Fri 4/26/02 |
|
|
33 |
temporary controller specified Pending finalization of controller requirements. |
8.33 days |
Thu 2/21/02 |
Tue 3/5/02 |
unassigned EE[60%] |
|
38 |
Test mooring riser cable system |
105 days |
Mon 2/11/02 |
Fri 7/5/02 |
|
|
39 |
selection of riser cable vendor Documentation packages out to Walter Paul and Phil Gibson (TMT) for evaluation. Results not back from TMT until around March 1. Cable must be ordered by second week in March to be assured timely delivery. |
20 days |
Mon 2/11/02 |
Fri 3/8/02 |
Chaffey Mark[60%],Mellinger Ed[10%] |
|
44 |
snubber hose system |
125 days |
Mon 2/11/02 |
Fri 8/2/02 |
|
|
45 |
coil cord specified Preliminary design completed by Walter Paul. It looks like the cable can contain eight electrical and four optical elements as desired. |
5 days |
Mon 2/11/02 |
Fri 2/15/02 |
Chaffey Mark[20%],Walter Paul[50%],Mellinger Ed[10%] |
|
46 |
snubber electro-optical connectors specified - Preliminary design cartoon and specification (see below) submitted to SeaCon for design and delivery quote. SeaCon requested more information and revised design cartoon going out Tuesday. |
5 days |
Mon 2/18/02 |
Fri 2/22/02 |
Chaffey Mark[60%],Mellinger Ed[10%] |
|
47 |
snubber hose system concept design - Initial design cartoon looks promising. Revised design cartoon going to team, Walter Paul and SeaCon Tuesday. Critical path to getting the connectors and snubber on order. |
8.5 days |
Fri 2/15/02 |
Wed 2/27/02 |
Erickson Jon[40%],Chaffey Mark[20%] |
|
48 |
bridle/snubber strain gage specified - Snubber design concept looks like strain gage can be a bolt-on addition in the location of the instrument cage between the two snubber elements. |
8.33 days |
Mon 2/11/02 |
Thu 2/21/02 |
unassigned EE[60%] |
|
49 |
bridle/snubber strain gage mechanical design - If the current snubber concept holds then this is not critical path. |
8.33 days |
Thu 2/21/02 |
Tue 3/5/02 |
Erickson Jon[60%] |
|
61 |
Surface buoy design |
79.67 days |
Tue 2/12/02 |
Mon 6/3/02 |
|
|
62 |
preliminary tower design - Mock-ups of vertical and tilted solar panel array styles complete and have been evaluated. Vertical array the preferred design from Observatory support perspective and does not require custom solar panels. Additional issues are the style and location of battery boxes and electronics enclosures. |
6 days |
Tue 2/12/02 |
Tue 2/19/02 |
Erickson Jon[60%] |
|
63 |
tower PDR - Tower PDR work is nearly complete. Will schedule PDR of design for end of week of February 25th. |
0 days |
Tue 2/19/02 |
Tue 2/19/02 |
Erickson Jon,Mellinger Ed |