MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
140.67 daysMon 2/11/02Mon 8/26/02 13%
2
power system design
87.33 daysTue 2/12/02Thu 6/13/02Mellinger Ed[45%]34%
3
power system prelim. design & diagram
8.33 daysTue 2/12/02Wed 3/13/02Mellinger Ed[60%]60%
4
Battery system 10W
79 daysFri 2/22/02Thu 6/13/02 45%
7
battery housing size, design and locate
10 daysWed 3/6/02Thu 3/21/02Mellinger Ed[60%],Erickson Jon[60%]75%
10
Solar power system
79 daysTue 2/12/02Fri 5/31/02 18%
12
design panel mounts and tower access
5 daysFri 2/22/02Mon 3/11/02Mellinger Ed[60%],Erickson Jon[60%]60%
13
specifiy and order panels
10 daysFri 3/1/02Fri 3/22/02Mellinger Ed[60%]60%
15
select solar charge controller/PPT
10 daysTue 3/19/02Thu 4/4/02Mellinger Ed[60%]10%
20
Wind power system
45.67 daysThu 3/7/02Thu 5/9/02 52%
22
turbine mount and access design
1 dayFri 3/8/02Fri 3/8/02Mellinger Ed[60%],Erickson Jon[60%]75%
29
controller and RF communications
86.83 daysMon 2/11/02Tue 6/11/02 20%
30
temporary controller requirements specified
8.33 daysMon 2/11/02Tue 3/19/02McBride Lance[60%]90%
31
wave/acceleration instrument specified
5 daysThu 2/28/02Thu 3/14/02Chaffey Mark[60%]10%
32
wave/acceleration instrument on order
35 daysThu 3/14/02Thu 5/2/02 0%
33
temporary controller specfied
8.33 daysMon 3/4/02Thu 3/21/02McBride Lance[60%]95%
36
CERF adapter board debugging
12 daysThu 3/14/02Fri 3/29/02McBride Lance[60%],SE[60%]33%
37
RF communications specified
8.33 daysTue 3/19/02Mon 4/1/02McBride Lance[60%]0%
41
Test mooring riser cable system
113 daysMon 2/11/02Wed 7/17/02 16%
42
selection of riser cable vendor
20 daysMon 2/11/02Wed 3/20/02Chaffey Mark[60%],Mellinger Ed[10%]90%
47
snubber hose system
140.67 daysMon 2/11/02Mon 8/26/02 6%
49
snubber electro-optical connectors specified
5 daysMon 2/18/02Wed 3/20/02Chaffey Mark[60%],Mellinger Ed[10%]75%
51
bridle/snubber strain gage specified
8.33 daysThu 2/28/02Thu 3/14/02unassigned EE[60%]40%
52
bridle/snubbe strain gage mechanical design
8.33 daysFri 3/15/02Wed 3/27/02Erickson Jon[60%]0%
64
Surface buoy design
70.83 daysTue 2/12/02Tue 5/21/02 7%
68
bridle final design
5 daysTue 3/19/02Mon 3/25/02Erickson Jon[60%]0%
72
float design
5 daysMon 3/4/02Fri 3/22/02Erickson Jon[60%]80%
74
Anchor and benthic transition design
61.67 daysTue 3/19/02Wed 6/12/02 0%
75
anchor system preliminary design
8.33 daysTue 3/19/02Fri 3/29/02Erickson Jon[60%],Chaffey Mark[60%]0%