Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 140.67 days | Mon 2/11/02 | Mon 8/26/02 | 13% | |
| 2 | power system design | 87.33 days | Tue 2/12/02 | Thu 6/13/02 | Mellinger Ed[45%] | 34% |
| 3 | power system prelim. design & diagram | 8.33 days | Tue 2/12/02 | Wed 3/13/02 | Mellinger Ed[60%] | 60% |
| 4 | Battery system 10W | 79 days | Fri 2/22/02 | Thu 6/13/02 | 45% | |
| 7 | battery housing size, design and locate | 10 days | Wed 3/6/02 | Thu 3/21/02 | Mellinger Ed[60%],Erickson Jon[60%] | 75% |
| 10 | Solar power system | 79 days | Tue 2/12/02 | Fri 5/31/02 | 18% | |
| 12 | design panel mounts and tower access | 5 days | Fri 2/22/02 | Mon 3/11/02 | Mellinger Ed[60%],Erickson Jon[60%] | 60% |
| 13 | specifiy and order panels | 10 days | Fri 3/1/02 | Fri 3/22/02 | Mellinger Ed[60%] | 60% |
| 15 | select solar charge controller/PPT | 10 days | Tue 3/19/02 | Thu 4/4/02 | Mellinger Ed[60%] | 10% |
| 20 | Wind power system | 45.67 days | Thu 3/7/02 | Thu 5/9/02 | 52% | |
| 22 | turbine mount and access design | 1 day | Fri 3/8/02 | Fri 3/8/02 | Mellinger Ed[60%],Erickson Jon[60%] | 75% |
| 29 | controller and RF communications | 86.83 days | Mon 2/11/02 | Tue 6/11/02 | 20% | |
| 30 | temporary controller requirements specified | 8.33 days | Mon 2/11/02 | Tue 3/19/02 | McBride Lance[60%] | 90% |
| 31 | wave/acceleration instrument specified | 5 days | Thu 2/28/02 | Thu 3/14/02 | Chaffey Mark[60%] | 10% |
| 32 | wave/acceleration instrument on order | 35 days | Thu 3/14/02 | Thu 5/2/02 | 0% | |
| 33 | temporary controller specfied | 8.33 days | Mon 3/4/02 | Thu 3/21/02 | McBride Lance[60%] | 95% |
| 36 | CERF adapter board debugging | 12 days | Thu 3/14/02 | Fri 3/29/02 | McBride Lance[60%],SE[60%] | 33% |
| 37 | RF communications specified | 8.33 days | Tue 3/19/02 | Mon 4/1/02 | McBride Lance[60%] | 0% |
| 41 | Test mooring riser cable system | 113 days | Mon 2/11/02 | Wed 7/17/02 | 16% | |
| 42 | selection of riser cable vendor | 20 days | Mon 2/11/02 | Wed 3/20/02 | Chaffey Mark[60%],Mellinger Ed[10%] | 90% |
| 47 | snubber hose system | 140.67 days | Mon 2/11/02 | Mon 8/26/02 | 6% | |
| 49 | snubber electro-optical connectors specified | 5 days | Mon 2/18/02 | Wed 3/20/02 | Chaffey Mark[60%],Mellinger Ed[10%] | 75% |
| 51 | bridle/snubber strain gage specified | 8.33 days | Thu 2/28/02 | Thu 3/14/02 | unassigned EE[60%] | 40% |
| 52 | bridle/snubbe strain gage mechanical design | 8.33 days | Fri 3/15/02 | Wed 3/27/02 | Erickson Jon[60%] | 0% |
| 64 | Surface buoy design | 70.83 days | Tue 2/12/02 | Tue 5/21/02 | 7% | |
| 68 | bridle final design | 5 days | Tue 3/19/02 | Mon 3/25/02 | Erickson Jon[60%] | 0% |
| 72 | float design | 5 days | Mon 3/4/02 | Fri 3/22/02 | Erickson Jon[60%] | 80% |
| 74 | Anchor and benthic transition design | 61.67 days | Tue 3/19/02 | Wed 6/12/02 | 0% | |
| 75 | anchor system preliminary design | 8.33 days | Tue 3/19/02 | Fri 3/29/02 | Erickson Jon[60%],Chaffey Mark[60%] | 0% |