MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02

Tasks

ID

Task Name

Duration

Start

Finish

Resource Names

% Complete

3

power system prelim. design & diagram

8.33 days

Tue 2/12/02

Fri 3/29/02

Mellinger Ed[60%]

70%

4

power system housing specification/design

5 days

Fri 3/29/02

Fri 4/5/02

Mellinger Ed[60%]

0%

9

battery housing size, design and locate

10 days

Wed 3/6/02

Tue 3/26/02

Mellinger Ed[60%],Erickson Jon[60%]

95%

14

design panel mounts and tower access

5 days

Fri 2/22/02

Mon 3/11/02

Mellinger Ed[60%],Erickson Jon[60%]

60%

16

panel delivery time

15 days

Thu 3/28/02

Wed 4/17/02

 

0%

17

select solar charge controller/PPT

10 days

Tue 3/19/02

Tue 4/9/02

Mellinger Ed[60%]

10%

24

turbine mount and access design

1 day

Fri 3/8/02

Fri 3/8/02

Mellinger Ed[60%],Erickson Jon[60%]

75%

27

select wind charge controller

8.33 days

Thu 3/28/02

Tue 4/9/02

Mellinger Ed[60%]

50%

32

temporary controller requirements specified

8.33 days

Mon 2/11/02

Tue 3/26/02

McBride Lance[60%]

95%

34

wave/acceleration instrument on order

35 days

Wed 3/27/02

Tue 5/14/02

 

0%

35

temporary controller specfied

8.33 days

Mon 3/4/02

Tue 3/26/02

McBride Lance[60%]

95%

38

CERF adapter board debugging

12 days

Thu 3/14/02

Fri 3/29/02

McBride Lance[60%],SE[60%]

75%

39

RF communications specified

8.33 days

Tue 3/26/02

Fri 4/5/02

McBride Lance[60%]

0%

41

controller housing and chassis specification/design

6 days

Tue 3/26/02

Wed 4/3/02

Chaffey Mark[10%],McBride Lance[60%]

0%

42

temporary controller on order/fab

30 days

Tue 3/26/02

Tue 5/7/02

 

0%

43

controller housing fabrication

20 days

Wed 4/3/02

Wed 5/1/02

 

0%

46

selection of riser cable vendor

20 days

Mon 2/11/02

Tue 3/26/02

Chaffey Mark[60%],Mellinger Ed[10%]

95%

47

riser cable on order

80 days

Wed 3/27/02

Tue 7/16/02

 

0%

53

snubber electro-optical connectors specified

5 days

Mon 2/18/02

Tue 3/26/02

Chaffey Mark[60%],Mellinger Ed[10%]

80%

55

bridle/snubber strain gage specified

8.33 days

Thu 2/28/02

Mon 4/1/02

unassigned EE[60%]

40%

57

snubber hose final design specifcation

8.33 days

Wed 3/27/02

Mon 4/8/02

Chaffey Mark[60%],Erickson Jon[60%]

25%

61

coilcord core cable fabrication

35 days

Tue 3/26/02

Mon 5/13/02

 

0%

63

snubber electo-optical connectors delivery time

100 days

Wed 3/27/02

Tue 8/13/02

 

0%

70

tower final detailed design

8.33 days

Tue 3/26/02

Fri 4/5/02

Erickson Jon[60%]

0%

71

bridle final design

5 days

Tue 3/26/02

Mon 4/1/02

Erickson Jon[60%]

0%

75

float design

5 days

Mon 3/4/02

Wed 3/27/02

Erickson Jon[60%]

80%

76

float order and lead time

40 days

Wed 3/27/02

Wed 5/22/02

 

0%

78

anchor system preliminary design

8.33 days

Tue 3/26/02

Fri 4/5/02

Erickson Jon[60%],Chaffey Mark[60%]

0%