Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02
|
ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
|
3 |
power system prelim. design & diagram |
8.33 days |
Tue 2/12/02 |
Fri 3/29/02 |
Mellinger Ed[60%] |
70% |
|
4 |
power system housing specification/design |
5 days |
Fri 3/29/02 |
Fri 4/5/02 |
Mellinger Ed[60%] |
0% |
|
9 |
battery housing size, design and locate |
10 days |
Wed 3/6/02 |
Tue 3/26/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
95% |
|
14 |
design panel mounts and tower access |
5 days |
Fri 2/22/02 |
Mon 3/11/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
60% |
|
16 |
panel delivery time |
15 days |
Thu 3/28/02 |
Wed 4/17/02 |
|
0% |
|
17 |
select solar charge controller/PPT |
10 days |
Tue 3/19/02 |
Tue 4/9/02 |
Mellinger Ed[60%] |
10% |
|
24 |
turbine mount and access design |
1 day |
Fri 3/8/02 |
Fri 3/8/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
75% |
|
27 |
select wind charge controller |
8.33 days |
Thu 3/28/02 |
Tue 4/9/02 |
Mellinger Ed[60%] |
50% |
|
32 |
temporary controller requirements specified |
8.33 days |
Mon 2/11/02 |
Tue 3/26/02 |
McBride Lance[60%] |
95% |
|
34 |
wave/acceleration instrument on order |
35 days |
Wed 3/27/02 |
Tue 5/14/02 |
|
0% |
|
35 |
temporary controller specfied |
8.33 days |
Mon 3/4/02 |
Tue 3/26/02 |
McBride Lance[60%] |
95% |
|
38 |
CERF adapter board debugging |
12 days |
Thu 3/14/02 |
Fri 3/29/02 |
McBride Lance[60%],SE[60%] |
75% |
|
39 |
RF communications specified |
8.33 days |
Tue 3/26/02 |
Fri 4/5/02 |
McBride Lance[60%] |
0% |
|
41 |
controller housing and chassis specification/design |
6 days |
Tue 3/26/02 |
Wed 4/3/02 |
Chaffey Mark[10%],McBride Lance[60%] |
0% |
|
42 |
temporary controller on order/fab |
30 days |
Tue 3/26/02 |
Tue 5/7/02 |
|
0% |
|
43 |
controller housing fabrication |
20 days |
Wed 4/3/02 |
Wed 5/1/02 |
|
0% |
|
46 |
selection of riser cable vendor |
20 days |
Mon 2/11/02 |
Tue 3/26/02 |
Chaffey Mark[60%],Mellinger Ed[10%] |
95% |
|
47 |
riser cable on order |
80 days |
Wed 3/27/02 |
Tue 7/16/02 |
|
0% |
|
53 |
snubber electro-optical connectors specified |
5 days |
Mon 2/18/02 |
Tue 3/26/02 |
Chaffey Mark[60%],Mellinger Ed[10%] |
80% |
|
55 |
bridle/snubber strain gage specified |
8.33 days |
Thu 2/28/02 |
Mon 4/1/02 |
unassigned EE[60%] |
40% |
|
57 |
snubber hose final design specifcation |
8.33 days |
Wed 3/27/02 |
Mon 4/8/02 |
Chaffey Mark[60%],Erickson Jon[60%] |
25% |
|
61 |
coilcord core cable fabrication |
35 days |
Tue 3/26/02 |
Mon 5/13/02 |
|
0% |
|
63 |
snubber electo-optical connectors delivery time |
100 days |
Wed 3/27/02 |
Tue 8/13/02 |
|
0% |
|
70 |
tower final detailed design |
8.33 days |
Tue 3/26/02 |
Fri 4/5/02 |
Erickson Jon[60%] |
0% |
|
71 |
bridle final design |
5 days |
Tue 3/26/02 |
Mon 4/1/02 |
Erickson Jon[60%] |
0% |
|
75 |
float design |
5 days |
Mon 3/4/02 |
Wed 3/27/02 |
Erickson Jon[60%] |
80% |
|
76 |
float order and lead time |
40 days |
Wed 3/27/02 |
Wed 5/22/02 |
|
0% |
|
78 |
anchor system preliminary design |
8.33 days |
Tue 3/26/02 |
Fri 4/5/02 |
Erickson Jon[60%],Chaffey Mark[60%] |
0% |