ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
|
1 |
Mooring test deployment |
147.67 days |
Mon 2/11/02 |
Wed 9/4/02 |
|
20% |
|
3 |
power system prelim. design & diagram |
8.33 days |
Tue 2/12/02 |
Thu 4/25/02 |
Mellinger Ed[60%] |
70% |
|
4 |
power system housing specification/design |
5 days |
Thu 4/25/02 |
Thu 5/2/02 |
Mellinger Ed[60%] |
0% |
|
14 |
design panel mounts and tower access |
5 days |
Fri 2/22/02 |
Mon 3/11/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
60% |
|
16 |
panel delivery time |
15 days |
Tue 4/23/02 |
Mon 5/13/02 |
|
0% |
|
17 |
select solar charge controller/PPT |
10 days |
Tue 3/19/02 |
Fri 5/3/02 |
Mellinger Ed[60%] |
10% |
|
24 |
turbine mount and access design |
1 day |
Fri 3/8/02 |
Fri 3/8/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
75% |
|
32 |
temporary controller requirements specified |
8.33 days |
Mon 2/11/02 |
Tue 3/26/02 |
McBride Lance[60%] |
95% |
|
34 |
wave/acceleration instrument on order |
35 days |
Tue 4/23/02 |
Mon 6/10/02 |
|
0% |
|
35 |
temporary controller specified |
8.33 days |
Mon 3/4/02 |
Tue 3/26/02 |
McBride Lance[60%] |
95% |
|
39 |
RF communications specified |
8.33 days |
Tue 3/26/02 |
Mon 4/29/02 |
McBride Lance[60%] |
50% |
|
40 |
controller wiring design complete |
8.33 days |
Mon 4/29/02 |
Thu 5/9/02 |
McBride Lance[60%] |
25% |
|
41 |
controller housing and chassis specification/design |
6 days |
Tue 3/26/02 |
Thu 4/25/02 |
Chaffey Mark[10%],McBride Lance[60%] |
50% |
|
42 |
temporary controller on order/fab |
30 days |
Tue 3/26/02 |
Tue 5/7/02 |
|
0% |
|
43 |
controller housing fabrication |
20 days |
Fri 4/26/02 |
Thu 5/23/02 |
|
0% |
|
48 |
riser cable termination socket design |
8.33 days |
Fri 4/19/02 |
Wed 5/1/02 |
Chaffey Mark[60%],Erickson Jon[60%] |
20% |
|
49 |
riser cable termination socket fabrication |
10 days |
Wed 5/1/02 |
Wed 5/15/02 |
shop[75%] |
0% |
|
55 |
bridle/snubber strain gage specified |
8.33 days |
Thu 2/28/02 |
Mon 4/29/02 |
unassigned EE[60%] |
40% |
|
57 |
snubber hose final design specifcation |
8.33 days |
Wed 3/27/02 |
Mon 4/29/02 |
Chaffey Mark[60%],Erickson Jon[60%] |
50% |
|
58 |
snubber hose fabrication |
84 days |
Mon 4/29/02 |
Fri 8/23/02 |
|
0% |
|
61 |
coilcord core cable fabrication |
35 days |
Mon 4/1/02 |
Fri 5/17/02 |
|
49% |
|
63 |
snubber electo-optical connectors delivery time |
90 days |
Tue 4/2/02 |
Mon 8/5/02 |
|
18% |
|
64 |
bending strain relief specified |
3 days |
Mon 4/15/02 |
Wed 4/17/02 |
Erickson Jon[60%] |
0% |
|
70 |
tower final detailed design |
8.33 days |
Wed 4/17/02 |
Mon 4/29/02 |
Erickson Jon[60%] |
0% |
|
71 |
bridle final design |
5 days |
Tue 3/26/02 |
Thu 4/25/02 |
Erickson Jon[60%] |
50% |
|
72 |
tower and bridle CDR |
0 days |
Mon 4/29/02 |
Mon 4/29/02 |
Erickson Jon |
0% |
|
73 |
tower fabrication |
35 days |
Mon 4/29/02 |
Mon 6/17/02 |
|
0% |
|
74 |
bridle fabrication |
35 days |
Mon 4/29/02 |
Mon 6/17/02 |
|
0% |
|
75 |
float design |
5 days |
Mon 3/4/02 |
Tue 4/23/02 |
Erickson Jon[60%] |
90% |
|
78 |
anchor system preliminary design |
8.33 days |
Tue 4/23/02 |
Fri 5/3/02 |
Erickson Jon[60%],Chaffey Mark[60%] |
0% |