MOOS mooring 4/24/02 meeting agenda

1.

ID

Task Name

Duration

Start

Finish

Resource Names

% Complete

1

Mooring test deployment

147.67 days

Mon 2/11/02

Wed 9/4/02

 

20%

3

power system prelim. design & diagram

8.33 days

Tue 2/12/02

Thu 4/25/02

Mellinger Ed[60%]

70%

4

power system housing specification/design

5 days

Thu 4/25/02

Thu 5/2/02

Mellinger Ed[60%]

0%

14

design panel mounts and tower access

5 days

Fri 2/22/02

Mon 3/11/02

Mellinger Ed[60%],Erickson Jon[60%]

60%

16

panel delivery time

15 days

Tue 4/23/02

Mon 5/13/02

 

0%

17

select solar charge controller/PPT

10 days

Tue 3/19/02

Fri 5/3/02

Mellinger Ed[60%]

10%

24

turbine mount and access design

1 day

Fri 3/8/02

Fri 3/8/02

Mellinger Ed[60%],Erickson Jon[60%]

75%

32

temporary controller requirements specified

8.33 days

Mon 2/11/02

Tue 3/26/02

McBride Lance[60%]

95%

34

wave/acceleration instrument on order

35 days

Tue 4/23/02

Mon 6/10/02

 

0%

35

temporary controller specified

8.33 days

Mon 3/4/02

Tue 3/26/02

McBride Lance[60%]

95%

39

RF communications specified

8.33 days

Tue 3/26/02

Mon 4/29/02

McBride Lance[60%]

50%

40

controller wiring design complete

8.33 days

Mon 4/29/02

Thu 5/9/02

McBride Lance[60%]

25%

41

controller housing and chassis specification/design

6 days

Tue 3/26/02

Thu 4/25/02

Chaffey Mark[10%],McBride Lance[60%]

50%

42

temporary controller on order/fab

30 days

Tue 3/26/02

Tue 5/7/02

 

0%

43

controller housing fabrication

20 days

Fri 4/26/02

Thu 5/23/02

 

0%

48

riser cable termination socket design

8.33 days

Fri 4/19/02

Wed 5/1/02

Chaffey Mark[60%],Erickson Jon[60%]

20%

49

riser cable termination socket fabrication

10 days

Wed 5/1/02

Wed 5/15/02

shop[75%]

0%

55

bridle/snubber strain gage specified

8.33 days

Thu 2/28/02

Mon 4/29/02

unassigned EE[60%]

40%

57

snubber hose final design specifcation

8.33 days

Wed 3/27/02

Mon 4/29/02

Chaffey Mark[60%],Erickson Jon[60%]

50%

58

snubber hose fabrication

84 days

Mon 4/29/02

Fri 8/23/02

 

0%

61

coilcord core cable fabrication

35 days

Mon 4/1/02

Fri 5/17/02

 

49%

63

snubber electo-optical connectors delivery time

90 days

Tue 4/2/02

Mon 8/5/02

 

18%

64

bending strain relief specified

3 days

Mon 4/15/02

Wed 4/17/02

Erickson Jon[60%]

0%

70

tower final detailed design

8.33 days

Wed 4/17/02

Mon 4/29/02

Erickson Jon[60%]

0%

71

bridle final design

5 days

Tue 3/26/02

Thu 4/25/02

Erickson Jon[60%]

50%

72

tower and bridle CDR

0 days

Mon 4/29/02

Mon 4/29/02

Erickson Jon

0%

73

tower fabrication

35 days

Mon 4/29/02

Mon 6/17/02

 

0%

74

bridle fabrication

35 days

Mon 4/29/02

Mon 6/17/02

 

0%

75

float design

5 days

Mon 3/4/02

Tue 4/23/02

Erickson Jon[60%]

90%

78

anchor system preliminary design

8.33 days

Tue 4/23/02

Fri 5/3/02

Erickson Jon[60%],Chaffey Mark[60%]

0%