Project Start Date: Tue 1/1/02
Project Finish Date: Wed 10/2/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 167.67 days | Mon 2/11/02 | Wed 10/2/02 | 23% | |
| 2 | power system design | 115.3 days | Tue 2/12/02 | Tue 7/23/02 | Mellinger Ed[45%] | 42% |
| 3 | power system prelim. design & diagram | 8.33 days | Tue 2/12/02 | Thu 5/23/02 | Mellinger Ed[60%] | 70% |
| 4 | power system housing specification/design | 5 days | Thu 4/25/02 | Mon 5/27/02 | Mellinger Ed[60%] | 50% |
| 6 | Battery system 10W | 79 days | Fri 2/22/02 | Thu 6/13/02 | 68% | |
| 10 | charge controller and monitoring | 10 days | Mon 5/20/02 | Fri 5/31/02 | Mellinger Ed[60%] | 20% |
| 12 | Solar power system | 115.3 days | Tue 2/12/02 | Tue 7/23/02 | 23% | |
| 14 | design panel mounts and tower access | 5 days | Fri 2/22/02 | Mon 3/11/02 | Mellinger Ed[60%],Erickson Jon[60%] | 60% |
| 15 | specifiy and order panels | 6 days | Fri 3/1/02 | Wed 5/22/02 | Mellinger Ed[60%] | 95% |
| 16 | panel delivery time | 21 days | Fri 5/24/02 | Fri 6/21/02 | 0% | |
| 17 | select solar charge controller/PPT | 10 days | Tue 3/19/02 | Tue 6/18/02 | Mellinger Ed[60%] | 25% |
| 22 | Wind power system | 79.5 days | Thu 3/7/02 | Wed 6/26/02 | 52% | |
| 24 | turbine mount and access design | 1 day | Fri 3/8/02 | Fri 3/8/02 | Mellinger Ed[60%],Erickson Jon[60%] | 75% |
| 27 | select wind charge controller | 8.33 days | Thu 3/28/02 | Mon 5/27/02 | Mellinger Ed[60%] | 50% |
| 28 | design wind monitoring hardware | 8.33 days | Mon 5/27/02 | Thu 6/6/02 | Mellinger Ed[60%] | 0% |
| 31 | controller and RF communications | 122.67 days | Mon 2/11/02 | Wed 7/31/02 | 34% | |
| 32 | temporary controller requirements specified | 8.33 days | Mon 2/11/02 | Tue 3/26/02 | McBride Lance[60%] | 95% |
| 34 | wave/acceleration instrument on order | 35 days | Tue 5/21/02 | Mon 7/8/02 | 0% | |
| 35 | temporary controller specfied | 8.33 days | Mon 3/4/02 | Tue 3/26/02 | McBride Lance[60%] | 95% |
| 39 | RF communications specified | 8.33 days | Tue 3/26/02 | Thu 5/23/02 | McBride Lance[60%] | 75% |
| 40 | controller wiring design complete | 8.33 days | Mon 4/29/02 | Fri 5/31/02 | McBride Lance[60%] | 45% |
| 41 | controller housing and chassis specification/design | 6 days | Tue 3/26/02 | Thu 5/23/02 | Chaffey Mark[10%],McBride Lance[60%] | 50% |
| 42 | temporary controller on order/fab | 20 days | Tue 5/21/02 | Mon 6/17/02 | 0% | |
| 43 | controller housing fabrication | 20 days | Fri 5/24/02 | Thu 6/20/02 | 0% | |
| 45 | Test mooring riser cable system | 121 days | Mon 2/11/02 | Mon 7/29/02 | 20% | |
| 47 | riser cable on order | 80 days | Tue 4/2/02 | Mon 7/22/02 | 0% | |
| 48 | riser cable termination socket design | 8.33 days | Fri 4/19/02 | Wed 5/29/02 | Chaffey Mark[60%],Erickson Jon[60%] | 20% |
| 51 | snubber hose system | 165.42 days | Mon 2/11/02 | Mon 9/30/02 | 21% | |
| 55 | bridle/snubber strain gage specified | 8.33 days | Thu 2/28/02 | Mon 5/27/02 | unassigned EE[60%] | 40% |
| 57 | snubber hose final design specifcation | 8.33 days | Wed 3/27/02 | Thu 5/23/02 | Chaffey Mark[60%],Erickson Jon[60%] | 75% |
| 58 | snubber hose fabrication | 84 days | Thu 5/23/02 | Wed 9/18/02 | 0% | |
| 61 | coilcord core cable fabrication | 35 days | Mon 4/1/02 | Fri 5/24/02 | 90% | |
| 62 | coilcord fabrication | 35 days | Fri 5/24/02 | Fri 7/12/02 | 0% | |
| 63 | snubber electo-optical connectors delivery time | 90 days | Tue 4/2/02 | Mon 8/5/02 | 18% | |
| 64 | bending strain relief specified | 3 days | Tue 5/21/02 | Thu 5/23/02 | Erickson Jon[60%] | 0% |
| 65 | bending strain relief delivery time | 50 days | Fri 5/24/02 | Thu 8/1/02 | 0% | |
| 67 | Surface buoy design | 110.5 days | Tue 2/12/02 | Tue 7/16/02 | 15% | |
| 70 | tower final detailed design | 8.33 days | Wed 4/17/02 | Mon 4/29/02 | Erickson Jon[60%] | 84% |
| 71 | bridle final design | 5 days | Tue 3/26/02 | Thu 4/25/02 | Erickson Jon[60%] | 50% |
| 72 | tower and bridle CDR | 0 days | Tue 5/21/02 | Tue 5/21/02 | Erickson Jon | 0% |
| 73 | tower fabrication | 35 days | Tue 5/21/02 | Mon 7/8/02 | 0% | |
| 74 | bridle fabrication | 35 days | Tue 5/21/02 | Mon 7/8/02 | 0% | |
| 75 | float design | 5 days | Mon 3/4/02 | Tue 5/21/02 | Erickson Jon[60%] | 90% |
| 76 | float order and lead time | 40 days | Tue 5/21/02 | Tue 7/16/02 | 0% | |
| 77 | Anchor and benthic transition design | 61.67 days | Tue 5/21/02 | Wed 8/14/02 | 0% | |
| 78 | anchor system preliminary design | 8.33 days | Tue 5/21/02 | Fri 5/31/02 | Erickson Jon[60%],Chaffey Mark[60%] | 0% |
| 87 | Final assembly of test mooring | 132.67 days | Mon 4/1/02 | Wed 10/2/02 | 0% | |
| 88 | Observatory support not available | 27 days | Mon 4/1/02 | Tue 5/7/02 | 0% | |
| 89 | Ed Mellinger not available | 22 days | Mon 4/1/02 | Tue 4/30/02 | Mellinger Ed | 0% |