MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Wed 10/2/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
167.67 daysMon 2/11/02Wed 10/2/02 23%
2
power system design
115.3 daysTue 2/12/02Tue 7/23/02Mellinger Ed[45%]42%
3
power system prelim. design & diagram
8.33 daysTue 2/12/02Thu 5/23/02Mellinger Ed[60%]70%
4
power system housing specification/design
5 daysThu 4/25/02Mon 5/27/02Mellinger Ed[60%]50%
6
Battery system 10W
79 daysFri 2/22/02Thu 6/13/02 68%
10
charge controller and monitoring
10 daysMon 5/20/02Fri 5/31/02Mellinger Ed[60%]20%
12
Solar power system
115.3 daysTue 2/12/02Tue 7/23/02 23%
14
design panel mounts and tower access
5 daysFri 2/22/02Mon 3/11/02Mellinger Ed[60%],Erickson Jon[60%]60%
15
specifiy and order panels
6 daysFri 3/1/02Wed 5/22/02Mellinger Ed[60%]95%
16
panel delivery time
21 daysFri 5/24/02Fri 6/21/02 0%
17
select solar charge controller/PPT
10 daysTue 3/19/02Tue 6/18/02Mellinger Ed[60%]25%
22
Wind power system
79.5 daysThu 3/7/02Wed 6/26/02 52%
24
turbine mount and access design
1 dayFri 3/8/02Fri 3/8/02Mellinger Ed[60%],Erickson Jon[60%]75%
27
select wind charge controller
8.33 daysThu 3/28/02Mon 5/27/02Mellinger Ed[60%]50%
28
design wind monitoring hardware
8.33 daysMon 5/27/02Thu 6/6/02Mellinger Ed[60%]0%
31
controller and RF communications
122.67 daysMon 2/11/02Wed 7/31/02 34%
32
temporary controller requirements specified
8.33 daysMon 2/11/02Tue 3/26/02McBride Lance[60%]95%
34
wave/acceleration instrument on order
35 daysTue 5/21/02Mon 7/8/02 0%
35
temporary controller specfied
8.33 daysMon 3/4/02Tue 3/26/02McBride Lance[60%]95%
39
RF communications specified
8.33 daysTue 3/26/02Thu 5/23/02McBride Lance[60%]75%
40
controller wiring design complete
8.33 daysMon 4/29/02Fri 5/31/02McBride Lance[60%]45%
41
controller housing and chassis specification/design
6 daysTue 3/26/02Thu 5/23/02Chaffey Mark[10%],McBride Lance[60%]50%
42
temporary controller on order/fab
20 daysTue 5/21/02Mon 6/17/02 0%
43
controller housing fabrication
20 daysFri 5/24/02Thu 6/20/02 0%
45
Test mooring riser cable system
121 daysMon 2/11/02Mon 7/29/02 20%
47
riser cable on order
80 daysTue 4/2/02Mon 7/22/02 0%
48
riser cable termination socket design
8.33 daysFri 4/19/02Wed 5/29/02Chaffey Mark[60%],Erickson Jon[60%]20%
51
snubber hose system
165.42 daysMon 2/11/02Mon 9/30/02 21%
55
bridle/snubber strain gage specified
8.33 daysThu 2/28/02Mon 5/27/02unassigned EE[60%]40%
57
snubber hose final design specifcation
8.33 daysWed 3/27/02Thu 5/23/02Chaffey Mark[60%],Erickson Jon[60%]75%
58
snubber hose fabrication
84 daysThu 5/23/02Wed 9/18/02 0%
61
coilcord core cable fabrication
35 daysMon 4/1/02Fri 5/24/02 90%
62
coilcord fabrication
35 daysFri 5/24/02Fri 7/12/02 0%
63
snubber electo-optical connectors delivery time
90 daysTue 4/2/02Mon 8/5/02 18%
64
bending strain relief specified
3 daysTue 5/21/02Thu 5/23/02Erickson Jon[60%]0%
65
bending strain relief delivery time
50 daysFri 5/24/02Thu 8/1/02 0%
67
Surface buoy design
110.5 daysTue 2/12/02Tue 7/16/02 15%
70
tower final detailed design
8.33 daysWed 4/17/02Mon 4/29/02Erickson Jon[60%]84%
71
bridle final design
5 daysTue 3/26/02Thu 4/25/02Erickson Jon[60%]50%
72
tower and bridle CDR
0 daysTue 5/21/02Tue 5/21/02Erickson Jon0%
73
tower fabrication
35 daysTue 5/21/02Mon 7/8/02 0%
74
bridle fabrication
35 daysTue 5/21/02Mon 7/8/02 0%
75
float design
5 daysMon 3/4/02Tue 5/21/02Erickson Jon[60%]90%
76
float order and lead time
40 daysTue 5/21/02Tue 7/16/02 0%
77
Anchor and benthic transition design
61.67 daysTue 5/21/02Wed 8/14/02 0%
78
anchor system preliminary design
8.33 daysTue 5/21/02Fri 5/31/02Erickson Jon[60%],Chaffey Mark[60%]0%
87
Final assembly of test mooring
132.67 daysMon 4/1/02Wed 10/2/02 0%
88
Observatory support not available
27 daysMon 4/1/02Tue 5/7/02 0%
89
Ed Mellinger not available
22 daysMon 4/1/02Tue 4/30/02Mellinger Ed0%