MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 10/8/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
172 daysMon 2/11/02Tue 10/8/02 42%
2
power system design
119.17 daysTue 2/12/02Mon 7/29/02Mellinger Ed[45%]57%
3
power system prelim. design & diagram
8.33 daysTue 2/12/02Thu 6/13/02Mellinger Ed[60%]80%
4
power system housing specification/design
5 daysThu 4/25/02Mon 6/17/02Mellinger Ed[60%]70%
5
power system housing fabrication
15 daysMon 6/17/02Mon 7/8/02shop[75%]0%
6
Battery system 10W
79 daysFri 2/22/02Thu 6/13/02 74%
10
charge controller and monitoring
10 daysMon 5/20/02Fri 5/31/02Mellinger Ed[60%]50%
11
fabricate and wire battery housing
8.33 daysMon 6/3/02Thu 6/13/02Mellinger Ed[60%],Erickson Jon[60%]0%
12
Solar power system
119.17 daysTue 2/12/02Mon 7/29/02 45%
14
design panel mounts and tower access
5 daysFri 2/22/02Thu 6/13/02Mellinger Ed[60%],Erickson Jon[60%]75%
17
select solar charge controller/PPT
10 daysTue 3/19/02Tue 6/18/02Mellinger Ed[60%]75%
18
solar charge controller/PPT lead time
10 daysTue 6/18/02Tue 7/2/02 0%
19
design solar monitoring system hardware
8.33 daysTue 6/18/02Fri 6/28/02Mellinger Ed[60%]0%
22
Wind power system
87.17 daysThu 3/7/02Mon 7/8/02 68%
28
design wind monitoring hardware
8.33 daysMon 5/27/02Tue 6/18/02Mellinger Ed[60%]50%
29
wind power system CDR
0 daysTue 6/18/02Tue 6/18/02 0%
30
assemble complete wind system and test
14 daysTue 6/18/02Mon 7/8/02Mellinger Ed[50%]0%
31
controller and RF communications
134.67 daysMon 2/11/02Fri 8/16/02 50%
32
temporary controller requirements specified
8.33 daysMon 2/11/02Tue 3/26/02McBride Lance[60%]95%
34
wave/acceleration instrument on order
36 daysWed 6/5/02Wed 7/24/02 17%
39
RF communications specified
8.33 daysTue 3/26/02Thu 5/23/02McBride Lance[60%]75%
40
controller wiring design complete
8.33 daysMon 4/29/02Mon 6/17/02McBride Lance[60%]60%
41
controller housing and chassis specification/design
6 daysTue 3/26/02Fri 6/14/02Chaffey Mark[10%],McBride Lance[60%]50%
42
temporary controller on order/fab
20 daysTue 5/21/02Mon 6/17/02 85%
43
controller housing fabrication
20 daysMon 6/17/02Fri 7/12/02 0%
45
Test mooring riser cable system
121 daysMon 2/11/02Mon 7/29/02 61%
47
riser cable on order
80 daysTue 4/2/02Mon 7/22/02 65%
48
riser cable termination socket design
8.33 daysFri 4/19/02Thu 6/20/02Chaffey Mark[60%],Erickson Jon[60%]20%
49
riser cable termination socket fabrication
10 daysThu 6/20/02Thu 7/4/02shop[75%]0%
51
snubber hose system
148.33 daysMon 2/11/02Thu 9/5/02 43%
58
snubber hose fabrication
40 daysWed 6/12/02Tue 8/6/02 0%
59
bridle/snubber/anchor strain gage on order
30 daysWed 6/12/02Tue 7/23/02Erickson Jon[60%]0%
60
coilcord core cable fabrication
35 daysMon 4/1/02Fri 5/24/02 90%
61
coilcord fabrication
35 daysFri 5/24/02Thu 7/18/02 25%
62
snubber electo-optical connectors delivery time
90 daysTue 4/2/02Mon 8/5/02 58%
63
bending strain relief specified
3 daysWed 6/12/02Fri 6/14/02Erickson Jon[60%]0%
64
bending strain relief delivery time
50 daysMon 6/17/02Fri 8/23/02 0%
66
Surface buoy design
126 daysTue 2/12/02Tue 8/6/02 16%
70
bridle final design
5 daysTue 3/26/02Thu 6/13/02Erickson Jon[60%]75%
71
tower and bridle CDR
0 daysFri 5/31/02Fri 5/31/02Erickson Jon0%
72
tower fabrication
35 daysWed 6/12/02Tue 7/30/02 0%
73
bridle fabrication
35 daysThu 6/13/02Thu 8/1/02 0%
75
float order and lead time
40 daysWed 6/12/02Tue 8/6/02 0%
76
Anchor and benthic transition design
43.75 daysWed 6/12/02Mon 8/12/02 0%
77
anchor system preliminary design
8.33 daysWed 6/12/02Mon 6/24/02Erickson Jon[60%],Chaffey Mark[60%]0%