MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Wed 11/6/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
193 daysMon 2/11/02Wed 11/6/02 41%
2
power system design
135 daysTue 2/12/02Mon 8/19/02Mellinger Ed[45%]61%
3
power system prelim. design & diagram
8.33 daysTue 2/12/02Wed 6/26/02Mellinger Ed[60%]80%
4
power system housing specification/design
5 daysThu 4/25/02Fri 6/28/02Mellinger Ed[60%]70%
5
power system housing fabrication
15 daysFri 6/28/02Fri 7/19/02shop[75%]0%
6
Battery system 10W
99 daysFri 2/22/02Thu 7/11/02 80%
10
charge controller and monitoring
10 daysMon 5/20/02Fri 6/28/02Mellinger Ed[60%]60%
11
fabricate and wire battery housing
8.33 daysMon 7/1/02Thu 7/11/02Mellinger Ed[60%],Erickson Jon[60%]25%
12
Solar power system
135 daysTue 2/12/02Mon 8/19/02 53%
14
design panel mounts and tower access
5 daysFri 2/22/02Wed 6/26/02Mellinger Ed[60%],Erickson Jon[60%]75%
19
design solar monitoring system hardware
8.33 daysTue 6/18/02Mon 7/1/02Mellinger Ed[60%]40%
20
solar power system CDR
0 daysMon 7/1/02Mon 7/1/02 0%
21
layout and fab power system board
20 daysTue 7/2/02Mon 7/29/02Mellinger Ed[20%],Duane Thompson[40%]0%
23
Wind power system
95.75 daysThu 3/7/02Thu 7/18/02 68%
29
design wind monitoring hardware
8.33 daysMon 5/27/02Fri 6/28/02Mellinger Ed[60%]55%
30
wind power system CDR
0 daysFri 6/28/02Fri 6/28/02 0%
31
assemble complete wind system and test
14 daysFri 6/28/02Thu 7/18/02Mellinger Ed[50%]0%
32
controller and RF communications
144.67 daysMon 2/11/02Fri 8/30/02 35%
33
temporary controller requirements specified
8.33 daysMon 2/11/02Tue 6/25/02McBride Lance[60%]95%
35
wave/acceleration instrument on order
36 daysWed 6/5/02Wed 7/24/02 42%
41
controller wiring design complete
8.33 daysMon 4/29/02Tue 7/2/02McBride Lance[60%]70%
42
controller housing and chassis specification/design
6 daysTue 3/26/02Thu 6/27/02Chaffey Mark[10%],McBride Lance[60%]55%
43
temporary controller on order/fab
20 daysTue 5/21/02Mon 6/17/02 85%
44
fiber test card design
20 daysThu 6/20/02Wed 7/17/02Scott Jensen[20%]20%
46
controller housing fabrication
20 daysThu 6/27/02Thu 7/25/02 0%
47
RF transcievers hosusing design and fab.
25 daysThu 6/27/02Thu 8/1/02Erickson Jon[10%],McBride Lance[10%]0%
48
compass driver software complete
5 daysTue 6/25/02Mon 7/1/02SE[50%]0%
49
heave sensor software driver
15 daysTue 6/25/02Mon 7/15/02Rich Henthorn0%
50
globalstar modem software driver
15 daysTue 6/25/02Mon 7/15/02Tim Meese[50%]0%
51
Z-Star sampling software driver
15 daysTue 6/25/02Mon 7/15/02Mike Risi0%
53
Test mooring riser cable system
135 daysMon 2/11/02Fri 8/16/02 52%
55
riser cable on order
80 daysTue 4/2/02Mon 7/22/02 76%
56
riser cable termination socket design
8.33 daysFri 4/19/02Wed 7/3/02Chaffey Mark[60%],Erickson Jon[60%]20%
57
riser cable termination socket fabrication
10 daysWed 7/3/02Wed 7/17/02shop[75%]0%
59
specify riser cable floats
4 daysTue 6/25/02Fri 6/28/02Chaffey Mark0%
60
riser cable floats on order
35 daysMon 7/1/02Fri 8/16/02 0%
61
snubber hose system
157.33 daysMon 2/11/02Wed 9/18/02 48%
68
snubber hose fabrication
40 daysTue 6/25/02Mon 8/19/02 0%
69
bridle/snubber/anchor strain gage on order
30 daysWed 6/12/02Tue 7/23/02Erickson Jon[60%]33%
70
coilcord core cable fabrication
35 daysMon 4/1/02Fri 6/28/02 90%
71
coilcord fabrication
35 daysFri 5/24/02Mon 8/5/02 25%
72
snubber electo-optical connectors delivery time
90 daysTue 4/2/02Mon 8/5/02 68%
73
bending strain relief specified
3 daysTue 6/25/02Thu 6/27/02Erickson Jon[60%]0%
74
bending strain relief delivery time
50 daysFri 6/28/02Thu 9/5/02 0%
76
Surface buoy design
131.25 daysTue 2/12/02Wed 8/14/02 24%
80
bridle final design
5 daysTue 3/26/02Wed 6/26/02Erickson Jon[60%]75%
81
tower and bridle CDR
0 daysFri 5/31/02Fri 5/31/02Erickson Jon0%
82
tower fabrication
35 daysTue 6/25/02Mon 8/12/02 0%
83
bridle fabrication
35 daysWed 6/26/02Wed 8/14/02 0%
85
float order and lead time
41 daysWed 6/12/02Wed 8/7/02 24%
86
Anchor and benthic transition design
34.75 daysTue 6/25/02Mon 8/12/02 0%
87
anchor system preliminary design
8.33 daysTue 6/25/02Fri 7/5/02Erickson Jon[60%],Chaffey Mark[60%]0%
93
Final assembly of test mooring
96 daysWed 6/26/02Wed 11/6/02 0%
94
Design and Fab. of stand-up support
20 daysWed 6/26/02Tue 7/23/02Erickson Jon0%