Project Start Date: Tue 1/1/02
Project Finish Date: Wed 11/6/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 193 days | Mon 2/11/02 | Wed 11/6/02 | 41% | |
| 2 | power system design | 135 days | Tue 2/12/02 | Mon 8/19/02 | Mellinger Ed[45%] | 61% |
| 3 | power system prelim. design & diagram | 8.33 days | Tue 2/12/02 | Wed 6/26/02 | Mellinger Ed[60%] | 80% |
| 4 | power system housing specification/design | 5 days | Thu 4/25/02 | Fri 6/28/02 | Mellinger Ed[60%] | 70% |
| 5 | power system housing fabrication | 15 days | Fri 6/28/02 | Fri 7/19/02 | shop[75%] | 0% |
| 6 | Battery system 10W | 99 days | Fri 2/22/02 | Thu 7/11/02 | 80% | |
| 10 | charge controller and monitoring | 10 days | Mon 5/20/02 | Fri 6/28/02 | Mellinger Ed[60%] | 60% |
| 11 | fabricate and wire battery housing | 8.33 days | Mon 7/1/02 | Thu 7/11/02 | Mellinger Ed[60%],Erickson Jon[60%] | 25% |
| 12 | Solar power system | 135 days | Tue 2/12/02 | Mon 8/19/02 | 53% | |
| 14 | design panel mounts and tower access | 5 days | Fri 2/22/02 | Wed 6/26/02 | Mellinger Ed[60%],Erickson Jon[60%] | 75% |
| 19 | design solar monitoring system hardware | 8.33 days | Tue 6/18/02 | Mon 7/1/02 | Mellinger Ed[60%] | 40% |
| 20 | solar power system CDR | 0 days | Mon 7/1/02 | Mon 7/1/02 | 0% | |
| 21 | layout and fab power system board | 20 days | Tue 7/2/02 | Mon 7/29/02 | Mellinger Ed[20%],Duane Thompson[40%] | 0% |
| 23 | Wind power system | 95.75 days | Thu 3/7/02 | Thu 7/18/02 | 68% | |
| 29 | design wind monitoring hardware | 8.33 days | Mon 5/27/02 | Fri 6/28/02 | Mellinger Ed[60%] | 55% |
| 30 | wind power system CDR | 0 days | Fri 6/28/02 | Fri 6/28/02 | 0% | |
| 31 | assemble complete wind system and test | 14 days | Fri 6/28/02 | Thu 7/18/02 | Mellinger Ed[50%] | 0% |
| 32 | controller and RF communications | 144.67 days | Mon 2/11/02 | Fri 8/30/02 | 35% | |
| 33 | temporary controller requirements specified | 8.33 days | Mon 2/11/02 | Tue 6/25/02 | McBride Lance[60%] | 95% |
| 35 | wave/acceleration instrument on order | 36 days | Wed 6/5/02 | Wed 7/24/02 | 42% | |
| 41 | controller wiring design complete | 8.33 days | Mon 4/29/02 | Tue 7/2/02 | McBride Lance[60%] | 70% |
| 42 | controller housing and chassis specification/design | 6 days | Tue 3/26/02 | Thu 6/27/02 | Chaffey Mark[10%],McBride Lance[60%] | 55% |
| 43 | temporary controller on order/fab | 20 days | Tue 5/21/02 | Mon 6/17/02 | 85% | |
| 44 | fiber test card design | 20 days | Thu 6/20/02 | Wed 7/17/02 | Scott Jensen[20%] | 20% |
| 46 | controller housing fabrication | 20 days | Thu 6/27/02 | Thu 7/25/02 | 0% | |
| 47 | RF transcievers hosusing design and fab. | 25 days | Thu 6/27/02 | Thu 8/1/02 | Erickson Jon[10%],McBride Lance[10%] | 0% |
| 48 | compass driver software complete | 5 days | Tue 6/25/02 | Mon 7/1/02 | SE[50%] | 0% |
| 49 | heave sensor software driver | 15 days | Tue 6/25/02 | Mon 7/15/02 | Rich Henthorn | 0% |
| 50 | globalstar modem software driver | 15 days | Tue 6/25/02 | Mon 7/15/02 | Tim Meese[50%] | 0% |
| 51 | Z-Star sampling software driver | 15 days | Tue 6/25/02 | Mon 7/15/02 | Mike Risi | 0% |
| 53 | Test mooring riser cable system | 135 days | Mon 2/11/02 | Fri 8/16/02 | 52% | |
| 55 | riser cable on order | 80 days | Tue 4/2/02 | Mon 7/22/02 | 76% | |
| 56 | riser cable termination socket design | 8.33 days | Fri 4/19/02 | Wed 7/3/02 | Chaffey Mark[60%],Erickson Jon[60%] | 20% |
| 57 | riser cable termination socket fabrication | 10 days | Wed 7/3/02 | Wed 7/17/02 | shop[75%] | 0% |
| 59 | specify riser cable floats | 4 days | Tue 6/25/02 | Fri 6/28/02 | Chaffey Mark | 0% |
| 60 | riser cable floats on order | 35 days | Mon 7/1/02 | Fri 8/16/02 | 0% | |
| 61 | snubber hose system | 157.33 days | Mon 2/11/02 | Wed 9/18/02 | 48% | |
| 68 | snubber hose fabrication | 40 days | Tue 6/25/02 | Mon 8/19/02 | 0% | |
| 69 | bridle/snubber/anchor strain gage on order | 30 days | Wed 6/12/02 | Tue 7/23/02 | Erickson Jon[60%] | 33% |
| 70 | coilcord core cable fabrication | 35 days | Mon 4/1/02 | Fri 6/28/02 | 90% | |
| 71 | coilcord fabrication | 35 days | Fri 5/24/02 | Mon 8/5/02 | 25% | |
| 72 | snubber electo-optical connectors delivery time | 90 days | Tue 4/2/02 | Mon 8/5/02 | 68% | |
| 73 | bending strain relief specified | 3 days | Tue 6/25/02 | Thu 6/27/02 | Erickson Jon[60%] | 0% |
| 74 | bending strain relief delivery time | 50 days | Fri 6/28/02 | Thu 9/5/02 | 0% | |
| 76 | Surface buoy design | 131.25 days | Tue 2/12/02 | Wed 8/14/02 | 24% | |
| 80 | bridle final design | 5 days | Tue 3/26/02 | Wed 6/26/02 | Erickson Jon[60%] | 75% |
| 81 | tower and bridle CDR | 0 days | Fri 5/31/02 | Fri 5/31/02 | Erickson Jon | 0% |
| 82 | tower fabrication | 35 days | Tue 6/25/02 | Mon 8/12/02 | 0% | |
| 83 | bridle fabrication | 35 days | Wed 6/26/02 | Wed 8/14/02 | 0% | |
| 85 | float order and lead time | 41 days | Wed 6/12/02 | Wed 8/7/02 | 24% | |
| 86 | Anchor and benthic transition design | 34.75 days | Tue 6/25/02 | Mon 8/12/02 | 0% | |
| 87 | anchor system preliminary design | 8.33 days | Tue 6/25/02 | Fri 7/5/02 | Erickson Jon[60%],Chaffey Mark[60%] | 0% |
| 93 | Final assembly of test mooring | 96 days | Wed 6/26/02 | Wed 11/6/02 | 0% | |
| 94 | Design and Fab. of stand-up support | 20 days | Wed 6/26/02 | Tue 7/23/02 | Erickson Jon | 0% |