MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/17/02

Tasks

ID

Task Name

Duration

Start

Finish

Resource Names

% Complete

1

Mooring test deployment

222 days

Mon 2/11/02

Tue 12/17/02

 

58%

2

power system design

175 days

Tue 2/12/02

Mon 10/14/02

Mellinger Ed[45%]

59%

4

power system wiring detailed design

16.67 days

Wed 6/26/02

Fri 8/9/02

Mellinger Ed[60%]

80%

5

power system distribution board schematic

16.67 days

Fri 8/9/02

Mon 9/2/02

Mellinger Ed[60%]

0%

6

power system connectors on order

14.29 days

Fri 8/9/02

Thu 8/29/02

Mellinger Ed[7%]

0%

7

power system housing specification/design

5 days

Thu 4/25/02

Wed 8/7/02

Mellinger Ed[60%]

75%

8

power system housing fabrication

15 days

Fri 8/9/02

Fri 8/30/02

shop[75%]

0%

9

Battery system 10W

120.83 days

Fri 2/22/02

Mon 8/12/02

 

94%

13

fabricate and wire battery housing

8.33 days

Mon 7/1/02

Mon 8/12/02

Mellinger Ed[60%],Erickson Jon[60%]

70%

14

Solar power system

127 days

Tue 2/12/02

Wed 8/7/02

 

98%

16

design panel mounts and tower access

5 days

Fri 2/22/02

Wed 8/7/02

Mellinger Ed[60%],Erickson Jon[60%]

80%

21

Wind power system

125.33 days

Thu 3/7/02

Thu 8/29/02

 

71%

27

assemble complete wind system and test

14 days

Fri 8/9/02

Thu 8/29/02

Mellinger Ed[50%]

0%

28

Power system CDR

0 days

Fri 8/9/02

Fri 8/9/02

 

0%

31

controller and RF communications

164.27 days

Mon 2/11/02

Fri 9/27/02

 

59%

41

controller housing and chassis specification/design

6 days

Tue 3/26/02

Wed 8/7/02

Chaffey Mark[10%],McBride Lance[60%]

90%

42

temporary controller on order/fab

20 days

Tue 5/21/02

Mon 6/17/02

 

95%

43

fiber test card design

20 days

Thu 6/20/02

Tue 8/13/02

Scott Jensen[20%]

75%

44

fiber test card fabrication and test

15 days

Wed 8/14/02

Tue 9/3/02

Scott Jensen[20%],Duane Thompson[40%]

0%

45

controller housing fabrication

20 days

Wed 8/7/02

Wed 9/4/02

 

0%

46

RF transcievers hosusing design and fab.

15 days

Wed 8/7/02

Tue 8/27/02

Erickson Jon[10%],McBride Lance[10%]

0%

47

compass driver software complete

5 days

Wed 8/7/02

Tue 8/13/02

SE[50%]

0%

48

heave sensor software driver

15 days

Fri 7/26/02

Fri 8/16/02

Rich Henthorn

50%

49

globalstar modem software driver

15 days

Wed 8/7/02

Tue 8/27/02

Tim Meese[50%]

0%

50

Z-Star sampling software driver

15 days

Tue 6/25/02

Mon 8/12/02

Mike Risi

75%

52

Test mooring riser cable system

162.4 days

Mon 2/11/02

Wed 9/25/02

 

66%

55

riser cable termination socket design

8.33 days

Fri 4/19/02

Thu 8/15/02

Chaffey Mark[60%],Erickson Jon[60%]

20%

56

riser cable termination socket fabrication

10 days

Thu 8/15/02

Thu 8/29/02

shop[75%]

0%

58

specify riser cable floats

4 days

Tue 6/25/02

Wed 8/7/02

Chaffey Mark

90%

59

riser cable floats on order

35 days

Wed 8/7/02

Wed 9/25/02

 

0%

60

snubber hose system

186.08 days

Mon 2/11/02

Tue 10/29/02

 

62%

67

snubber hose fabrication

40 days

Tue 6/25/02

Mon 8/19/02

 

80%

68

bridle/snubber/anchor strain gage on order

57 days

Wed 6/12/02

Thu 8/29/02

Erickson Jon[60%]

72%

69

coilcord core cable fabrication

35 days

Mon 4/1/02

Mon 8/12/02

 

90%

70

coilcord fabrication

35 days

Fri 5/24/02

Tue 9/17/02

 

25%

71

snubber electo-optical connectors delivery time

90 days

Tue 4/2/02

Mon 8/5/02

 

68%

72

bending strain relief specified

3 days

Tue 6/25/02

Wed 8/7/02

Erickson Jon[60%]

75%

73

bending strain relief delivery time

50 days

Wed 8/7/02

Wed 10/16/02

 

0%

75

Surface buoy design

136.25 days

Tue 2/12/02

Wed 8/21/02

 

84%

81

tower fabrication

35 days

Tue 6/25/02

Mon 8/12/02

 

91%

82

bridle fabrication

35 days

Wed 6/26/02

Mon 8/19/02

 

75%

84

float order and lead time

41 days

Wed 6/12/02

Wed 8/21/02

 

75%

85

Anchor and benthic transition design

32.08 days

Wed 8/7/02

Fri 9/20/02

 

0%

86

anchor system preliminary design

8.33 days

Wed 8/7/02

Mon 8/19/02

Erickson Jon[60%],Chaffey Mark[60%]

0%

92

Final assembly of test mooring

125 days

Wed 6/26/02

Tue 12/17/02

 

0%

93

Design and Fab. of stand-up support

20 days

Wed 6/26/02

Tue 7/23/02

Erickson Jon

0%