Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/17/02
|
ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
|
1 |
Mooring test deployment |
222 days |
Mon 2/11/02 |
Tue 12/17/02 |
|
58% |
|
2 |
power system design |
175 days |
Tue 2/12/02 |
Mon 10/14/02 |
Mellinger Ed[45%] |
59% |
|
4 |
power system wiring detailed design |
16.67 days |
Wed 6/26/02 |
Fri 8/9/02 |
Mellinger Ed[60%] |
80% |
|
5 |
power system distribution board schematic |
16.67 days |
Fri 8/9/02 |
Mon 9/2/02 |
Mellinger Ed[60%] |
0% |
|
6 |
power system connectors on order |
14.29 days |
Fri 8/9/02 |
Thu 8/29/02 |
Mellinger Ed[7%] |
0% |
|
7 |
power system housing specification/design |
5 days |
Thu 4/25/02 |
Wed 8/7/02 |
Mellinger Ed[60%] |
75% |
|
8 |
power system housing fabrication |
15 days |
Fri 8/9/02 |
Fri 8/30/02 |
shop[75%] |
0% |
|
9 |
Battery system 10W |
120.83 days |
Fri 2/22/02 |
Mon 8/12/02 |
|
94% |
|
13 |
fabricate and wire battery housing |
8.33 days |
Mon 7/1/02 |
Mon 8/12/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
70% |
|
14 |
Solar power system |
127 days |
Tue 2/12/02 |
Wed 8/7/02 |
|
98% |
|
16 |
design panel mounts and tower access |
5 days |
Fri 2/22/02 |
Wed 8/7/02 |
Mellinger Ed[60%],Erickson Jon[60%] |
80% |
|
21 |
Wind power system |
125.33 days |
Thu 3/7/02 |
Thu 8/29/02 |
|
71% |
|
27 |
assemble complete wind system and test |
14 days |
Fri 8/9/02 |
Thu 8/29/02 |
Mellinger Ed[50%] |
0% |
|
28 |
Power system CDR |
0 days |
Fri 8/9/02 |
Fri 8/9/02 |
|
0% |
|
31 |
controller and RF communications |
164.27 days |
Mon 2/11/02 |
Fri 9/27/02 |
|
59% |
|
41 |
controller housing and chassis specification/design |
6 days |
Tue 3/26/02 |
Wed 8/7/02 |
Chaffey Mark[10%],McBride Lance[60%] |
90% |
|
42 |
temporary controller on order/fab |
20 days |
Tue 5/21/02 |
Mon 6/17/02 |
|
95% |
|
43 |
fiber test card design |
20 days |
Thu 6/20/02 |
Tue 8/13/02 |
Scott Jensen[20%] |
75% |
|
44 |
fiber test card fabrication and test |
15 days |
Wed 8/14/02 |
Tue 9/3/02 |
Scott Jensen[20%],Duane Thompson[40%] |
0% |
|
45 |
controller housing fabrication |
20 days |
Wed 8/7/02 |
Wed 9/4/02 |
|
0% |
|
46 |
RF transcievers hosusing design and fab. |
15 days |
Wed 8/7/02 |
Tue 8/27/02 |
Erickson Jon[10%],McBride Lance[10%] |
0% |
|
47 |
compass driver software complete |
5 days |
Wed 8/7/02 |
Tue 8/13/02 |
SE[50%] |
0% |
|
48 |
heave sensor software driver |
15 days |
Fri 7/26/02 |
Fri 8/16/02 |
Rich Henthorn |
50% |
|
49 |
globalstar modem software driver |
15 days |
Wed 8/7/02 |
Tue 8/27/02 |
Tim Meese[50%] |
0% |
|
50 |
Z-Star sampling software driver |
15 days |
Tue 6/25/02 |
Mon 8/12/02 |
Mike Risi |
75% |
|
52 |
Test mooring riser cable system |
162.4 days |
Mon 2/11/02 |
Wed 9/25/02 |
|
66% |
|
55 |
riser cable termination socket design |
8.33 days |
Fri 4/19/02 |
Thu 8/15/02 |
Chaffey Mark[60%],Erickson Jon[60%] |
20% |
|
56 |
riser cable termination socket fabrication |
10 days |
Thu 8/15/02 |
Thu 8/29/02 |
shop[75%] |
0% |
|
58 |
specify riser cable floats |
4 days |
Tue 6/25/02 |
Wed 8/7/02 |
Chaffey Mark |
90% |
|
59 |
riser cable floats on order |
35 days |
Wed 8/7/02 |
Wed 9/25/02 |
|
0% |
|
60 |
snubber hose system |
186.08 days |
Mon 2/11/02 |
Tue 10/29/02 |
|
62% |
|
67 |
snubber hose fabrication |
40 days |
Tue 6/25/02 |
Mon 8/19/02 |
|
80% |
|
68 |
bridle/snubber/anchor strain gage on order |
57 days |
Wed 6/12/02 |
Thu 8/29/02 |
Erickson Jon[60%] |
72% |
|
69 |
coilcord core cable fabrication |
35 days |
Mon 4/1/02 |
Mon 8/12/02 |
|
90% |
|
70 |
coilcord fabrication |
35 days |
Fri 5/24/02 |
Tue 9/17/02 |
|
25% |
|
71 |
snubber electo-optical connectors delivery time |
90 days |
Tue 4/2/02 |
Mon 8/5/02 |
|
68% |
|
72 |
bending strain relief specified |
3 days |
Tue 6/25/02 |
Wed 8/7/02 |
Erickson Jon[60%] |
75% |
|
73 |
bending strain relief delivery time |
50 days |
Wed 8/7/02 |
Wed 10/16/02 |
|
0% |
|
75 |
Surface buoy design |
136.25 days |
Tue 2/12/02 |
Wed 8/21/02 |
|
84% |
|
81 |
tower fabrication |
35 days |
Tue 6/25/02 |
Mon 8/12/02 |
|
91% |
|
82 |
bridle fabrication |
35 days |
Wed 6/26/02 |
Mon 8/19/02 |
|
75% |
|
84 |
float order and lead time |
41 days |
Wed 6/12/02 |
Wed 8/21/02 |
|
75% |
|
85 |
Anchor and benthic transition design |
32.08 days |
Wed 8/7/02 |
Fri 9/20/02 |
|
0% |
|
86 |
anchor system preliminary design |
8.33 days |
Wed 8/7/02 |
Mon 8/19/02 |
Erickson Jon[60%],Chaffey Mark[60%] |
0% |
|
92 |
Final assembly of test mooring |
125 days |
Wed 6/26/02 |
Tue 12/17/02 |
|
0% |
|
93 |
Design and Fab. of stand-up support |
20 days |
Wed 6/26/02 |
Tue 7/23/02 |
Erickson Jon |
0% |