MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 56%
2
power system design
176 daysTue 2/12/02Tue 10/15/02Mellinger Ed[45%]60%
4
Battery system 10W
120.83 daysFri 2/22/02Mon 8/12/02 94%
8
fabricate and wire battery housing
8.33 daysMon 7/1/02Mon 8/12/02Mellinger Ed[60%],Erickson Jon[60%]70%
9
Solar power system
140 daysTue 2/12/02Mon 8/26/02 76%
11
design panel mounts and tower access
5 daysFri 2/22/02Wed 8/7/02Mellinger Ed[60%],Erickson Jon[60%]80%
16
solar panel mount fabrication
13 daysThu 8/8/02Mon 8/26/02shop[50%]0%
23
power system wiring detailed design
16.67 daysWed 6/26/02Fri 8/9/02Mellinger Ed[60%]92%
24
power system distribution board concept design
1 dayFri 8/9/02Mon 8/12/02 0%
25
power system distribution board schematic
16.67 daysMon 8/12/02Tue 9/3/02Mellinger Ed[60%]0%
26
power system connectors on order
14.29 daysFri 8/9/02Thu 8/29/02Mellinger Ed[7%]0%
27
power system housing specification/design
5 daysThu 4/25/02Tue 8/13/02Mellinger Ed[60%]75%
28
power system housing fabrication
15 daysTue 8/13/02Tue 9/3/02shop[75%]0%
32
controller and RF communications
164.27 daysMon 2/11/02Fri 9/27/02 55%
42
controller housing and chassis specification/design
6 daysTue 3/26/02Wed 8/7/02Chaffey Mark[10%],McBride Lance[60%]90%
43
temporary controller on order/fab
20 daysTue 5/21/02Mon 6/17/02 95%
44
fiber test card design
20 daysThu 6/20/02Tue 8/13/02Scott Jensen[20%]75%
45
fiber test card fabrication and test
15 daysWed 8/14/02Tue 9/3/02Scott Jensen[20%],Duane Thompson[40%]0%
46
controller housing and chassis fabrication
20 daysWed 8/7/02Wed 9/4/02 0%
47
RF transcievers hosusing design and fab.
15 daysWed 8/7/02Tue 8/27/02Erickson Jon[10%],McBride Lance[10%]0%
48
compass software driver
10 daysWed 8/7/02Tue 8/20/02Tom O'Reilly[50%]0%
49
heave sensor software driver
15 daysFri 7/26/02Fri 8/16/02Rich Henthorn50%
50
GPS software driver
10 daysWed 8/7/02Tue 8/20/02Kent Headley[50%]0%
51
globalstar modem software driver
15 daysWed 8/7/02Tue 8/27/02Tim Meese[50%]0%
52
Z-Star sampling software driver
15 daysTue 6/25/02Mon 8/12/02Mike Risi75%
53
SSDS instrument metadata plan
3 daysTue 8/13/02Thu 8/15/02John Graybeal[20%]0%
55
Test mooring riser cable system
162.4 daysMon 2/11/02Wed 9/25/02 66%
58
riser cable termination socket design
8.33 daysFri 4/19/02Thu 8/15/02Chaffey Mark[60%],Erickson Jon[60%]20%
59
riser cable termination socket fabrication
10 daysThu 8/15/02Thu 8/29/02shop[75%]0%
61
specify riser cable floats
4 daysTue 6/25/02Wed 8/7/02Chaffey Mark90%
62
riser cable floats on order
35 daysWed 8/7/02Wed 9/25/02 0%
63
snubber hose system
189.83 daysMon 2/11/02Fri 11/1/02 62%
70
snubber hose fabrication
40 daysTue 6/25/02Mon 8/19/02 80%
71
snubber union/instrument cage assembly design
4 daysTue 6/11/02Thu 8/15/02Erickson Jon[15%]25%
72
snubber union/instrument cage assembly fabrication
10.67 daysFri 8/16/02Fri 8/30/02shop[75%]0%
73
bridle/snubber/anchor strain gage on order
57 daysWed 6/12/02Thu 8/29/02Erickson Jon[60%]72%
74
coilcord core cable fabrication
35 daysMon 4/1/02Tue 8/13/02 90%
75
coilcord fabrication
35 daysTue 8/13/02Tue 10/1/02 0%
76
snubber electo-optical connectors delivery time
131 daysMon 4/22/02Tue 10/22/02 60%
78
bending strain relief delivery time
50 daysTue 7/9/02Tue 9/17/02 45%
80
Surface buoy design
134.75 daysTue 2/12/02Mon 8/19/02 87%
86
tower fabrication
35 daysTue 6/25/02Mon 8/12/02 91%
87
bridle fabrication
35 daysWed 6/26/02Mon 8/19/02 75%
89
float order and lead time
41 daysWed 6/12/02Fri 8/16/02 85%
90
Anchor and benthic transition design
32.08 daysWed 8/7/02Fri 9/20/02 0%
91
anchor system preliminary design
8.33 daysWed 8/7/02Mon 8/19/02Erickson Jon[60%],Chaffey Mark[60%]0%
92
anchor system PDR
0 daysMon 8/19/02Mon 8/19/02 0%
93
anchor system final design
10 daysMon 8/19/02Mon 9/2/02 0%
97
Final assembly of test mooring
85 daysWed 8/7/02Tue 12/3/02 0%
98
Design and model test mooring configuration
50 daysThu 8/8/02Wed 10/16/02Chaffey Mark[20%]0%
99
Design and Fab. of stand-up support
20 daysWed 8/7/02Tue 9/3/02Erickson Jon0%