MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 59%
2
power system design
183.2 daysTue 2/12/02Fri 10/25/02Mellinger Ed[45%]60%
4
Battery system 10W
129.17 daysFri 2/22/02Thu 8/22/02 94%
8
fabricate and wire battery housing
8.33 daysMon 7/1/02Thu 8/22/02Mellinger Ed[60%],Erickson Jon[60%]70%
9
Solar power system
148.75 daysTue 2/12/02Fri 9/6/02 76%
11
design panel mounts and tower access
5 daysFri 2/22/02Tue 8/20/02Mellinger Ed[60%],Erickson Jon[60%]85%
16
solar panel mount fabrication
13 daysTue 8/20/02Fri 9/6/02shop[50%]0%
23
power system wiring detailed design
16.67 daysWed 6/26/02Wed 8/21/02Mellinger Ed[60%]92%
24
power system distribution board concept design
1 dayFri 8/9/02Wed 8/21/02 80%
25
power system distribution board schematic
16.67 daysWed 8/21/02Fri 9/13/02Mellinger Ed[60%]0%
26
power system connectors on order
14.29 daysWed 8/21/02Tue 9/10/02Mellinger Ed[7%]0%
27
power system housing specification/design
5 daysThu 4/25/02Thu 8/22/02Mellinger Ed[60%]75%
28
power system housing fabrication
15 daysThu 8/22/02Thu 9/12/02shop[75%]0%
32
controller and RF communications
173.27 daysMon 2/11/02Thu 10/10/02 62%
42
controller housing and chassis specification/design
6 daysTue 3/26/02Tue 8/20/02Chaffey Mark[10%],McBride Lance[60%]90%
44
fiber test card design
20 daysThu 6/20/02Mon 8/26/02Scott Jensen[20%]75%
45
fiber test card fabrication and test
15 daysTue 8/27/02Mon 9/16/02Scott Jensen[20%],Duane Thompson[40%]0%
46
controller housing and chassis fabrication
20 daysTue 8/20/02Tue 9/17/02 15%
48
compass software driver
10 daysTue 8/20/02Mon 9/2/02Tom O'Reilly[50%]0%
49
heave sensor software driver
15 daysFri 7/26/02Thu 8/29/02Rich Henthorn50%
50
GPS software driver
10 daysTue 8/20/02Mon 9/2/02Kent Headley[50%]0%
51
globalstar modem software driver
15 daysTue 8/20/02Mon 9/9/02Tim Meese[50%]0%
52
Z-Star sampling software driver
15 daysTue 6/25/02Fri 8/23/02Mike Risi75%
53
SSDS instrument metadata plan
3 daysTue 8/20/02Thu 8/22/02John Graybeal[20%]0%
55
Test mooring riser cable system
171 daysMon 2/11/02Mon 10/7/02 66%
58
riser cable termination socket design
8.33 daysFri 4/19/02Wed 8/28/02Chaffey Mark[60%],Erickson Jon[60%]20%
62
riser cable floats on order
35 daysTue 8/20/02Mon 10/7/02 0%
63
snubber hose system
197.83 daysMon 2/11/02Wed 11/13/02 66%
70
snubber hose fabrication
40 daysTue 6/25/02Mon 8/19/02 80%
71
snubber union/instrument cage assembly design
4 daysTue 6/11/02Thu 8/22/02Erickson Jon[15%]25%
72
snubber union/instrument cage assembly fabrication
10.67 daysFri 8/23/02Fri 9/6/02shop[75%]0%
73
bridle/snubber/anchor strain gage on order
57 daysWed 6/12/02Thu 8/29/02Erickson Jon[60%]88%
74
coilcord core cable fabrication
35 daysMon 4/1/02Fri 8/23/02 90%
75
coilcord fabrication
35 daysFri 8/23/02Fri 10/11/02 0%
76
snubber electo-optical connectors delivery time
131 daysMon 4/22/02Fri 11/1/02 60%
78
bending strain relief delivery time
50 daysTue 7/9/02Tue 9/17/02 61%
80
Surface buoy design
142 daysTue 2/12/02Wed 8/28/02 92%
86
tower fabrication
35 daysTue 6/25/02Wed 8/21/02 95%
87
bridle fabrication
35 daysWed 6/26/02Wed 8/28/02 80%
89
float order and lead time
41 daysWed 6/12/02Thu 8/22/02 95%
90
Anchor and benthic transition design
32.08 daysTue 8/20/02Thu 10/3/02 0%
91
anchor system preliminary design
8.33 daysTue 8/20/02Fri 8/30/02Erickson Jon[60%],Chaffey Mark[60%]0%
97
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 0%
98
Design and model test mooring configuration
50 daysTue 8/20/02Mon 10/28/02Chaffey Mark[20%]0%
99
Design and Fab. of stand-up support
20 daysTue 8/20/02Mon 9/16/02Erickson Jon0%