Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 212 days | Mon 2/11/02 | Tue 12/3/02 | 66% | |
| 2 | power system design | 186.29 days | Tue 2/12/02 | Wed 10/30/02 | Mellinger Ed[45%] | 68% |
| 4 | Battery system 10W | 139.33 days | Fri 2/22/02 | Thu 9/5/02 | 96% | |
| 8 | fabricate and wire battery housing | 8.33 days | Mon 7/1/02 | Thu 9/5/02 | Mellinger Ed[60%],Erickson Jon[60%] | 80% |
| 9 | Solar power system | 159.25 days | Tue 2/12/02 | Mon 9/23/02 | 77% | |
| 11 | design panel mounts and tower access | 5 days | Fri 2/22/02 | Wed 9/4/02 | Mellinger Ed[60%],Erickson Jon[60%] | 95% |
| 16 | solar panel mount fabrication | 13 days | Wed 9/4/02 | Mon 9/23/02 | shop[50%] | 0% |
| 25 | power system distribution board schematic | 16.67 days | Wed 8/21/02 | Fri 9/13/02 | Mellinger Ed[60%] | 63% |
| 26 | power system connectors on order | 14.29 days | Thu 8/29/02 | Wed 9/18/02 | Mellinger Ed[7%] | 35% |
| 27 | power system housing specification/design | 5 days | Thu 4/25/02 | Wed 9/4/02 | Mellinger Ed[60%] | 80% |
| 28 | power system housing fabrication | 15 days | Thu 9/5/02 | Wed 9/25/02 | shop[75%] | 0% |
| 32 | controller and RF communications | 171.17 days | Mon 2/11/02 | Tue 10/8/02 | 70% | |
| 44 | fiber test card design | 20 days | Thu 6/20/02 | Mon 9/9/02 | Scott Jensen[20%] | 80% |
| 45 | fiber test card fabrication and test | 15 days | Tue 9/10/02 | Mon 9/30/02 | Scott Jensen[20%],Duane Thompson[40%] | 0% |
| 46 | controller housing and chassis fabrication | 20 days | Tue 8/20/02 | Thu 9/26/02 | 15% | |
| 48 | compass software driver | 10 days | Tue 8/20/02 | Tue 9/10/02 | Tom O'Reilly[50%] | 50% |
| 49 | heave sensor software driver | 15 days | Fri 7/26/02 | Fri 9/13/02 | Rich Henthorn | 50% |
| 50 | GPS software driver | 10 days | Tue 8/20/02 | Tue 9/10/02 | Kent Headley[50%] | 50% |
| 51 | globalstar modem software driver | 15 days | Tue 8/20/02 | Fri 9/13/02 | Tim Meese[50%] | 50% |
| 52 | Z-Star sampling software driver | 15 days | Tue 6/25/02 | Fri 9/6/02 | Mike Risi | 80% |
| 53 | SSDS instrument metadata plan | 3 days | Tue 8/20/02 | Wed 9/4/02 | John Graybeal[20%] | 75% |
| 55 | Test mooring riser cable system | 171 days | Mon 2/11/02 | Mon 10/7/02 | 73% | |
| 58 | riser cable termination socket design | 8.33 days | Fri 4/19/02 | Wed 8/28/02 | Chaffey Mark[60%],Erickson Jon[60%] | 20% |
| 59 | riser cable termination socket fabrication | 10 days | Wed 8/28/02 | Wed 9/11/02 | shop[75%] | 0% |
| 60 | terminate riser cable | 5 days | Wed 9/11/02 | Wed 9/18/02 | Chaffey Mark[60%],Etech[75%] | 0% |
| 62 | riser cable floats on order | 35 days | Tue 8/20/02 | Mon 10/7/02 | 34% | |
| 63 | snubber hose system | 189.83 days | Mon 2/11/02 | Fri 11/1/02 | 70% | |
| 70 | snubber hose fabrication | 83 days | Tue 6/25/02 | Thu 10/17/02 | 63% | |
| 71 | snubber union/instrument cage assembly design | 4 days | Tue 6/11/02 | Thu 9/5/02 | Erickson Jon[15%] | 50% |
| 72 | snubber union/instrument cage assembly fabrication | 10.67 days | Fri 9/6/02 | Fri 9/20/02 | shop[75%] | 0% |
| 73 | bridle/snubber/anchor strain gage on order | 57 days | Wed 6/12/02 | Wed 9/11/02 | Erickson Jon[60%] | 90% |
| 74 | coilcord core cable fabrication | 35 days | Mon 4/1/02 | Mon 9/9/02 | 90% | |
| 75 | coilcord fabrication | 15 days | Mon 9/9/02 | Mon 9/30/02 | 0% | |
| 76 | snubber electo-optical connectors delivery time | 131 days | Mon 4/22/02 | Tue 10/22/02 | 60% | |
| 78 | bending strain relief delivery time | 50 days | Tue 7/9/02 | Tue 9/17/02 | 83% | |
| 80 | Surface buoy design | 149.5 days | Tue 2/12/02 | Mon 9/9/02 | 97% | |
| 86 | tower fabrication | 35 days | Tue 6/25/02 | Wed 9/4/02 | 98% | |
| 87 | bridle fabrication | 35 days | Wed 6/26/02 | Mon 9/9/02 | 90% | |
| 90 | Anchor and benthic transition design | 41 days | Tue 8/20/02 | Tue 10/15/02 | 6% | |
| 91 | anchor system preliminary design | 8.33 days | Tue 8/20/02 | Thu 9/12/02 | Erickson Jon[60%],Chaffey Mark[60%] | 25% |
| 97 | Final assembly of test mooring | 76 days | Tue 8/20/02 | Tue 12/3/02 | 13% | |
| 98 | Design and model test mooring configuration | 50 days | Tue 8/20/02 | Mon 10/28/02 | Chaffey Mark[20%] | 25% |
| 99 | Design and Fab. of stand-up support | 20 days | Tue 8/20/02 | Mon 9/16/02 | Erickson Jon | 25% |