MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 66%
2
power system design
186.29 daysTue 2/12/02Wed 10/30/02Mellinger Ed[45%]68%
4
Battery system 10W
139.33 daysFri 2/22/02Thu 9/5/02 96%
8
fabricate and wire battery housing
8.33 daysMon 7/1/02Thu 9/5/02Mellinger Ed[60%],Erickson Jon[60%]80%
9
Solar power system
159.25 daysTue 2/12/02Mon 9/23/02 77%
11
design panel mounts and tower access
5 daysFri 2/22/02Wed 9/4/02Mellinger Ed[60%],Erickson Jon[60%]95%
16
solar panel mount fabrication
13 daysWed 9/4/02Mon 9/23/02shop[50%]0%
25
power system distribution board schematic
16.67 daysWed 8/21/02Fri 9/13/02Mellinger Ed[60%]63%
26
power system connectors on order
14.29 daysThu 8/29/02Wed 9/18/02Mellinger Ed[7%]35%
27
power system housing specification/design
5 daysThu 4/25/02Wed 9/4/02Mellinger Ed[60%]80%
28
power system housing fabrication
15 daysThu 9/5/02Wed 9/25/02shop[75%]0%
32
controller and RF communications
171.17 daysMon 2/11/02Tue 10/8/02 70%
44
fiber test card design
20 daysThu 6/20/02Mon 9/9/02Scott Jensen[20%]80%
45
fiber test card fabrication and test
15 daysTue 9/10/02Mon 9/30/02Scott Jensen[20%],Duane Thompson[40%]0%
46
controller housing and chassis fabrication
20 daysTue 8/20/02Thu 9/26/02 15%
48
compass software driver
10 daysTue 8/20/02Tue 9/10/02Tom O'Reilly[50%]50%
49
heave sensor software driver
15 daysFri 7/26/02Fri 9/13/02Rich Henthorn50%
50
GPS software driver
10 daysTue 8/20/02Tue 9/10/02Kent Headley[50%]50%
51
globalstar modem software driver
15 daysTue 8/20/02Fri 9/13/02Tim Meese[50%]50%
52
Z-Star sampling software driver
15 daysTue 6/25/02Fri 9/6/02Mike Risi80%
53
SSDS instrument metadata plan
3 daysTue 8/20/02Wed 9/4/02John Graybeal[20%]75%
55
Test mooring riser cable system
171 daysMon 2/11/02Mon 10/7/02 73%
58
riser cable termination socket design
8.33 daysFri 4/19/02Wed 8/28/02Chaffey Mark[60%],Erickson Jon[60%]20%
59
riser cable termination socket fabrication
10 daysWed 8/28/02Wed 9/11/02shop[75%]0%
60
terminate riser cable
5 daysWed 9/11/02Wed 9/18/02Chaffey Mark[60%],Etech[75%]0%
62
riser cable floats on order
35 daysTue 8/20/02Mon 10/7/02 34%
63
snubber hose system
189.83 daysMon 2/11/02Fri 11/1/02 70%
70
snubber hose fabrication
83 daysTue 6/25/02Thu 10/17/02 63%
71
snubber union/instrument cage assembly design
4 daysTue 6/11/02Thu 9/5/02Erickson Jon[15%]50%
72
snubber union/instrument cage assembly fabrication
10.67 daysFri 9/6/02Fri 9/20/02shop[75%]0%
73
bridle/snubber/anchor strain gage on order
57 daysWed 6/12/02Wed 9/11/02Erickson Jon[60%]90%
74
coilcord core cable fabrication
35 daysMon 4/1/02Mon 9/9/02 90%
75
coilcord fabrication
15 daysMon 9/9/02Mon 9/30/02 0%
76
snubber electo-optical connectors delivery time
131 daysMon 4/22/02Tue 10/22/02 60%
78
bending strain relief delivery time
50 daysTue 7/9/02Tue 9/17/02 83%
80
Surface buoy design
149.5 daysTue 2/12/02Mon 9/9/02 97%
86
tower fabrication
35 daysTue 6/25/02Wed 9/4/02 98%
87
bridle fabrication
35 daysWed 6/26/02Mon 9/9/02 90%
90
Anchor and benthic transition design
41 daysTue 8/20/02Tue 10/15/02 6%
91
anchor system preliminary design
8.33 daysTue 8/20/02Thu 9/12/02Erickson Jon[60%],Chaffey Mark[60%]25%
97
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 13%
98
Design and model test mooring configuration
50 daysTue 8/20/02Mon 10/28/02Chaffey Mark[20%]25%
99
Design and Fab. of stand-up support
20 daysTue 8/20/02Mon 9/16/02Erickson Jon25%