MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 80%
2
power system design
190.83 daysTue 2/12/02Tue 11/5/02Mellinger Ed[45%]86%
4
Battery system 10W
157.5 daysFri 2/22/02Tue 10/1/02 98%
8
fabricate and wire battery housing
8.33 daysMon 7/1/02Tue 10/1/02Mellinger Ed[60%],Erickson Jon[60%]90%
9
Solar power system
168.25 daysTue 2/12/02Fri 10/4/02 94%
16
solar panel mount fabrication
13 daysWed 9/4/02Fri 10/4/02shop[50%]75%
25
power system distribution board schematic
16.67 daysWed 8/21/02Tue 10/1/02Mellinger Ed[60%]95%
28
power system housing fabrication
15 daysThu 9/5/02Thu 10/3/02shop[75%]85%
29
Power system/ distribution board CDR
0 daysTue 10/1/02Tue 10/1/02 0%
30
layout and fab power system board
15 daysTue 10/1/02Tue 10/22/02Mellinger Ed[20%],Duane Thompson[80%]0%
32
controller and RF communications
171 daysMon 2/11/02Mon 10/7/02 95%
46
controller housing and chassis fabrication
20 daysTue 8/20/02Tue 10/1/02 95%
48
compass software driver
10 daysTue 8/20/02Tue 10/1/02Tom O'Reilly[50%]90%
49
heave sensor software driver
15 daysFri 7/26/02Wed 10/2/02Rich Henthorn90%
50
GPS software driver
10 daysTue 8/20/02Tue 10/1/02Kent Headley[50%]90%
51
globalstar modem software driver
15 daysTue 8/20/02Fri 10/4/02Tim Meese[50%]75%
52
Z-Star sampling software driver
15 daysTue 6/25/02Tue 10/1/02Mike Risi95%
54
temporary controller final assembly, test and software integration
16.67 daysMon 9/9/02Mon 10/7/02McBride Lance[60%]70%
55
Test mooring riser cable system
187.67 daysMon 2/11/02Wed 10/30/02 85%
58
riser cable termination socket design
8.33 daysFri 4/19/02Wed 10/9/02Chaffey Mark[60%],Erickson Jon[60%]20%
62
riser cable floats on order
35 daysTue 8/20/02Mon 10/7/02 89%
63
snubber hose system
198.83 daysMon 2/11/02Thu 11/14/02 79%
70
snubber hose fabrication
83 daysTue 6/25/02Thu 10/17/02 86%
71
snubber union/instrument cage assembly design
4 daysTue 6/11/02Tue 10/1/02Erickson Jon[15%]85%
72
snubber union/instrument cage assembly fabrication
10.67 daysTue 10/1/02Wed 10/16/02shop[75%]0%
74
coilcord core cable fabrication
35 daysMon 4/1/02Fri 10/4/02 90%
75
coilcord fabrication
6 daysFri 10/4/02Mon 10/14/02 0%
76
snubber electo-optical connectors delivery time
131 daysMon 4/22/02Mon 11/4/02 60%
90
Anchor and benthic transition design
60 daysTue 8/20/02Mon 11/11/02 6%
91
anchor system preliminary design
8.33 daysTue 8/20/02Wed 10/9/02Erickson Jon[60%],Chaffey Mark[60%]25%
97
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 40%
98
Design and model test mooring configuration
50 daysTue 8/20/02Mon 10/28/02Chaffey Mark[20%]62%
100
final assembly of surface float mechanical components
10 daysFri 9/20/02Fri 10/4/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]78%
101
Mooring stood up in highbay
0 daysFri 10/4/02Fri 10/4/02 0%
102
Wire mooring and tower
5 daysFri 10/4/02Fri 10/11/02Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson0%
106
Prepare deployment plan
10 daysTue 10/1/02Mon 10/14/02Kelley Mike[5%],Chaffey Mark[5%],Erickson Jon[5%]0%