Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 212 days | Mon 2/11/02 | Tue 12/3/02 | 85% | |
| 2 | power system design | 185.83 days | Tue 2/12/02 | Tue 10/29/02 | Mellinger Ed[45%] | 96% |
| 28 | power system housing fabrication | 15 days | Thu 9/5/02 | Wed 10/16/02 | shop[75%] | 95% |
| 30 | layout and fab power system board | 15 days | Tue 10/1/02 | Tue 10/22/02 | Mellinger Ed[20%],Duane Thompson[80%] | 70% |
| 31 | assemble solar system housing and test | 5 days | Tue 10/22/02 | Tue 10/29/02 | Mellinger Ed[50%] | 0% |
| 32 | controller and RF communications | 192.83 days | Mon 2/11/02 | Wed 11/6/02 | 96% | |
| 48 | compass software driver | 10 days | Tue 8/20/02 | Wed 10/16/02 | Tom O'Reilly[50%] | 95% |
| 49 | heave sensor software driver | 15 days | Fri 7/26/02 | Wed 10/16/02 | Rich Henthorn | 95% |
| 50 | GPS software driver | 10 days | Tue 8/20/02 | Wed 10/16/02 | Kent Headley[50%] | 95% |
| 51 | globalstar modem software driver | 15 days | Tue 8/20/02 | Thu 10/17/02 | Tim Meese[50%] | 90% |
| 52 | Z-Star sampling software driver | 15 days | Tue 6/25/02 | Wed 10/16/02 | Mike Risi | 95% |
| 54 | temporary controller final assembly, test and software integration | 16.67 days | Mon 9/9/02 | Thu 10/17/02 | McBride Lance[60%] | 90% |
| 55 | Controller and power system lab integration and test | 5 days | Tue 10/29/02 | Tue 11/5/02 | Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%] | 0% |
| 57 | Test mooring riser cable system | 200.92 days | Mon 2/11/02 | Mon 11/18/02 | 86% | |
| 60 | riser cable termination socket design | 8.33 days | Fri 4/19/02 | Fri 10/18/02 | Chaffey Mark[60%],Erickson Jon[60%] | 65% |
| 61 | riser cable termination socket fabrication | 10 days | Fri 10/18/02 | Fri 11/1/02 | shop[75%] | 0% |
| 66 | snubber hose system | 201.83 days | Mon 2/11/02 | Tue 11/19/02 | 82% | |
| 73 | snubber hose fabrication | 87.5 days | Tue 6/25/02 | Thu 10/24/02 | 94% | |
| 74 | snubber union/instrument cage assembly design | 4 days | Tue 6/11/02 | Wed 10/16/02 | Erickson Jon[15%] | 95% |
| 75 | snubber union/instrument cage assembly fabrication | 10.67 days | Wed 10/16/02 | Wed 10/30/02 | shop[75%] | 0% |
| 78 | coilcord fabrication | 6 days | Fri 10/4/02 | Thu 10/17/02 | 75% | |
| 79 | snubber electo-optical connectors delivery time | 131 days | Mon 4/22/02 | Thu 11/7/02 | 60% | |
| 93 | Anchor and benthic transition design | 68.92 days | Tue 8/20/02 | Fri 11/22/02 | 13% | |
| 94 | anchor system preliminary design | 8.33 days | Tue 8/20/02 | Tue 10/22/02 | Erickson Jon[60%],Chaffey Mark[60%] | 50% |
| 95 | anchor system PDR | 0 days | Tue 10/22/02 | Tue 10/22/02 | 0% | |
| 96 | anchor system final design | 10 days | Tue 10/22/02 | Tue 11/5/02 | 0% | |
| 100 | Final assembly of test mooring | 76 days | Tue 8/20/02 | Tue 12/3/02 | 48% | |
| 101 | Design and model test mooring configuration | 50 days | Tue 8/20/02 | Tue 11/5/02 | Chaffey Mark[20%] | 70% |
| 103 | final assembly of surface float mechanical components | 10 days | Fri 9/20/02 | Wed 10/16/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%] | 90% |
| 104 | Mooring stood up in highbay | 0 days | Wed 10/16/02 | Wed 10/16/02 | 0% | |
| 105 | Wire mooring and tower | 5 days | Thu 10/17/02 | Wed 10/23/02 | Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson | 0% |
| 106 | Fabricate power system Hoffman boxes | 1 day | Wed 10/16/02 | Wed 10/16/02 | 0% | |
| 107 | Final instrument integration and shore testing | 20 days | Tue 10/22/02 | Mon 11/18/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%] | 0% |
| 110 | Prepare deployment plan | 10 days | Wed 10/16/02 | Tue 10/29/02 | Kelley Mike[5%],Chaffey Mark[5%],Erickson Jon[5%] | 0% |