MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 85%
2
power system design
185.83 daysTue 2/12/02Tue 10/29/02Mellinger Ed[45%]96%
28
power system housing fabrication
15 daysThu 9/5/02Wed 10/16/02shop[75%]95%
30
layout and fab power system board
15 daysTue 10/1/02Tue 10/22/02Mellinger Ed[20%],Duane Thompson[80%]70%
31
assemble solar system housing and test
5 daysTue 10/22/02Tue 10/29/02Mellinger Ed[50%]0%
32
controller and RF communications
192.83 daysMon 2/11/02Wed 11/6/02 96%
48
compass software driver
10 daysTue 8/20/02Wed 10/16/02Tom O'Reilly[50%]95%
49
heave sensor software driver
15 daysFri 7/26/02Wed 10/16/02Rich Henthorn95%
50
GPS software driver
10 daysTue 8/20/02Wed 10/16/02Kent Headley[50%]95%
51
globalstar modem software driver
15 daysTue 8/20/02Thu 10/17/02Tim Meese[50%]90%
52
Z-Star sampling software driver
15 daysTue 6/25/02Wed 10/16/02Mike Risi95%
54
temporary controller final assembly, test and software integration
16.67 daysMon 9/9/02Thu 10/17/02McBride Lance[60%]90%
55
Controller and power system lab integration and test
5 daysTue 10/29/02Tue 11/5/02Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%]0%
57
Test mooring riser cable system
200.92 daysMon 2/11/02Mon 11/18/02 86%
60
riser cable termination socket design
8.33 daysFri 4/19/02Fri 10/18/02Chaffey Mark[60%],Erickson Jon[60%]65%
61
riser cable termination socket fabrication
10 daysFri 10/18/02Fri 11/1/02shop[75%]0%
66
snubber hose system
201.83 daysMon 2/11/02Tue 11/19/02 82%
73
snubber hose fabrication
87.5 daysTue 6/25/02Thu 10/24/02 94%
74
snubber union/instrument cage assembly design
4 daysTue 6/11/02Wed 10/16/02Erickson Jon[15%]95%
75
snubber union/instrument cage assembly fabrication
10.67 daysWed 10/16/02Wed 10/30/02shop[75%]0%
78
coilcord fabrication
6 daysFri 10/4/02Thu 10/17/02 75%
79
snubber electo-optical connectors delivery time
131 daysMon 4/22/02Thu 11/7/02 60%
93
Anchor and benthic transition design
68.92 daysTue 8/20/02Fri 11/22/02 13%
94
anchor system preliminary design
8.33 daysTue 8/20/02Tue 10/22/02Erickson Jon[60%],Chaffey Mark[60%]50%
95
anchor system PDR
0 daysTue 10/22/02Tue 10/22/02 0%
96
anchor system final design
10 daysTue 10/22/02Tue 11/5/02 0%
100
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 48%
101
Design and model test mooring configuration
50 daysTue 8/20/02Tue 11/5/02Chaffey Mark[20%]70%
103
final assembly of surface float mechanical components
10 daysFri 9/20/02Wed 10/16/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]90%
104
Mooring stood up in highbay
0 daysWed 10/16/02Wed 10/16/02 0%
105
Wire mooring and tower
5 daysThu 10/17/02Wed 10/23/02Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson0%
106
Fabricate power system Hoffman boxes
1 dayWed 10/16/02Wed 10/16/02 0%
107
Final instrument integration and shore testing
20 daysTue 10/22/02Mon 11/18/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%]0%
110
Prepare deployment plan
10 daysWed 10/16/02Tue 10/29/02Kelley Mike[5%],Chaffey Mark[5%],Erickson Jon[5%]0%