MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 90%
2
power system design
186.25 daysTue 2/12/02Wed 10/30/02Mellinger Ed[45%]97%
28
power system housing fabrication
15 daysThu 9/5/02Tue 10/22/02shop[75%]98%
30
layout and fab power system board
15 daysTue 10/1/02Thu 10/24/02Mellinger Ed[20%],Duane Thompson[80%]85%
31
assemble solar system housing and test
4 daysThu 10/24/02Wed 10/30/02Mellinger Ed[50%]0%
32
controller and RF communications
193.25 daysMon 2/11/02Thu 11/7/02 96%
48
compass software driver
10 daysTue 8/20/02Tue 10/22/02Tom O'Reilly[50%]95%
49
heave sensor software driver
15 daysFri 7/26/02Tue 10/22/02Rich Henthorn95%
50
GPS software driver
10 daysTue 8/20/02Tue 10/22/02Kent Headley[50%]95%
51
globalstar modem software driver
15 daysTue 8/20/02Wed 10/23/02Tim Meese[50%]90%
52
Z-Star sampling software driver
15 daysTue 6/25/02Tue 10/22/02Mike Risi95%
54
temporary controller final assembly, test and software integration
16.67 daysMon 9/9/02Wed 10/23/02McBride Lance[60%]90%
55
Controller and power system lab integration and test
5 daysWed 10/30/02Wed 11/6/02Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%]0%
56
Move controller and power housing to mooring
1 dayWed 11/6/02Thu 11/7/02Mellinger Ed[50%],McBride Lance[50%],Duane Thompson[50%]0%
57
Test mooring riser cable system
203.67 daysMon 2/11/02Thu 11/21/02 87%
60
riser cable termination socket design
8.33 daysFri 4/19/02Wed 10/23/02Chaffey Mark[60%],Erickson Jon[60%]80%
61
riser cable termination socket CDR
0 daysWed 10/23/02Wed 10/23/02 0%
62
riser cable termination socket fabrication
10 daysWed 10/23/02Wed 11/6/02shop[75%]0%
63
Test riser cable termination
6 daysWed 11/6/02Thu 11/14/02Chaffey Mark[50%]0%
67
snubber hose system
204 daysMon 2/11/02Thu 11/21/02 91%
74
snubber hose fabrication
87.5 daysTue 6/25/02Tue 10/29/02 94%
76
snubber union/instrument cage assembly fabrication
10.67 daysTue 10/22/02Tue 11/5/02shop[75%]0%
79
coilcord fabrication
6 daysTue 10/22/02Tue 10/29/02 50%
80
snubber electo-optical connectors delivery time
151.5 daysMon 4/22/02Tue 11/19/02 87%
94
Anchor and benthic transition design
63 daysTue 8/20/02Thu 11/14/02 31%
95
anchor system preliminary design
9.5 daysTue 8/20/02Thu 10/24/02Andrew Hamilton[60%],Chaffey Mark[60%]79%
96
anchor system PDR
0 daysThu 10/24/02Thu 10/24/02Andrew Hamilton[50%],Chaffey Mark[50%]0%
97
anchor system final design
3 daysFri 10/25/02Tue 10/29/02Andrew Hamilton,Erickson Jon0%
98
anchor system CDR
0 daysTue 10/29/02Tue 10/29/02Andrew Hamilton,Erickson Jon0%
99
anchor system fabricate
8 daysWed 10/30/02Fri 11/8/02shop[80%]0%
101
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 62%
102
Design and model test mooring configuration
43 daysTue 8/20/02Fri 10/25/02Andrew Hamilton[20%],Chaffey Mark[60%]93%
104
final assembly of surface float mechanical components
10 daysFri 9/20/02Wed 10/23/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]90%
105
Fabricate power system Hoffman boxes
1 dayWed 10/16/02Wed 10/23/02 90%
106
Wire mooring and tower
5 daysThu 10/17/02Tue 10/29/02Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson20%
111
Prepare deployment plan
11 daysWed 10/16/02Wed 10/30/02Kelley Mike[50%],Chaffey Mark[50%],Erickson Jon[5%],Andrew Hamilton[50%]9%