MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 91%
2
power system design
186.25 daysTue 2/12/02Wed 10/30/02Mellinger Ed[45%]99%
31
assemble power system housing and test
4 daysThu 10/24/02Wed 10/30/02Mellinger Ed[50%]90%
32
controller and RF communications
196 daysMon 2/11/02Mon 11/11/02 97%
48
compass software driver
10 daysTue 8/20/02Tue 10/22/02Tom O'Reilly[50%]98%
49
heave sensor software driver
15 daysFri 7/26/02Tue 10/22/02Rich Henthorn98%
50
GPS software driver
10 daysTue 8/20/02Tue 10/22/02Kent Headley[50%]98%
51
globalstar modem software driver
15 daysTue 8/20/02Wed 10/23/02Tim Meese[50%]98%
52
Z-Star sampling software driver
15 daysTue 6/25/02Tue 10/22/02Mike Risi98%
54
temporary controller final assembly, test and software integration
16.67 daysMon 9/9/02Wed 10/23/02McBride Lance[60%]95%
55
Controller and power system lab integration and test
4 daysTue 11/5/02Fri 11/8/02Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%]0%
56
Move controller and power housing to mooring
1 dayMon 11/11/02Mon 11/11/02Mellinger Ed[50%],McBride Lance[50%],Duane Thompson[50%]0%
57
Test mooring riser cable system
201.62 daysMon 2/11/02Tue 11/19/02 95%
62
riser cable termination socket fabrication
11 daysWed 10/23/02Wed 11/13/02shop[75%]55%
63
Test riser cable termination
2 daysWed 11/13/02Fri 11/15/02Chaffey Mark[50%]0%
64
terminate riser cable
2 daysFri 11/15/02Tue 11/19/02Chaffey Mark[60%],Etech[75%]0%
67
snubber hose system
202 daysMon 2/11/02Tue 11/19/02 88%
76
snubber union/instrument cage assembly fabrication
10.67 daysTue 10/22/02Mon 11/11/02shop[75%]60%
80
snubber electo-optical connectors delivery time
149 daysMon 4/22/02Fri 11/15/02 66%
83
snubber final assembly and test
2 daysMon 11/18/02Tue 11/19/02Chaffey Mark[60%],Mtech[60%],Erickson Jon[60%]0%
94
Anchor and benthic transition design
65.5 daysTue 8/20/02Tue 11/19/02 53%
97
anchor system final design
3 daysFri 10/25/02Wed 11/6/02Andrew Hamilton,Erickson Jon50%
98
anchor system CDR
0 daysWed 11/6/02Wed 11/6/02Andrew Hamilton,Erickson Jon0%
99
anchor system fabricate
8 daysWed 11/6/02Mon 11/18/02shop[80%]0%
100
anchor system final assembly and test
1 dayMon 11/18/02Tue 11/19/02shop[80%],unassigned EE[60%],Erickson Jon[60%]0%
101
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 61%
102
Design and model test mooring configuration
43 daysTue 8/20/02Thu 11/7/02Andrew Hamilton[20%],Chaffey Mark[60%]93%
104
final assembly of surface float mechanical components
10 daysFri 9/20/02Tue 11/5/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]95%
106
Wire mooring and tower
5 daysThu 10/17/02Tue 11/5/02Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson80%
107
Final instrument integration and shore testing
11 daysTue 11/12/02Tue 11/26/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%]0%
108
Final predeployment assembly
5 daysMon 11/18/02Fri 11/22/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]0%
111
Prepare deployment plan
20 daysWed 10/16/02Tue 11/12/02Kelley Mike[50%],Chaffey Mark[50%],Erickson Jon[5%],Andrew Hamilton[50%]5%