Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 212 days | Mon 2/11/02 | Tue 12/3/02 | 91% | |
| 2 | power system design | 186.25 days | Tue 2/12/02 | Wed 10/30/02 | Mellinger Ed[45%] | 99% |
| 31 | assemble power system housing and test | 4 days | Thu 10/24/02 | Wed 10/30/02 | Mellinger Ed[50%] | 90% |
| 32 | controller and RF communications | 196 days | Mon 2/11/02 | Mon 11/11/02 | 97% | |
| 48 | compass software driver | 10 days | Tue 8/20/02 | Tue 10/22/02 | Tom O'Reilly[50%] | 98% |
| 49 | heave sensor software driver | 15 days | Fri 7/26/02 | Tue 10/22/02 | Rich Henthorn | 98% |
| 50 | GPS software driver | 10 days | Tue 8/20/02 | Tue 10/22/02 | Kent Headley[50%] | 98% |
| 51 | globalstar modem software driver | 15 days | Tue 8/20/02 | Wed 10/23/02 | Tim Meese[50%] | 98% |
| 52 | Z-Star sampling software driver | 15 days | Tue 6/25/02 | Tue 10/22/02 | Mike Risi | 98% |
| 54 | temporary controller final assembly, test and software integration | 16.67 days | Mon 9/9/02 | Wed 10/23/02 | McBride Lance[60%] | 95% |
| 55 | Controller and power system lab integration and test | 4 days | Tue 11/5/02 | Fri 11/8/02 | Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%] | 0% |
| 56 | Move controller and power housing to mooring | 1 day | Mon 11/11/02 | Mon 11/11/02 | Mellinger Ed[50%],McBride Lance[50%],Duane Thompson[50%] | 0% |
| 57 | Test mooring riser cable system | 201.62 days | Mon 2/11/02 | Tue 11/19/02 | 95% | |
| 62 | riser cable termination socket fabrication | 11 days | Wed 10/23/02 | Wed 11/13/02 | shop[75%] | 55% |
| 63 | Test riser cable termination | 2 days | Wed 11/13/02 | Fri 11/15/02 | Chaffey Mark[50%] | 0% |
| 64 | terminate riser cable | 2 days | Fri 11/15/02 | Tue 11/19/02 | Chaffey Mark[60%],Etech[75%] | 0% |
| 67 | snubber hose system | 202 days | Mon 2/11/02 | Tue 11/19/02 | 88% | |
| 76 | snubber union/instrument cage assembly fabrication | 10.67 days | Tue 10/22/02 | Mon 11/11/02 | shop[75%] | 60% |
| 80 | snubber electo-optical connectors delivery time | 149 days | Mon 4/22/02 | Fri 11/15/02 | 66% | |
| 83 | snubber final assembly and test | 2 days | Mon 11/18/02 | Tue 11/19/02 | Chaffey Mark[60%],Mtech[60%],Erickson Jon[60%] | 0% |
| 94 | Anchor and benthic transition design | 65.5 days | Tue 8/20/02 | Tue 11/19/02 | 53% | |
| 97 | anchor system final design | 3 days | Fri 10/25/02 | Wed 11/6/02 | Andrew Hamilton,Erickson Jon | 50% |
| 98 | anchor system CDR | 0 days | Wed 11/6/02 | Wed 11/6/02 | Andrew Hamilton,Erickson Jon | 0% |
| 99 | anchor system fabricate | 8 days | Wed 11/6/02 | Mon 11/18/02 | shop[80%] | 0% |
| 100 | anchor system final assembly and test | 1 day | Mon 11/18/02 | Tue 11/19/02 | shop[80%],unassigned EE[60%],Erickson Jon[60%] | 0% |
| 101 | Final assembly of test mooring | 76 days | Tue 8/20/02 | Tue 12/3/02 | 61% | |
| 102 | Design and model test mooring configuration | 43 days | Tue 8/20/02 | Thu 11/7/02 | Andrew Hamilton[20%],Chaffey Mark[60%] | 93% |
| 104 | final assembly of surface float mechanical components | 10 days | Fri 9/20/02 | Tue 11/5/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%] | 95% |
| 106 | Wire mooring and tower | 5 days | Thu 10/17/02 | Tue 11/5/02 | Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson | 80% |
| 107 | Final instrument integration and shore testing | 11 days | Tue 11/12/02 | Tue 11/26/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%] | 0% |
| 108 | Final predeployment assembly | 5 days | Mon 11/18/02 | Fri 11/22/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%] | 0% |
| 111 | Prepare deployment plan | 20 days | Wed 10/16/02 | Tue 11/12/02 | Kelley Mike[50%],Chaffey Mark[50%],Erickson Jon[5%],Andrew Hamilton[50%] | 5% |