MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
212 daysMon 2/11/02Tue 12/3/02 97%
2
power system design
195.08 daysTue 2/12/02Tue 11/12/02Mellinger Ed[45%]99%
31
assemble power system housing and test
4 daysThu 10/24/02Tue 11/12/02Mellinger Ed[50%]98%
32
controller and RF communications
197.88 daysMon 2/11/02Wed 11/13/02 99%
48
compass software driver
10 daysTue 8/20/02Tue 10/22/02Tom O'Reilly[50%]98%
49
heave sensor software driver
15 daysFri 7/26/02Tue 10/22/02Rich Henthorn98%
50
GPS software driver
10 daysTue 8/20/02Tue 10/22/02Kent Headley[50%]98%
51
globalstar modem software driver
15 daysTue 8/20/02Wed 10/23/02Tim Meese[50%]98%
52
Z-Star sampling software driver
15 daysTue 6/25/02Tue 10/22/02Mike Risi98%
54
temporary controller final assembly, test and software integration
16.67 daysMon 9/9/02Wed 10/23/02McBride Lance[60%]95%
55
Controller and power system lab integration and test
4 daysTue 11/5/02Tue 11/12/02Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%]80%
56
Move controller and power housing to mooring
1 dayTue 11/12/02Wed 11/13/02Mellinger Ed[50%],McBride Lance[50%],Duane Thompson[50%]0%
57
Test mooring riser cable system
201.62 daysMon 2/11/02Tue 11/19/02 97%
62
riser cable termination socket fabrication
11 daysWed 10/23/02Wed 11/13/02shop[75%]94%
63
Test riser cable termination
2 daysWed 11/13/02Fri 11/15/02Chaffey Mark[50%]0%
64
terminate riser cable
2 daysFri 11/15/02Tue 11/19/02Chaffey Mark[60%],Etech[75%]0%
67
snubber hose system
202 daysMon 2/11/02Tue 11/19/02 99%
80
snubber electo-optical connectors delivery time
149.5 daysMon 4/22/02Fri 11/15/02 98%
83
snubber final assembly and test
2 daysMon 11/18/02Tue 11/19/02Chaffey Mark[60%],Mtech[60%],Erickson Jon[60%]0%
94
Anchor and benthic transition design
67.03 daysTue 8/20/02Thu 11/21/02 65%
97
anchor system final design
3 daysFri 10/25/02Tue 11/12/02Andrew Hamilton,Erickson Jon99%
98
anchor system CDR
0 daysTue 11/12/02Tue 11/12/02Andrew Hamilton,Erickson Jon0%
99
anchor system fabricate
6 daysTue 11/12/02Wed 11/20/02shop[80%]0%
100
anchor system final assembly and test
1 dayWed 11/20/02Thu 11/21/02shop[80%],unassigned EE[60%],Erickson Jon[60%]0%
101
Final assembly of test mooring
76 daysTue 8/20/02Tue 12/3/02 79%
104
final assembly of surface float mechanical components
10 daysFri 9/20/02Tue 11/12/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]99%
106
Wire mooring and tower
5 daysThu 10/17/02Tue 11/12/02Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson90%
107
Final instrument integration and shore testing
8 daysWed 11/13/02Mon 11/25/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%]0%
108
Final predeployment assembly
5 daysMon 11/18/02Fri 11/22/02Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%]0%
109
Final system checkout
5 daysMon 11/25/02Fri 11/29/02Chaffey Mark[60%],Mellinger Ed,Erickson Jon,Tim Meese,Tom O'Reilly,Kent Headley0%
110
load mooring system on Point Sur
1 dayMon 12/2/02Mon 12/2/02Chaffey Mark,Erickson Jon,Mellinger Ed,observatrory support0%
111
Prepare deployment plan
25 daysWed 10/16/02Tue 11/19/02Kelley Mike[50%],Chaffey Mark[50%],Erickson Jon[5%],Andrew Hamilton[50%]80%
112
Deployment of test mooring
1 dayTue 12/3/02Tue 12/3/02Erickson Jon,Chaffey Mark,observatrory support0%