Project Start Date: Tue 1/1/02
Project Finish Date: Tue 12/3/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 212 days | Mon 2/11/02 | Tue 12/3/02 | 98% | |
| 2 | power system design | 201.04 days | Tue 2/12/02 | Wed 11/20/02 | Mellinger Ed[45%] | 99% |
| 31 | assemble power system housing and test | 4 days | Thu 10/24/02 | Wed 11/20/02 | Mellinger Ed[50%] | 99% |
| 32 | controller and RF communications | 203.84 days | Mon 2/11/02 | Thu 11/21/02 | 99% | |
| 55 | Controller and power system lab integration and test | 4 days | Tue 11/5/02 | Wed 11/20/02 | Mellinger Ed[50%],Duane Thompson[50%],McBride Lance[50%],Kent Headley[25%] | 95% |
| 56 | Move controller and power housing to mooring | 1 day | Wed 11/20/02 | Thu 11/21/02 | Mellinger Ed[50%],McBride Lance[50%],Duane Thompson[50%] | 0% |
| 57 | Test mooring riser cable system | 204.2 days | Mon 2/11/02 | Fri 11/22/02 | 99% | |
| 63 | Test riser cable termination | 2 days | Wed 11/13/02 | Wed 11/20/02 | Chaffey Mark[50%] | 90% |
| 64 | terminate riser cable | 2 days | Wed 11/20/02 | Fri 11/22/02 | Chaffey Mark[60%],Etech[75%] | 20% |
| 67 | snubber hose system | 204 days | Mon 2/11/02 | Thu 11/21/02 | 99% | |
| 83 | snubber final assembly and test | 2 days | Wed 11/20/02 | Thu 11/21/02 | Chaffey Mark[60%],Mtech[60%],Erickson Jon[60%] | 0% |
| 94 | Anchor and benthic transition design | 67.5 days | Tue 8/20/02 | Thu 11/21/02 | 91% | |
| 99 | anchor system fabricate | 2 days | Tue 11/12/02 | Wed 11/20/02 | shop[80%] | 75% |
| 100 | anchor system final assembly and test | 1 day | Wed 11/20/02 | Thu 11/21/02 | shop[80%],unassigned EE[60%],Erickson Jon[60%] | 0% |
| 101 | Final assembly of test mooring | 76 days | Tue 8/20/02 | Tue 12/3/02 | 86% | |
| 106 | Wire mooring and tower | 5 days | Thu 10/17/02 | Wed 11/20/02 | Chaffey Mark[60%],Kelley Mike,Mellinger Ed,observatrory support,Etech[75%],Duane Thompson | 99% |
| 107 | Final instrument integration and shore testing | 2 days | Thu 11/21/02 | Mon 11/25/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[75%],Mtech[80%],shop[75%] | 0% |
| 108 | Final predeployment assembly | 5 days | Fri 11/22/02 | Fri 11/29/02 | Chaffey Mark[60%],Erickson Jon[60%],Mellinger Ed[60%],observatrory support[200%],Etech[80%],Mtech[80%],shop[80%] | 0% |
| 109 | Deployment readyness review | 0 days | Mon 11/25/02 | Mon 11/25/02 | 0% | |
| 110 | Final system checkout | 5 days | Mon 11/25/02 | Fri 11/29/02 | Chaffey Mark[60%],Mellinger Ed,Erickson Jon,Tim Meese,Tom O'Reilly,Kent Headley | 0% |
| 111 | load mooring system on Point Sur | 1 day | Mon 12/2/02 | Mon 12/2/02 | Chaffey Mark,Erickson Jon,Mellinger Ed,observatrory support | 0% |
| 112 | Prepare deployment plan | 26.25 days | Wed 10/16/02 | Thu 11/21/02 | Kelley Mike[50%],Chaffey Mark[50%],Erickson Jon[5%],Andrew Hamilton[50%] | 90% |
| 113 | Deployment of test mooring | 1 day | Tue 12/3/02 | Tue 12/3/02 | Erickson Jon,Chaffey Mark,observatrory support | 0% |