MOOS mooring system


Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
Mooring test deployment
140.67 daysMon 2/11/02Mon 8/26/02 10%
2
power system design
87.33 daysTue 2/12/02Thu 6/13/02Mellinger Ed[60%]25%
3
power system prelim. design & diagram
8.33 daysTue 2/12/02Wed 3/13/02Mellinger Ed[60%]60%
4
Battery system 10W
79 daysFri 2/22/02Thu 6/13/02 41%
7
battery housing size, design and locate
10 daysWed 3/6/02Wed 3/20/02Mellinger Ed[60%],Erickson Jon[60%]60%
10
Solar power system
77 daysTue 2/12/02Wed 5/29/02 17%
12
design panel mounts and tower access
5 daysFri 2/22/02Mon 3/11/02Mellinger Ed[60%],Erickson Jon[60%]60%
13
specifiy and order panels
10 daysFri 3/1/02Mon 3/18/02Mellinger Ed[60%]50%
20
Wind power system
45.67 daysThu 3/7/02Thu 5/9/02 25%
22
turbine mount and access design
1 dayFri 3/8/02Fri 3/8/02Mellinger Ed[60%],Erickson Jon[60%]75%
29
controller and RF communications
90.17 daysMon 2/11/02Mon 6/17/02 12%
30
temporary controller requirements specified
8.33 daysMon 2/11/02Mon 3/11/02McBride Lance[60%]80%
31
wave/acceleration instrument specified
5 daysThu 2/28/02Thu 3/14/02Chaffey Mark[60%]10%
33
temporary controller specfied
8.33 daysMon 3/4/02Wed 3/20/02McBride Lance[60%]75%
35
CERF adapter board in fab.
7 daysMon 3/4/02Tue 3/12/02 71%
37
RF communications specified
8.33 daysMon 3/11/02Thu 3/21/02McBride Lance[60%]0%
41
Test mooring riser cable system
108 daysMon 2/11/02Wed 7/10/02 14%
42
selection of riser cable vendor
20 daysMon 2/11/02Wed 3/13/02Chaffey Mark[60%],Mellinger Ed[10%]80%
47
snubber hose system
140.67 daysMon 2/11/02Mon 8/26/02 5%
48
coil cord specified
5 daysMon 2/11/02Mon 3/11/02Chaffey Mark[20%],Walter Paul[50%],Mellinger Ed[10%]75%
49
snubber electro-optical connectors specified
5 daysMon 2/18/02Wed 3/13/02Chaffey Mark[60%],Mellinger Ed[10%]75%
51
bridle/snubber strain gage specified
8.33 daysThu 2/28/02Thu 3/14/02unassigned EE[60%]40%
64
Surface buoy design
69.67 daysTue 2/12/02Mon 5/20/02 7%
72
float design
5 daysMon 3/4/02Thu 3/21/02Erickson Jon[60%]70%
74
Anchor and benthic transition design
61.67 daysMon 3/11/02Tue 6/4/02 0%
75
anchor system preliminary design
8.33 daysMon 3/11/02Thu 3/21/02Erickson Jon[60%],Chaffey Mark[60%]0%