Project Start Date: Tue 1/1/02
Project Finish Date: Mon 8/26/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Mooring test deployment | 140.67 days | Mon 2/11/02 | Mon 8/26/02 | 10% | |
| 2 | power system design | 87.33 days | Tue 2/12/02 | Thu 6/13/02 | Mellinger Ed[60%] | 25% |
| 3 | power system prelim. design & diagram | 8.33 days | Tue 2/12/02 | Wed 3/13/02 | Mellinger Ed[60%] | 60% |
| 4 | Battery system 10W | 79 days | Fri 2/22/02 | Thu 6/13/02 | 41% | |
| 7 | battery housing size, design and locate | 10 days | Wed 3/6/02 | Wed 3/20/02 | Mellinger Ed[60%],Erickson Jon[60%] | 60% |
| 10 | Solar power system | 77 days | Tue 2/12/02 | Wed 5/29/02 | 17% | |
| 12 | design panel mounts and tower access | 5 days | Fri 2/22/02 | Mon 3/11/02 | Mellinger Ed[60%],Erickson Jon[60%] | 60% |
| 13 | specifiy and order panels | 10 days | Fri 3/1/02 | Mon 3/18/02 | Mellinger Ed[60%] | 50% |
| 20 | Wind power system | 45.67 days | Thu 3/7/02 | Thu 5/9/02 | 25% | |
| 22 | turbine mount and access design | 1 day | Fri 3/8/02 | Fri 3/8/02 | Mellinger Ed[60%],Erickson Jon[60%] | 75% |
| 29 | controller and RF communications | 90.17 days | Mon 2/11/02 | Mon 6/17/02 | 12% | |
| 30 | temporary controller requirements specified | 8.33 days | Mon 2/11/02 | Mon 3/11/02 | McBride Lance[60%] | 80% |
| 31 | wave/acceleration instrument specified | 5 days | Thu 2/28/02 | Thu 3/14/02 | Chaffey Mark[60%] | 10% |
| 33 | temporary controller specfied | 8.33 days | Mon 3/4/02 | Wed 3/20/02 | McBride Lance[60%] | 75% |
| 35 | CERF adapter board in fab. | 7 days | Mon 3/4/02 | Tue 3/12/02 | 71% | |
| 37 | RF communications specified | 8.33 days | Mon 3/11/02 | Thu 3/21/02 | McBride Lance[60%] | 0% |
| 41 | Test mooring riser cable system | 108 days | Mon 2/11/02 | Wed 7/10/02 | 14% | |
| 42 | selection of riser cable vendor | 20 days | Mon 2/11/02 | Wed 3/13/02 | Chaffey Mark[60%],Mellinger Ed[10%] | 80% |
| 47 | snubber hose system | 140.67 days | Mon 2/11/02 | Mon 8/26/02 | 5% | |
| 48 | coil cord specified | 5 days | Mon 2/11/02 | Mon 3/11/02 | Chaffey Mark[20%],Walter Paul[50%],Mellinger Ed[10%] | 75% |
| 49 | snubber electro-optical connectors specified | 5 days | Mon 2/18/02 | Wed 3/13/02 | Chaffey Mark[60%],Mellinger Ed[10%] | 75% |
| 51 | bridle/snubber strain gage specified | 8.33 days | Thu 2/28/02 | Thu 3/14/02 | unassigned EE[60%] | 40% |
| 64 | Surface buoy design | 69.67 days | Tue 2/12/02 | Mon 5/20/02 | 7% | |
| 72 | float design | 5 days | Mon 3/4/02 | Thu 3/21/02 | Erickson Jon[60%] | 70% |
| 74 | Anchor and benthic transition design | 61.67 days | Mon 3/11/02 | Tue 6/4/02 | 0% | |
| 75 | anchor system preliminary design | 8.33 days | Mon 3/11/02 | Thu 3/21/02 | Erickson Jon[60%],Chaffey Mark[60%] | 0% |