MOOS Mooring MSE Deployment_1


Project Start Date: Wed 1/5/05
Project Finish Date: Fri 12/30/05

Tasks

ID
Task Name
DurationStartFinishRemaining Slack% CompleteResource
1
MOOS mooring project management
260 daysMon 1/3/05Fri 12/30/050 days20%Mark Chaffey[50%]
2
MTM3 deployment
73.33 daysMon 1/24/05Thu 5/5/05-15.83 days32% 
4
MTM3 Analog isolation PCB (load cell)
16.67 daysMon 1/24/05Fri 3/11/050 days60%Ed Mellinger[60%],Jose Rosal,Tom Marion
5
MTM3 Analog isolation software driver
5 daysTue 2/15/05Thu 3/17/050 days50%Ed Mellinger[60%],Mike Risi[60%]
6
MTM3 power system final build and test
13.33 daysTue 3/15/05Fri 4/1/05-17.33 days0%Ed Mellinger[60%],Tom Marion[75%]
7
MTM3 assemble and lab test controller
28.8 daysMon 2/7/05Thu 3/17/050 days15%Mark Chaffey[50%],Lance McBride[50%]
8
Order, receive and install second optical channel
28.8 daysMon 2/7/05Thu 3/17/050 days15%Lance McBride[7%]
13
MTM3 fabricate instrument mounts
19 daysWed 2/9/05Tue 3/15/051.05 days95%Johnny Ferrira[20%]
20
Test winch level-wind hardware
2 daysTue 3/15/05Wed 3/16/0513 days0%Johnny Ferrira,Andrew Hamilton
26
MTM4 Major System Milestones
109 daysThu 2/3/05Wed 7/6/058.33 days16% 
28
MTM4 Draft of overall system topology
10 daysMon 2/7/05Thu 3/3/050 days90%Mark Chaffey[40%],John Ryan,Jim Barry,Charlie Paull
29
Instrument list under change control
0 daysTue 3/1/05Tue 3/1/0519.08 days0%Mark Chaffey[60%]
30
MTM4 Power budget
20 daysThu 3/17/05Wed 4/13/058.33 days0%Ed Mellinger[10%]
31
Fix number of BINs and topological layout
0 daysFri 3/4/05Fri 3/4/0520.33 days0%Mark Chaffey[60%]
32
Final revisions of instrument list
26 daysFri 3/4/05Fri 4/8/0511.33 days35%Mark Chaffey[4%],John Ryan[2%],Jim Barry[2%],Charlie Paull[2%]
36
MTM4 MMC and surface instrument wiring
91.25 daysWed 3/2/05Thu 7/7/058.08 days2% 
37
MTM4 Complete MMC configuration drawings
7 daysWed 3/2/05Thu 3/24/058.08 days25%Lance McBride[60%]
42
MTM4 Medusa PCB
86 daysMon 1/24/05Mon 5/23/0540.33 days48% 
44
Medusa ver. 2 parts procurement
20 daysTue 2/8/05Mon 3/21/0540.33 days85%Wayne Radochonski[20%]
48
Medusa ver. 2 board fabrication and stuff
20 daysTue 3/22/05Mon 4/18/0540.33 days0%Wayne Radochonski[10%]
53
Medusa power management testing
3.33 daysThu 3/17/05Tue 3/22/0575 days0%Tim Meese[60%]
54
Medusa test port mirroring/failover support
8.33 daysThu 3/17/05Tue 3/29/0570 days0%Tim Meese[60%]
55
Medusa SPI communications support
13.33 daysThu 3/17/05Tue 4/5/0565 days0%Tim Meese[60%]
58
MTM4 MMC Software upgrades
123 daysThu 3/17/05Mon 9/5/0584 days0% 
59
MMC software, Verify watchdog function
2 daysThu 3/17/05Fri 3/18/055 days0%Tim Meese[60%]
67
MTM4 power system
109.67 daysMon 2/28/05Fri 7/29/05110.33 days4% 
68
Revise P2 PCB for MMC rev. 2 backplane
10 daysMon 2/28/05Mon 3/21/0514.33 days70%Ed Mellinger[60%],Tom Marion
70
Design modifications 48-12 converter
16.67 daysTue 3/22/05Wed 4/13/0514.33 days0%Ed Mellinger[60%],Jose Rosal,Tom Marion
73
Micropower 400-12 module design
33.33 daysMon 3/21/05Thu 5/5/0553 days0%Ed Mellinger[60%],Jose Rosal,Tom Marion
76
MTM4 BINS
139.33 daysMon 1/24/05Fri 8/5/053.67 days14% 
80
MTM BIN order and receive instrument penetrators/cables
65 daysThu 3/17/05Wed 6/15/0531 days0%Mark Chaffey[7%],Jon Erickson[3%]
81
MTM4 BIN sphere fabrication
85 daysMon 3/7/05Fri 7/1/053.67 days9%Jon Erickson[2%]
88
MTM4 Benthic cable assemblies
100.25 daysFri 3/4/05Fri 7/22/0513.75 days1% 
89
Specify Benthic interconnect cable and connectors
5 daysFri 3/4/05Wed 3/23/0513.75 days15%Mark Chaffey[60%]
90
Order Benthic cable and connectors
0 daysWed 3/23/05Wed 3/23/0513.75 days0% 
91
Fabricate Benthic cable and connectors
72 daysWed 3/23/05Fri 7/1/0513.75 days0%Mark Chaffey[1%]
93
MTM4 Riser cable assembly
151 daysFri 2/4/05Fri 9/2/0537 days4% 
97
MTM4 confirm riser cable specifications and JDR purchase agreement
25 daysWed 2/23/05Wed 3/30/0541.67 days23%Andrew Hamilton[20%]
102
MTM4 configuration modeling
13.33 daysFri 2/4/05Wed 2/23/0534.67 days0%Andrew Hamilton[60%]
103
MTM4 float clamp redesign
40 daysWed 2/23/05Wed 4/20/0526.67 days20%Andrew Hamilton[20%]
104
MTM4 float bending strain relief redesign spec. to CRP
4 daysWed 2/23/05Tue 3/1/0562.67 days0%Andrew Hamilton[50%]
105
MTM4 cable stop clamp design
11.67 daysThu 2/24/05Fri 3/11/0554.33 days0%Andrew Hamilton[60%]
106
MTM4 bottom termination redesign
25 daysFri 3/11/05Thu 4/14/0530 days0%Andrew Hamilton[60%],Mark Brown[60%]
116
MTM4 Snubber assembly
159.67 daysFri 2/4/05Thu 9/15/056.33 days1% 
123
MTM4 fabricate coilcord cable
30 daysThu 3/17/05Wed 4/27/056.33 days0%Mark Chaffey[3%]
137
Deployment and installation planning
103.33 daysMon 3/14/05Thu 8/4/0535.67 days0% 
138
Tank test of ROV Mateable & BIN (Ventana)
2 daysMon 3/14/05Tue 3/15/05127.84 days0%Mark Chaffey,Johnny Ferrira[200%]