Project Start Date: Wed 1/5/05
Project Finish Date: Fri 12/30/05
| ID | Task Name | Duration | Start | Finish | Remaining Slack | % Complete | Resource |
|---|---|---|---|---|---|---|---|
| 1 | MOOS mooring project management | 260 days | Mon 1/3/05 | Fri 12/30/05 | 0 days | 20% | Mark Chaffey[50%] |
| 2 | MTM3 deployment | 73.33 days | Mon 1/24/05 | Thu 5/5/05 | -15.83 days | 32% | |
| 4 | MTM3 Analog isolation PCB (load cell) | 16.67 days | Mon 1/24/05 | Fri 3/11/05 | 0 days | 60% | Ed Mellinger[60%],Jose Rosal,Tom Marion |
| 5 | MTM3 Analog isolation software driver | 5 days | Tue 2/15/05 | Thu 3/17/05 | 0 days | 50% | Ed Mellinger[60%],Mike Risi[60%] |
| 6 | MTM3 power system final build and test | 13.33 days | Tue 3/15/05 | Fri 4/1/05 | -17.33 days | 0% | Ed Mellinger[60%],Tom Marion[75%] |
| 7 | MTM3 assemble and lab test controller | 28.8 days | Mon 2/7/05 | Thu 3/17/05 | 0 days | 15% | Mark Chaffey[50%],Lance McBride[50%] |
| 8 | Order, receive and install second optical channel | 28.8 days | Mon 2/7/05 | Thu 3/17/05 | 0 days | 15% | Lance McBride[7%] |
| 13 | MTM3 fabricate instrument mounts | 19 days | Wed 2/9/05 | Tue 3/15/05 | 1.05 days | 95% | Johnny Ferrira[20%] |
| 20 | Test winch level-wind hardware | 2 days | Tue 3/15/05 | Wed 3/16/05 | 13 days | 0% | Johnny Ferrira,Andrew Hamilton |
| 26 | MTM4 Major System Milestones | 109 days | Thu 2/3/05 | Wed 7/6/05 | 8.33 days | 16% | |
| 28 | MTM4 Draft of overall system topology | 10 days | Mon 2/7/05 | Thu 3/3/05 | 0 days | 90% | Mark Chaffey[40%],John Ryan,Jim Barry,Charlie Paull |
| 29 | Instrument list under change control | 0 days | Tue 3/1/05 | Tue 3/1/05 | 19.08 days | 0% | Mark Chaffey[60%] |
| 30 | MTM4 Power budget | 20 days | Thu 3/17/05 | Wed 4/13/05 | 8.33 days | 0% | Ed Mellinger[10%] |
| 31 | Fix number of BINs and topological layout | 0 days | Fri 3/4/05 | Fri 3/4/05 | 20.33 days | 0% | Mark Chaffey[60%] |
| 32 | Final revisions of instrument list | 26 days | Fri 3/4/05 | Fri 4/8/05 | 11.33 days | 35% | Mark Chaffey[4%],John Ryan[2%],Jim Barry[2%],Charlie Paull[2%] |
| 36 | MTM4 MMC and surface instrument wiring | 91.25 days | Wed 3/2/05 | Thu 7/7/05 | 8.08 days | 2% | |
| 37 | MTM4 Complete MMC configuration drawings | 7 days | Wed 3/2/05 | Thu 3/24/05 | 8.08 days | 25% | Lance McBride[60%] |
| 42 | MTM4 Medusa PCB | 86 days | Mon 1/24/05 | Mon 5/23/05 | 40.33 days | 48% | |
| 44 | Medusa ver. 2 parts procurement | 20 days | Tue 2/8/05 | Mon 3/21/05 | 40.33 days | 85% | Wayne Radochonski[20%] |
| 48 | Medusa ver. 2 board fabrication and stuff | 20 days | Tue 3/22/05 | Mon 4/18/05 | 40.33 days | 0% | Wayne Radochonski[10%] |
| 53 | Medusa power management testing | 3.33 days | Thu 3/17/05 | Tue 3/22/05 | 75 days | 0% | Tim Meese[60%] |
| 54 | Medusa test port mirroring/failover support | 8.33 days | Thu 3/17/05 | Tue 3/29/05 | 70 days | 0% | Tim Meese[60%] |
| 55 | Medusa SPI communications support | 13.33 days | Thu 3/17/05 | Tue 4/5/05 | 65 days | 0% | Tim Meese[60%] |
| 58 | MTM4 MMC Software upgrades | 123 days | Thu 3/17/05 | Mon 9/5/05 | 84 days | 0% | |
| 59 | MMC software, Verify watchdog function | 2 days | Thu 3/17/05 | Fri 3/18/05 | 5 days | 0% | Tim Meese[60%] |
| 67 | MTM4 power system | 109.67 days | Mon 2/28/05 | Fri 7/29/05 | 110.33 days | 4% | |
| 68 | Revise P2 PCB for MMC rev. 2 backplane | 10 days | Mon 2/28/05 | Mon 3/21/05 | 14.33 days | 70% | Ed Mellinger[60%],Tom Marion |
| 70 | Design modifications 48-12 converter | 16.67 days | Tue 3/22/05 | Wed 4/13/05 | 14.33 days | 0% | Ed Mellinger[60%],Jose Rosal,Tom Marion |
| 73 | Micropower 400-12 module design | 33.33 days | Mon 3/21/05 | Thu 5/5/05 | 53 days | 0% | Ed Mellinger[60%],Jose Rosal,Tom Marion |
| 76 | MTM4 BINS | 139.33 days | Mon 1/24/05 | Fri 8/5/05 | 3.67 days | 14% | |
| 80 | MTM BIN order and receive instrument penetrators/cables | 65 days | Thu 3/17/05 | Wed 6/15/05 | 31 days | 0% | Mark Chaffey[7%],Jon Erickson[3%] |
| 81 | MTM4 BIN sphere fabrication | 85 days | Mon 3/7/05 | Fri 7/1/05 | 3.67 days | 9% | Jon Erickson[2%] |
| 88 | MTM4 Benthic cable assemblies | 100.25 days | Fri 3/4/05 | Fri 7/22/05 | 13.75 days | 1% | |
| 89 | Specify Benthic interconnect cable and connectors | 5 days | Fri 3/4/05 | Wed 3/23/05 | 13.75 days | 15% | Mark Chaffey[60%] |
| 90 | Order Benthic cable and connectors | 0 days | Wed 3/23/05 | Wed 3/23/05 | 13.75 days | 0% | |
| 91 | Fabricate Benthic cable and connectors | 72 days | Wed 3/23/05 | Fri 7/1/05 | 13.75 days | 0% | Mark Chaffey[1%] |
| 93 | MTM4 Riser cable assembly | 151 days | Fri 2/4/05 | Fri 9/2/05 | 37 days | 4% | |
| 97 | MTM4 confirm riser cable specifications and JDR purchase agreement | 25 days | Wed 2/23/05 | Wed 3/30/05 | 41.67 days | 23% | Andrew Hamilton[20%] |
| 102 | MTM4 configuration modeling | 13.33 days | Fri 2/4/05 | Wed 2/23/05 | 34.67 days | 0% | Andrew Hamilton[60%] |
| 103 | MTM4 float clamp redesign | 40 days | Wed 2/23/05 | Wed 4/20/05 | 26.67 days | 20% | Andrew Hamilton[20%] |
| 104 | MTM4 float bending strain relief redesign spec. to CRP | 4 days | Wed 2/23/05 | Tue 3/1/05 | 62.67 days | 0% | Andrew Hamilton[50%] |
| 105 | MTM4 cable stop clamp design | 11.67 days | Thu 2/24/05 | Fri 3/11/05 | 54.33 days | 0% | Andrew Hamilton[60%] |
| 106 | MTM4 bottom termination redesign | 25 days | Fri 3/11/05 | Thu 4/14/05 | 30 days | 0% | Andrew Hamilton[60%],Mark Brown[60%] |
| 116 | MTM4 Snubber assembly | 159.67 days | Fri 2/4/05 | Thu 9/15/05 | 6.33 days | 1% | |
| 123 | MTM4 fabricate coilcord cable | 30 days | Thu 3/17/05 | Wed 4/27/05 | 6.33 days | 0% | Mark Chaffey[3%] |
| 137 | Deployment and installation planning | 103.33 days | Mon 3/14/05 | Thu 8/4/05 | 35.67 days | 0% | |
| 138 | Tank test of ROV Mateable & BIN (Ventana) | 2 days | Mon 3/14/05 | Tue 3/15/05 | 127.84 days | 0% | Mark Chaffey,Johnny Ferrira[200%] |