Project Start Date: Wed 1/5/05
Project Finish Date: Fri 12/29/06
| ID | Task Name | Duration | Start | Finish | Remaining Slack | % Complete | Resource |
|---|---|---|---|---|---|---|---|
| 1 | MOOS mooring project management | 520 days | Mon 1/3/05 | Fri 12/29/06 | 0 days | 42% | Mark Chaffey[50%] |
| 26 | MTM4 Major System Milestones | 276 days? | Thu 2/3/05 | Fri 2/24/06 | -7 days? | 65% | |
| 30 | MTM4 Power budget | 108 days | Wed 5/4/05 | Fri 12/9/05 | 48 days | 80% | Ed Mellinger[10%] |
| 34 | MTM4 order and receive instrumentation | 150 days? | Mon 8/1/05 | Fri 2/24/06 | -60.33 days? | 46% | Mark Chaffey,John Ryan,Lance McBride |
| 35 | Satlantic HyperSpectral Radiometers | 52 days? | Thu 12/15/05 | Fri 2/24/06 | -60.33 days? | 0% | |
| 36 | Satlantic/MBARI ISUS | 53 days? | Thu 11/10/05 | Mon 1/23/06 | -36.33 days? | 0% | |
| 37 | WetLabs Flourometer/backscatter | 55.59 days? | Fri 8/5/05 | Mon 11/21/05 | 8.89 days? | 95% | |
| 38 | SBE 37MCTD | 52 days | Thu 12/15/05 | Fri 2/24/06 | -60.33 days | 0% | |
| 42 | MTM4 MMC and surface instrument wiring | 206 days? | Wed 3/2/05 | Wed 12/14/05 | 8.67 days? | 76% | |
| 47 | MTM4 Mold PUCKs and test | 5 days | Thu 11/17/05 | Wed 11/23/05 | 6.67 days | 0% | Lance McBride,Jim Scholfield |
| 48 | MTM4 build up spare MMC housing | 20 days? | Thu 11/17/05 | Wed 12/14/05 | 8.67 days? | 0% | Lance McBride[60%],Tom Marion[50%] |
| 49 | MTM4 Medusa PCB | 216.17 days | Mon 1/24/05 | Tue 11/22/05 | 8.5 days | 90% | |
| 60 | Medusa power management testing | 7 days | Wed 5/4/05 | Thu 11/17/05 | 8.58 days | 29% | Bob Herlien[60%] |
| 61 | Medusa test port mirroring/failover support | 8.33 days | Thu 3/17/05 | Thu 11/17/05 | 8.5 days | 35% | Bob Herlien[60%] |
| 62 | Medusa diagnostic data serial interface port | 13.33 days | Wed 5/4/05 | Thu 11/10/05 | 13.25 days | 95% | Bob Herlien[60%] |
| 64 | Medusa full function testing with SIAM | 11 days | Mon 5/23/05 | Tue 11/22/05 | 8.5 days | 75% | Bob Herlien[60%],Mark Chaffey[60%],Wayne Radochonski[60%] |
| 65 | MTM4 MMC Software upgrades | 279.33 days | Wed 1/5/05 | Tue 1/31/06 | 246.67 days | 39% | |
| 68 | MMC software, clock distribution application | 33.33 days | Thu 12/15/05 | Tue 1/31/06 | -41.66 days | 0% | Bob Herlien[60%] |
| 69 | MMC software, Compass turns counter testing and upgrade | 11.67 days | Wed 1/5/05 | Thu 1/20/05 | 514.33 days | 0% | Tim Meese[60%] |
| 70 | MMC software, upgrade Linux OS | 55 days | Tue 6/7/05 | Fri 12/9/05 | 263.08 days | 75% | Tim Meese[60%] |
| 71 | MMC software, test SIAM against OS software upgrades | 20 days | Fri 12/9/05 | Fri 1/6/06 | 263.08 days | 0% | Tim Meese[60%],Tom O'Reilly[60%] |
| 72 | MTM4 power system | 242.67 days? | Mon 2/28/05 | Wed 2/1/06 | 245.33 days? | 49% | |
| 73 | Revise P2 PCB for MMC rev. 2 backplane | 10 days | Mon 2/28/05 | Fri 12/16/05 | 0.67 days | 95% | Ed Mellinger[60%],Tom Marion |
| 74 | Design modifications 48-12 converter | 16.67 days | Wed 8/3/05 | Mon 11/28/05 | 16.17 days | 25% | Ed Mellinger[60%],Jose Rosal,Tom Marion |
| 75 | Design modifications 48-400 converter | 16.67 days? | Mon 11/7/05 | Wed 12/21/05 | -0.5 days? | 75% | Ed Mellinger[60%] |
| 76 | Complete assembly of spare power cans | 18.67 days | Wed 5/4/05 | Wed 12/21/05 | -3.33 days | 75% | Jim Scholfield[75%],Tom Marion[75%],Ed Mellinger[10%] |
| 77 | Design modifications, 400-12 w/switch | 30 days | Sun 5/29/05 | Mon 1/9/06 | -26 days | 40% | Ed Mellinger[60%],Jose Rosal[75%],Tom Marion |
| 78 | 400 Volt switch P2 driver | 16.67 days | Tue 12/20/05 | Wed 1/11/06 | -16.33 days | 0% | Ed Mellinger[60%],Mike Risi[60%] |
| 79 | MTM4 recycle MTM2 power components and test | 20 days | Mon 5/9/05 | Thu 11/10/05 | 304 days | 95% | Ed Mellinger[60%],Tom Marion[75%] |
| 81 | MTM4 BINS | 284 days | Mon 1/24/05 | Thu 2/23/06 | -9 days | 80% | |
| 85 | MTM4 BIN order and receive instrument cable stock | 40 days | Mon 11/14/05 | Fri 1/6/06 | 5 days | 58% | |
| 86 | MTM BIN order and receive instrument penetrators/cables | 67 days | Thu 11/10/05 | Fri 2/10/06 | -42.33 days | 37% | Mark Chaffey[7%],Jon Erickson[3%] |
| 92 | MTM4 BIN first assembly | 3.33 days | Thu 10/6/05 | Thu 10/20/05 | 39.17 days | 85% | Jon Erickson[60%],Johnny Ferrira |
| 94 | MTM4 Benthic cable assemblies | 293 days? | Fri 3/4/05 | Fri 4/14/06 | 191 days? | 38% | |
| 97 | Fabricate Benthic interconnect optical cable spare | 92 days? | Thu 8/11/05 | Fri 12/16/05 | 28 days? | 98% | |
| 98 | Specify Benthic optical cable connector spares | 1 day? | Thu 12/15/05 | Thu 12/15/05 | -44 days? | 0% | |
| 99 | Order Benthic optical cable connectors | 1 day | Fri 12/16/05 | Fri 12/16/05 | -44 days | 0% | |
| 100 | Fabricate Benthic optical cable connector spares | 72 days | Mon 12/19/05 | Tue 3/28/06 | -44 days | 0% | Mark Chaffey[1%] |
| 102 | MTM4 specify copper Benthic instrument cable | 1 day | Thu 12/15/05 | Thu 12/15/05 | -52.33 days | 0% | Mark Chaffey[50%] |
| 103 | MTM4 Fabricate copper Benthic instrument cable | 50 days | Fri 12/16/05 | Thu 2/23/06 | -52.33 days | 0% | Mark Chaffey[1%] |
| 104 | MTM4 Order copper UW mateable connectors | 1 day? | Fri 12/16/05 | Fri 12/16/05 | 278 days? | 0% | |
| 106 | MTM4 Riser cable assembly | 295.25 days | Fri 2/4/05 | Fri 3/24/06 | 208.75 days | 57% | |
| 114 | MTM4 Cable build | 35 days | Thu 11/10/05 | Wed 12/28/05 | -7 days | 71% | Andrew Hamilton[3%] |
| 118 | MTM4 float clamp redesign | 40 days | Wed 2/23/05 | Wed 12/7/05 | 285 days | 63% | Andrew Hamilton[20%] |
| 119 | MTM4 float bending strain relief redesign spec. to CRP | 4 days | Thu 11/10/05 | Mon 11/21/05 | 297 days | 25% | Andrew Hamilton[50%] |
| 120 | MTM4 cable stop clamp design | 8.33 days | Thu 11/10/05 | Fri 11/25/05 | 293.75 days | 25% | Andrew Hamilton[60%] |
| 121 | MTM4 bottom termination redesign | 25 days | Fri 3/11/05 | Fri 12/23/05 | -26.25 days | 75% | Andrew Hamilton[60%],Mark Brown[60%] |
| 123 | MTM4 linksyn fabrication | 40 days | Mon 12/5/05 | Fri 1/27/06 | 2 days | 0% | Andrew Hamilton[1%] |
| 124 | MTM4 float clamp fabrication | 50 days | Mon 12/5/05 | Fri 2/10/06 | -8 days | 0% | Andrew Hamilton[4%] |
| 130 | MTM4 Snubber assembly | 295.3 days? | Fri 2/4/05 | Fri 3/24/06 | -16.3 days? | 58% | |
| 135 | MTM4 fabricate snubber hose | 105 days | Mon 7/18/05 | Fri 12/9/05 | 37.33 days | 84% | Mark Chaffey[2%] |
| 138 | MTM4 fabricate coilcord | 20.63 days | Thu 12/15/05 | Thu 1/12/06 | -5.63 days | 0% | Mark Chaffey[8%] |
| 139 | MTM4 Terminate coilcord with optical connectors | 86 days | Wed 11/2/05 | Thu 3/9/06 | -26.3 days | 13% | Mark Chaffey[2%] |
| 142 | MTM4 20 meter MMC housing fabrication | 10 days? | Thu 8/25/05 | Fri 12/16/05 | -14.33 days? | 80% | Machine shop |
| 143 | MTM4 20 meter MMC assemble chassis and wire | 4 days? | Mon 12/19/05 | Thu 12/22/05 | -14.33 days? | 0% | Jim Scholfield[75%] |
| 144 | MTM4 20 meter MMC housing order and receive optical connectors | 62 days | Thu 11/17/05 | Fri 2/10/06 | -7.67 days | 0% | Mark Chaffey[60%] |
| 146 | MTM4 Surface float final mechanical assembly | 263.33 days | Sun 5/8/05 | Fri 5/5/06 | -60.33 days | 37% | |
| 149 | MTM4 Install high efficiency solar panels and batteries | 4 days | Thu 12/15/05 | Tue 12/20/05 | 22.67 days | 0% | Johnny Ferrira[50%],Jim Scholfield[50%] |
| 150 | MTM4 Assemble tower on float | 2 days | Wed 12/21/05 | Thu 12/22/05 | 22.67 days | 0% | Johnny Ferrira |
| 156 | Deployment and installation planning | 190 days | Mon 5/2/05 | Fri 1/20/06 | 17 days | 20% | |
| 157 | First draft buoy deployment plan | 5 days | Mon 5/2/05 | Mon 11/21/05 | 59.33 days | 40% | Mark Chaffey[60%],Andrew Hamilton |
| 160 | First draft benthic installation plan | 5 days | Fri 6/3/05 | Mon 11/21/05 | 0.5 days | 50% | Mark Chaffey[60%],Andrew Hamilton |
| 161 | Installation planning meeting with Tiburon group | 0.83 days | Tue 11/22/05 | Tue 11/22/05 | 0 days | 0% | Mark Chaffey[60%],Andrew Hamilton,Jon Erickson,Johnny Ferrira,Dale Graves,Buck Reynolds,Charlie Paull[60%] |
| 171 | MSE System deployment | 202 days? | Tue 10/18/05 | Fri 7/14/06 | 120 days? | 16% |