MOOSMooringMTM4rev08_06_05


Project Start Date: Wed 1/5/05
Project Finish Date: Tue 1/2/07

Tasks

ID
Task Name
DurationStartFinishRemaining Slack% CompleteResource
1
MOOS mooring project management
521 daysMon 1/3/05Tue 1/2/070 days89%Mark Chaffey[50%]
68
MTM4 SIAM/MMC Software upgrades
405.05 days?Tue 4/12/05Wed 10/18/0654.95 days?89% 
73
MMC RTC, calibrate RTC register
1 dayThu 6/15/06Thu 6/15/06146 days0% 
76
MMC Revise Aquadopp summarizer
1 day?Wed 9/13/06Wed 10/18/062.95 days?95%Tom O'Reilly[60%],Brian Schlining
77
MMC Revise RDI ADCP sampling mode
1 day?Wed 9/13/06Wed 10/18/062.95 days?95%Tom O'Reilly[60%],Karen Salamy
79
MMC/SIAM Revise on-board archive system
1 day?Thu 10/12/06Thu 10/12/066 days?0%Kent Headley
80
MMC/SIAM Upgrade config -t for ext-3 filesystem
1 day?Thu 10/12/06Thu 10/12/066 days?0%Kent Headley,Brian Kieft
81
MMC/SIAM Revise BIN backup power policy
1 day?Wed 9/27/06Wed 10/18/062.95 days?95%Kent Headley,Brian Kieft
82
MTM4 power system
437.25 days?Mon 2/28/05Wed 10/18/062.25 days?99% 
96
MTM4 fabricate and test 3 BIN power systems
5 daysWed 5/10/06Wed 10/18/062.25 days95%Ed Mellinger[60%],Tom Marion[75%]
112
MTM4 Benthic cable assemblies
463 days?Fri 3/4/05Tue 11/28/0625 days?85% 
119
Fabricate replacement Benthic optical cable
52.5 daysFri 8/11/06Fri 10/20/060.5 days95% 
120
Terminate Benthic optical cable spare
3 daysMon 10/23/06Wed 10/25/060 days0%Mark Chaffey[13%]
122
MTM4 Fabricate copper Benthic instrument cable
20 daysWed 10/18/06Tue 11/14/0625 days0%Mark Chaffey[1%],Larry Bird[2%]
123
MTM4 Benthic instrument cable schematic
1 day?Wed 10/18/06Wed 10/18/0649 days?0%Mark Chaffey[60%]
171
MTM4 System final integration and testing
417.67 days?Sun 5/8/05Thu 11/30/0623.33 days?93% 
194
BIN - Digital still camera
33.33 daysWed 2/8/06Thu 11/30/0623.33 days5%Mark Chaffey[60%]
195
BIN Install/Check batteries in ADCP's, SBE16 and Wetlabs
1 day?Wed 10/18/06Wed 10/18/062.5 days?0%Mark Chaffey[60%],Dick Littlefield[75%]
206
BIN Final assembly of SHELF BIN II
1 day?Wed 10/18/06Wed 10/18/062.5 days?0%Mark Chaffey[60%]
207
BIN receive connectors from ODI
0.5 daysThu 10/19/06Thu 10/19/062 days0% 
208
BIN build up AXIS BIN
5 daysFri 10/6/06Thu 10/19/062 days50%Mark Chaffey[60%]
209
Axis and Shelf BIN Instrument readiness review
0.5 daysMon 10/23/06Mon 10/23/060 days0%Tom O'Reilly[60%]
210
Phase II Closed housing testing
2 daysMon 10/23/06Wed 10/25/060 days0% 
211
Phase II 24 hour Wet/Cold soak
0.5 daysWed 10/25/06Wed 10/25/060 days0%Mark Chaffey[60%]
212
Phase II Final dockside testing
1 day?Thu 10/26/06Thu 10/26/060 days?0%Mark Chaffey[60%]
251
Phase two benthic installation
9 days?Fri 10/27/06Wed 11/8/0639 days?0% 
252
WF mobilization
1 dayFri 10/27/06Fri 10/27/060 days0%Western Flyer,Mark Chaffey[60%],Larry Bird[75%],Johnny Ferrira[75%]
253
WF transit
1 dayMon 10/30/06Mon 10/30/060 days0%Western Flyer
254
Lay cable from SHELF BIN to AXIS BIN
1 dayTue 10/31/06Tue 10/31/0639 days0% 
260
MSE maintain mooring and instrument system
236 days?Tue 1/17/06Wed 11/29/0624 days?33%Mark Chaffey[20%],Andrew Hamilton[7%],Ed Mellinger[12%],Tom O'Reilly[5%],Jon Erickson[3%],Tim Meese[5%]
262
Recover McLane profiler
1 day?Tue 1/17/06Tue 1/17/06259 days?0% 
263
Wester Flyer maint. Cruise
2 daysMon 10/16/06Tue 10/17/060 days0% 
265
Surface maint/data download - Zephyer period 2
2 daysMon 9/18/06Tue 9/19/060 days0%Zephyer