Project Start Date: Wed 1/5/05
Project Finish Date: Tue 1/2/07
| ID | Task Name | Duration | Start | Finish | Remaining Slack | % Complete | Resource |
|---|---|---|---|---|---|---|---|
| 1 | MOOS mooring project management | 521 days | Mon 1/3/05 | Tue 1/2/07 | 0 days | 89% | Mark Chaffey[50%] |
| 68 | MTM4 SIAM/MMC Software upgrades | 405.05 days? | Tue 4/12/05 | Wed 10/18/06 | 54.95 days? | 89% | |
| 73 | MMC RTC, calibrate RTC register | 1 day | Thu 6/15/06 | Thu 6/15/06 | 146 days | 0% | |
| 76 | MMC Revise Aquadopp summarizer | 1 day? | Wed 9/13/06 | Wed 10/18/06 | 2.95 days? | 95% | Tom O'Reilly[60%],Brian Schlining |
| 77 | MMC Revise RDI ADCP sampling mode | 1 day? | Wed 9/13/06 | Wed 10/18/06 | 2.95 days? | 95% | Tom O'Reilly[60%],Karen Salamy |
| 79 | MMC/SIAM Revise on-board archive system | 1 day? | Thu 10/12/06 | Thu 10/12/06 | 6 days? | 0% | Kent Headley |
| 80 | MMC/SIAM Upgrade config -t for ext-3 filesystem | 1 day? | Thu 10/12/06 | Thu 10/12/06 | 6 days? | 0% | Kent Headley,Brian Kieft |
| 81 | MMC/SIAM Revise BIN backup power policy | 1 day? | Wed 9/27/06 | Wed 10/18/06 | 2.95 days? | 95% | Kent Headley,Brian Kieft |
| 82 | MTM4 power system | 437.25 days? | Mon 2/28/05 | Wed 10/18/06 | 2.25 days? | 99% | |
| 96 | MTM4 fabricate and test 3 BIN power systems | 5 days | Wed 5/10/06 | Wed 10/18/06 | 2.25 days | 95% | Ed Mellinger[60%],Tom Marion[75%] |
| 112 | MTM4 Benthic cable assemblies | 463 days? | Fri 3/4/05 | Tue 11/28/06 | 25 days? | 85% | |
| 119 | Fabricate replacement Benthic optical cable | 52.5 days | Fri 8/11/06 | Fri 10/20/06 | 0.5 days | 95% | |
| 120 | Terminate Benthic optical cable spare | 3 days | Mon 10/23/06 | Wed 10/25/06 | 0 days | 0% | Mark Chaffey[13%] |
| 122 | MTM4 Fabricate copper Benthic instrument cable | 20 days | Wed 10/18/06 | Tue 11/14/06 | 25 days | 0% | Mark Chaffey[1%],Larry Bird[2%] |
| 123 | MTM4 Benthic instrument cable schematic | 1 day? | Wed 10/18/06 | Wed 10/18/06 | 49 days? | 0% | Mark Chaffey[60%] |
| 171 | MTM4 System final integration and testing | 417.67 days? | Sun 5/8/05 | Thu 11/30/06 | 23.33 days? | 93% | |
| 194 | BIN - Digital still camera | 33.33 days | Wed 2/8/06 | Thu 11/30/06 | 23.33 days | 5% | Mark Chaffey[60%] |
| 195 | BIN Install/Check batteries in ADCP's, SBE16 and Wetlabs | 1 day? | Wed 10/18/06 | Wed 10/18/06 | 2.5 days? | 0% | Mark Chaffey[60%],Dick Littlefield[75%] |
| 206 | BIN Final assembly of SHELF BIN II | 1 day? | Wed 10/18/06 | Wed 10/18/06 | 2.5 days? | 0% | Mark Chaffey[60%] |
| 207 | BIN receive connectors from ODI | 0.5 days | Thu 10/19/06 | Thu 10/19/06 | 2 days | 0% | |
| 208 | BIN build up AXIS BIN | 5 days | Fri 10/6/06 | Thu 10/19/06 | 2 days | 50% | Mark Chaffey[60%] |
| 209 | Axis and Shelf BIN Instrument readiness review | 0.5 days | Mon 10/23/06 | Mon 10/23/06 | 0 days | 0% | Tom O'Reilly[60%] |
| 210 | Phase II Closed housing testing | 2 days | Mon 10/23/06 | Wed 10/25/06 | 0 days | 0% | |
| 211 | Phase II 24 hour Wet/Cold soak | 0.5 days | Wed 10/25/06 | Wed 10/25/06 | 0 days | 0% | Mark Chaffey[60%] |
| 212 | Phase II Final dockside testing | 1 day? | Thu 10/26/06 | Thu 10/26/06 | 0 days? | 0% | Mark Chaffey[60%] |
| 251 | Phase two benthic installation | 9 days? | Fri 10/27/06 | Wed 11/8/06 | 39 days? | 0% | |
| 252 | WF mobilization | 1 day | Fri 10/27/06 | Fri 10/27/06 | 0 days | 0% | Western Flyer,Mark Chaffey[60%],Larry Bird[75%],Johnny Ferrira[75%] |
| 253 | WF transit | 1 day | Mon 10/30/06 | Mon 10/30/06 | 0 days | 0% | Western Flyer |
| 254 | Lay cable from SHELF BIN to AXIS BIN | 1 day | Tue 10/31/06 | Tue 10/31/06 | 39 days | 0% | |
| 260 | MSE maintain mooring and instrument system | 236 days? | Tue 1/17/06 | Wed 11/29/06 | 24 days? | 33% | Mark Chaffey[20%],Andrew Hamilton[7%],Ed Mellinger[12%],Tom O'Reilly[5%],Jon Erickson[3%],Tim Meese[5%] |
| 262 | Recover McLane profiler | 1 day? | Tue 1/17/06 | Tue 1/17/06 | 259 days? | 0% | |
| 263 | Wester Flyer maint. Cruise | 2 days | Mon 10/16/06 | Tue 10/17/06 | 0 days | 0% | |
| 265 | Surface maint/data download - Zephyer period 2 | 2 days | Mon 9/18/06 | Tue 9/19/06 | 0 days | 0% | Zephyer |