MOOSMooringMTM4


Project Start Date: Tue 1/2/07
Project Finish Date: Mon 12/31/07

Tasks

ID
Task Name
DurationStartFinishRemaining Slack% CompleteResource
1
MOOS mooring project management
260 daysTue 1/2/07Mon 12/31/070 days3%Mark Chaffey[55%]
2
Monitor power data, respond to contingencies
254 days?Tue 1/9/07Fri 12/28/071 day?1%Ed Mellinger[3%]
3
Highest priority tasks (PRI 1)
61.67 days?Tue 1/9/07Wed 4/4/07193.33 days?0% 
4
Telemetry system improvements
38.33 days?Tue 1/9/07Fri 3/2/07216.67 days?0% 
5
Telemetery-diagnose and analyze current performance (PRI 1)
13.33 days?Tue 1/9/07Fri 1/26/07216.67 days?0%Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%],Brian Kieft[60%]
6
Telemetery-review bug fixes and architecural mods (PRI 1)
8.33 days?Fri 1/26/07Wed 2/7/07216.67 days?0%Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%]
7
Telemetery-implement and test modifications (PRI 1)
16.67 days?Wed 2/7/07Fri 3/2/07216.67 days?0%Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%]
8
Seahorse deployment
25 days?Mon 1/22/07Fri 2/23/0723.33 days?0% 
9
Seahorse, test instrument service (PRI 1)
12.5 days?Mon 1/22/07Wed 2/7/0723.33 days?0%Kent Headley[40%],Andrew Hamilton[60%],Karen Salamy[60%]
10
Seahorse integration and final test
12.5 days?Wed 2/7/07Fri 2/23/0723.33 days?0%Kent Headley[40%],Andrew Hamilton[60%],Karen Salamy[60%]
11
McLane deployment
22.67 days?Mon 2/26/07Wed 3/28/070.67 days?0% 
12
McLane, test instrument service (PRI 1)
8.33 days?Mon 2/26/07Thu 3/8/0710 days?0%Brian Kieft[60%],Andrew Hamilton[60%],Karen Salamy
13
McLane, recover for labtest & turnaround (PRI 1)
1.67 days?Tue 3/20/07Wed 3/21/070.67 days?0%Andrew Hamilton[60%]
14
McLane, integration and final test (PRI 1)
5 daysWed 3/21/07Wed 3/28/070.67 days0%Brian Kieft[60%],Andrew Hamilton[60%],Karen Salamy[60%]
15
SSDS processing for profiling tools (PRI 1)
16.67 days?Mon 1/22/07Tue 3/20/0718.67 days?0%Kevin Gomes[60%],John Graybeal[60%],Mike McCann[60%]
16
Cable Laying drum
46.67 days?Tue 1/30/07Wed 4/4/0711 days?0% 
17
Receive benthic test cable (PRI 1)
0 daysTue 1/30/07Tue 1/30/0711 days0% 
18
McLane cable lay testing (PRI 1)
6.67 days?Tue 1/30/07Wed 2/7/0711 days?0%Larry Bird[75%],Mark Chaffey[60%]
19
Order and receive final benthic cable (PRI 1)
40 daysWed 2/7/07Wed 4/4/0711 days0%Mark Chaffey[3%]
20
Zephyr maintenance trip (PRI 1)
1 dayMon 3/19/07Mon 3/19/070 days0%Mark Chaffey,OSG[200%]
21
SHELF BIN final integration and test (PRI 1)
12 daysWed 3/28/07Fri 4/13/070.67 days0%Mark Chaffey[60%],Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%],Bob Herlien[60%],Karen Salamy[60%]
22
SHELF BIN instrument readiness review (PRI 1)
3.33 daysFri 4/13/07Wed 4/18/070.67 days0%Mark Chaffey[60%],Tom O'Reilly[60%],Kent Headley[40%],Brian Kieft[60%],Karen Salamy
23
SHELF BIN swap final staging (PRI 1)
3.33 days?Thu 4/19/07Tue 4/24/070.67 days?0%Mark Chaffey[60%],Andrew Hamilton[60%],Larry Bird[75%],Johnny Ferrira[75%]
24
SHELF BIN swap deployment (PRI 1)
5 daysWed 4/25/07Tue 5/1/070 days0%Mark Chaffey,Brian Kieft,Larry Bird,Andrew Hamilton
25
Zephyr maintenance trip (PRI 1)
1 dayTue 6/26/07Tue 6/26/07134 days0%Mark Chaffey,OSG[200%]
26
MBARI ethernet camera integration
165 days?Mon 1/22/07Fri 9/7/0746.67 days?0% 
27
Digital camera PDR level review of design (PRI 1)
35 daysMon 1/22/07Fri 3/9/07121.67 days0%Mark Chaffey[60%],Tom O'Reilly[60%]
28
Digital camera SIAM instrument service (PRI 1)
30 days?Mon 6/25/07Fri 8/3/0746.67 days?0%Tom O'Reilly[60%],Karen Salamy[60%]
29
Digital camera integration and test (PRI 1)
18 daysMon 8/13/07Wed 9/5/0748.67 days0%Mark Chaffey[60%],Tom O'Reilly[60%],Johnny Ferrira[75%],Larry Bird[75%],Karen Salamy[60%]
30
SSDS interfaces for digital camera data (PRI 1)
25 days?Mon 8/6/07Fri 9/7/0746.67 days?0%Kevin Gomes[60%]
31
Ken Smith camera integration
80 days?Sun 5/20/07Sun 9/9/0746.67 days?0% 
32
Smith camera - McGill evaluation (PRI 1)
0 days?Sun 5/20/07Sun 5/20/07125.83 days?0%Paul McGill[50%]
33
Smith camera PDR review (PRI 1)
0.83 days?Tue 7/17/07Tue 7/17/0784.83 days?0%Tom O'Reilly[60%],Mark Chaffey[60%]
34
Smith camera SIAM Instrument service (PRI 1)
0 daysSun 9/9/07Sun 9/9/0746.67 days0%Tom O'Reilly[3%]
35
AXIS BIN final integration and test (PRI 1)
12 daysMon 10/15/07Tue 10/30/0721.67 days0%Mark Chaffey[60%],Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%],Karen Salamy[60%]
36
AXIS BIN instrument readiness review (PRI 1)
2 days?Wed 10/31/07Thu 11/1/0721.67 days?0%Tom O'Reilly[60%],Karen Salamy,Mark Chaffey[60%],Brian Kieft[60%]
37
AXIS BIN swap final staging (PRI 1)
3.33 days?Mon 11/12/07Thu 11/15/0715.67 days?0%Mark Chaffey[60%],Andrew Hamilton[60%],Larry Bird[75%],Johnny Ferrira[75%]
38
Zephyr maintenance trip (PRI 1)
1 dayTue 12/4/07Tue 12/4/0719 days0%Mark Chaffey,OSG
39
AXIS BIN swap deployment (PRI 1)
5 daysFri 12/7/07Thu 12/13/070 days0%Mark Chaffey,Tom O'Reilly,Brian Kieft
40
Secondary priority tasks (PRI 2)
209 days?Tue 1/9/07Fri 10/26/0746 days?0% 
41
Portal configuration script (PRI 2)
3.33 days?Mon 7/2/07Thu 7/5/07127.67 days?0%Brian Kieft[60%],Kent Headley[40%]
42
Portal GUI (PRI 2)
8.33 days?Mon 7/16/07Thu 7/26/07112.67 days?0%Bob Herlien[60%]
43
SIAM Node configuration tool (PRI 2)
8.33 days?Mon 7/30/07Thu 8/9/07102.67 days?0%Kent Headley[40%],Brian Kieft[60%]
44
PUCK configuration tool upgrade (PRI 2)
16.67 days?Mon 8/20/07Tue 9/11/0779.33 days?0%Tom O'Reilly[60%],Andrew Chase,Karen Salamy[60%]
45
Documentation for SIAM users (PRI 2)
10 days?Mon 10/8/07Fri 10/19/0751 days?0%Karen Salamy[60%],Tom O'Reilly[60%]
46
Documentation for SIAM programmers (PRI 2)
10 days?Mon 10/15/07Fri 10/26/0746 days?0%Karen Salamy[60%],Tom O'Reilly[60%]
47
WIFI communications for rapid data downloading (PRI 2)
8.33 days?Mon 7/30/07Thu 8/9/07102.67 days?0%Mark Chaffey[60%],Bob Herlien[60%],Etech[75%]
48
Improve onboard data archiving for higher data volumes (PRI 2)
25 days?Mon 7/2/07Fri 8/3/07106 days?0%Brian Kieft[60%]
49
SIAM, refine interface with SSDS (PRI 2)
3.33 days?Wed 7/11/07Mon 7/16/07120.67 days?0%Tom O'Reilly[60%],Kevin Gomes[60%]
50
SSDS Query dev. for access to MSE data (PRI 2)
15 days?Tue 7/17/07Mon 8/6/07105 days?0%Kevin Gomes[60%]
51
Telemetry-Implement dual modem architecture (PRI 2)
16.67 days?Mon 8/13/07Tue 9/4/0784.33 days?0%Tom O'Reilly[60%],Kent Headley[40%],Bob Herlien[60%],Brian Kieft[60%]
52
Telemetry-Install high gain antenna (PRI 2)
3.33 days?Mon 2/19/07Thu 2/22/0716.67 days?0%Mark Chaffey[60%],Johnny Ferrira[75%]
53
MOOS mooring system paper (PRI 2)
11.67 days?Thu 6/28/07Sun 7/15/070 days?0%Mark Chaffey[60%]
54
MOOS mooring system presentation (PRI 2)
5 days?Mon 9/17/07Fri 9/21/075 days?0%Mark Chaffey[60%]
55
SIAM Oceans paper (PRI 2)
17.5 days?Wed 6/20/07Sun 7/15/070 days?0%Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%]
56
SIAM Oceans presentation (PRI 2)
7.5 days?Mon 9/17/07Wed 9/26/072.5 days?0%Tom O'Reilly[60%],Brian Kieft[60%]
57
Power System oceans paper (PRI 2)
11.67 days?Thu 6/28/07Sun 7/15/070 days?0%Ed Mellinger[60%]
58
Power System presentation (PRI 2)
5 days?Mon 9/17/07Fri 9/21/075 days?0%Ed Mellinger[60%]
59
Oceans 2007 (PRI 2)
4 daysSat 9/29/07Thu 10/4/070 days0%Mark Chaffey,Ed Mellinger,Tom O'Reilly,Brian Kieft
60
Fabricate spare MTM4 anchor (PRI 2)
2 days?Tue 1/9/07Wed 1/10/07253 days?0%Andrew Hamilton[60%],Frank Flores
61
Third priority tasks (PRI 3)
145 days?Mon 6/11/07Fri 12/28/071 day?0% 
62
Linux Kernel source configuration (PRI 3)
5 days?Mon 10/15/07Fri 10/19/0751 days?0%SE unassigned
63
SideARM Coma mode bug (PRI 3)
5 days?Mon 10/22/07Fri 10/26/0746 days?0%SE unassigned
64
SideARM Serial over-run bug (PRI 3)
5 days?Mon 10/29/07Fri 11/2/0741 days?0%SE unassigned
65
Jump to boot loader on console transition bug (PRI 3)
6.67 days?Mon 11/5/07Tue 11/13/0734.33 days?0%SE unassigned[60%]
66
Medusa diagnostics (GUI) (PRI 3)
10 days?Mon 11/19/07Fri 11/30/0721 days?0%SE unassigned[60%]
67
Medusa failover on link status (PRI 3)
10 days?Mon 11/19/07Fri 11/30/0721 days?0%SE unassigned[60%]
68
Revise BIN 400-12 Switch board (PRI 3)
66.67 days?Mon 6/11/07Tue 9/11/0779.33 days?0%Ed Mellinger[60%],SE unassigned[60%],Etech[75%]
69
Replace Solar MPPT unit (PRI 3)
33.33 days?Mon 10/1/07Thu 11/15/0732.67 days?0%Ed Mellinger[60%],SE unassigned[60%],Jon Erickson[60%],Machine shop,Tom Marion[75%]
70
Modify Converter/GF Board (PRI 3)
33.33 days?Mon 11/12/07Thu 12/27/072.67 days?0%Ed Mellinger[60%],SE unassigned[60%],Etech[75%]
71
Power system status (GUI) (PRI 3)
5 days?Mon 12/24/07Fri 12/28/071 day?0%EE unassigned[60%],Ed Mellinger[60%]
72
Dummy task
0 days?Thu 1/11/07Thu 1/11/07253 days?0%Mark Chaffey[60%],Andrew Hamilton[60%],Ed Mellinger[60%],Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%],Brian Kieft[60%],Kevin Gomes[60%]