Project Start Date: Tue 1/2/07
Project Finish Date: Mon 12/31/07
| ID | Task Name | Duration | Start | Finish | Remaining Slack | % Complete | Resource |
|---|---|---|---|---|---|---|---|
| 1 | MOOS mooring project management | 260 days | Tue 1/2/07 | Mon 12/31/07 | 0 days | 3% | Mark Chaffey[55%] |
| 2 | Monitor power data, respond to contingencies | 254 days? | Tue 1/9/07 | Fri 12/28/07 | 1 day? | 1% | Ed Mellinger[3%] |
| 3 | Highest priority tasks (PRI 1) | 61.67 days? | Tue 1/9/07 | Wed 4/4/07 | 193.33 days? | 0% | |
| 4 | Telemetry system improvements | 38.33 days? | Tue 1/9/07 | Fri 3/2/07 | 216.67 days? | 0% | |
| 5 | Telemetery-diagnose and analyze current performance (PRI 1) | 13.33 days? | Tue 1/9/07 | Fri 1/26/07 | 216.67 days? | 0% | Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%],Brian Kieft[60%] |
| 6 | Telemetery-review bug fixes and architecural mods (PRI 1) | 8.33 days? | Fri 1/26/07 | Wed 2/7/07 | 216.67 days? | 0% | Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%] |
| 7 | Telemetery-implement and test modifications (PRI 1) | 16.67 days? | Wed 2/7/07 | Fri 3/2/07 | 216.67 days? | 0% | Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%] |
| 8 | Seahorse deployment | 25 days? | Mon 1/22/07 | Fri 2/23/07 | 23.33 days? | 0% | |
| 9 | Seahorse, test instrument service (PRI 1) | 12.5 days? | Mon 1/22/07 | Wed 2/7/07 | 23.33 days? | 0% | Kent Headley[40%],Andrew Hamilton[60%],Karen Salamy[60%] |
| 10 | Seahorse integration and final test | 12.5 days? | Wed 2/7/07 | Fri 2/23/07 | 23.33 days? | 0% | Kent Headley[40%],Andrew Hamilton[60%],Karen Salamy[60%] |
| 11 | McLane deployment | 22.67 days? | Mon 2/26/07 | Wed 3/28/07 | 0.67 days? | 0% | |
| 12 | McLane, test instrument service (PRI 1) | 8.33 days? | Mon 2/26/07 | Thu 3/8/07 | 10 days? | 0% | Brian Kieft[60%],Andrew Hamilton[60%],Karen Salamy |
| 13 | McLane, recover for labtest & turnaround (PRI 1) | 1.67 days? | Tue 3/20/07 | Wed 3/21/07 | 0.67 days? | 0% | Andrew Hamilton[60%] |
| 14 | McLane, integration and final test (PRI 1) | 5 days | Wed 3/21/07 | Wed 3/28/07 | 0.67 days | 0% | Brian Kieft[60%],Andrew Hamilton[60%],Karen Salamy[60%] |
| 15 | SSDS processing for profiling tools (PRI 1) | 16.67 days? | Mon 1/22/07 | Tue 3/20/07 | 18.67 days? | 0% | Kevin Gomes[60%],John Graybeal[60%],Mike McCann[60%] |
| 16 | Cable Laying drum | 46.67 days? | Tue 1/30/07 | Wed 4/4/07 | 11 days? | 0% | |
| 17 | Receive benthic test cable (PRI 1) | 0 days | Tue 1/30/07 | Tue 1/30/07 | 11 days | 0% | |
| 18 | McLane cable lay testing (PRI 1) | 6.67 days? | Tue 1/30/07 | Wed 2/7/07 | 11 days? | 0% | Larry Bird[75%],Mark Chaffey[60%] |
| 19 | Order and receive final benthic cable (PRI 1) | 40 days | Wed 2/7/07 | Wed 4/4/07 | 11 days | 0% | Mark Chaffey[3%] |
| 20 | Zephyr maintenance trip (PRI 1) | 1 day | Mon 3/19/07 | Mon 3/19/07 | 0 days | 0% | Mark Chaffey,OSG[200%] |
| 21 | SHELF BIN final integration and test (PRI 1) | 12 days | Wed 3/28/07 | Fri 4/13/07 | 0.67 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%],Bob Herlien[60%],Karen Salamy[60%] |
| 22 | SHELF BIN instrument readiness review (PRI 1) | 3.33 days | Fri 4/13/07 | Wed 4/18/07 | 0.67 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%],Kent Headley[40%],Brian Kieft[60%],Karen Salamy |
| 23 | SHELF BIN swap final staging (PRI 1) | 3.33 days? | Thu 4/19/07 | Tue 4/24/07 | 0.67 days? | 0% | Mark Chaffey[60%],Andrew Hamilton[60%],Larry Bird[75%],Johnny Ferrira[75%] |
| 24 | SHELF BIN swap deployment (PRI 1) | 5 days | Wed 4/25/07 | Tue 5/1/07 | 0 days | 0% | Mark Chaffey,Brian Kieft,Larry Bird,Andrew Hamilton |
| 25 | Zephyr maintenance trip (PRI 1) | 1 day | Tue 6/26/07 | Tue 6/26/07 | 134 days | 0% | Mark Chaffey,OSG[200%] |
| 26 | MBARI ethernet camera integration | 165 days? | Mon 1/22/07 | Fri 9/7/07 | 46.67 days? | 0% | |
| 27 | Digital camera PDR level review of design (PRI 1) | 35 days | Mon 1/22/07 | Fri 3/9/07 | 121.67 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%] |
| 28 | Digital camera SIAM instrument service (PRI 1) | 30 days? | Mon 6/25/07 | Fri 8/3/07 | 46.67 days? | 0% | Tom O'Reilly[60%],Karen Salamy[60%] |
| 29 | Digital camera integration and test (PRI 1) | 18 days | Mon 8/13/07 | Wed 9/5/07 | 48.67 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%],Johnny Ferrira[75%],Larry Bird[75%],Karen Salamy[60%] |
| 30 | SSDS interfaces for digital camera data (PRI 1) | 25 days? | Mon 8/6/07 | Fri 9/7/07 | 46.67 days? | 0% | Kevin Gomes[60%] |
| 31 | Ken Smith camera integration | 80 days? | Sun 5/20/07 | Sun 9/9/07 | 46.67 days? | 0% | |
| 32 | Smith camera - McGill evaluation (PRI 1) | 0 days? | Sun 5/20/07 | Sun 5/20/07 | 125.83 days? | 0% | Paul McGill[50%] |
| 33 | Smith camera PDR review (PRI 1) | 0.83 days? | Tue 7/17/07 | Tue 7/17/07 | 84.83 days? | 0% | Tom O'Reilly[60%],Mark Chaffey[60%] |
| 34 | Smith camera SIAM Instrument service (PRI 1) | 0 days | Sun 9/9/07 | Sun 9/9/07 | 46.67 days | 0% | Tom O'Reilly[3%] |
| 35 | AXIS BIN final integration and test (PRI 1) | 12 days | Mon 10/15/07 | Tue 10/30/07 | 21.67 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%],Karen Salamy[60%] |
| 36 | AXIS BIN instrument readiness review (PRI 1) | 2 days? | Wed 10/31/07 | Thu 11/1/07 | 21.67 days? | 0% | Tom O'Reilly[60%],Karen Salamy,Mark Chaffey[60%],Brian Kieft[60%] |
| 37 | AXIS BIN swap final staging (PRI 1) | 3.33 days? | Mon 11/12/07 | Thu 11/15/07 | 15.67 days? | 0% | Mark Chaffey[60%],Andrew Hamilton[60%],Larry Bird[75%],Johnny Ferrira[75%] |
| 38 | Zephyr maintenance trip (PRI 1) | 1 day | Tue 12/4/07 | Tue 12/4/07 | 19 days | 0% | Mark Chaffey,OSG |
| 39 | AXIS BIN swap deployment (PRI 1) | 5 days | Fri 12/7/07 | Thu 12/13/07 | 0 days | 0% | Mark Chaffey,Tom O'Reilly,Brian Kieft |
| 40 | Secondary priority tasks (PRI 2) | 209 days? | Tue 1/9/07 | Fri 10/26/07 | 46 days? | 0% | |
| 41 | Portal configuration script (PRI 2) | 3.33 days? | Mon 7/2/07 | Thu 7/5/07 | 127.67 days? | 0% | Brian Kieft[60%],Kent Headley[40%] |
| 42 | Portal GUI (PRI 2) | 8.33 days? | Mon 7/16/07 | Thu 7/26/07 | 112.67 days? | 0% | Bob Herlien[60%] |
| 43 | SIAM Node configuration tool (PRI 2) | 8.33 days? | Mon 7/30/07 | Thu 8/9/07 | 102.67 days? | 0% | Kent Headley[40%],Brian Kieft[60%] |
| 44 | PUCK configuration tool upgrade (PRI 2) | 16.67 days? | Mon 8/20/07 | Tue 9/11/07 | 79.33 days? | 0% | Tom O'Reilly[60%],Andrew Chase,Karen Salamy[60%] |
| 45 | Documentation for SIAM users (PRI 2) | 10 days? | Mon 10/8/07 | Fri 10/19/07 | 51 days? | 0% | Karen Salamy[60%],Tom O'Reilly[60%] |
| 46 | Documentation for SIAM programmers (PRI 2) | 10 days? | Mon 10/15/07 | Fri 10/26/07 | 46 days? | 0% | Karen Salamy[60%],Tom O'Reilly[60%] |
| 47 | WIFI communications for rapid data downloading (PRI 2) | 8.33 days? | Mon 7/30/07 | Thu 8/9/07 | 102.67 days? | 0% | Mark Chaffey[60%],Bob Herlien[60%],Etech[75%] |
| 48 | Improve onboard data archiving for higher data volumes (PRI 2) | 25 days? | Mon 7/2/07 | Fri 8/3/07 | 106 days? | 0% | Brian Kieft[60%] |
| 49 | SIAM, refine interface with SSDS (PRI 2) | 3.33 days? | Wed 7/11/07 | Mon 7/16/07 | 120.67 days? | 0% | Tom O'Reilly[60%],Kevin Gomes[60%] |
| 50 | SSDS Query dev. for access to MSE data (PRI 2) | 15 days? | Tue 7/17/07 | Mon 8/6/07 | 105 days? | 0% | Kevin Gomes[60%] |
| 51 | Telemetry-Implement dual modem architecture (PRI 2) | 16.67 days? | Mon 8/13/07 | Tue 9/4/07 | 84.33 days? | 0% | Tom O'Reilly[60%],Kent Headley[40%],Bob Herlien[60%],Brian Kieft[60%] |
| 52 | Telemetry-Install high gain antenna (PRI 2) | 3.33 days? | Mon 2/19/07 | Thu 2/22/07 | 16.67 days? | 0% | Mark Chaffey[60%],Johnny Ferrira[75%] |
| 53 | MOOS mooring system paper (PRI 2) | 11.67 days? | Thu 6/28/07 | Sun 7/15/07 | 0 days? | 0% | Mark Chaffey[60%] |
| 54 | MOOS mooring system presentation (PRI 2) | 5 days? | Mon 9/17/07 | Fri 9/21/07 | 5 days? | 0% | Mark Chaffey[60%] |
| 55 | SIAM Oceans paper (PRI 2) | 17.5 days? | Wed 6/20/07 | Sun 7/15/07 | 0 days? | 0% | Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%] |
| 56 | SIAM Oceans presentation (PRI 2) | 7.5 days? | Mon 9/17/07 | Wed 9/26/07 | 2.5 days? | 0% | Tom O'Reilly[60%],Brian Kieft[60%] |
| 57 | Power System oceans paper (PRI 2) | 11.67 days? | Thu 6/28/07 | Sun 7/15/07 | 0 days? | 0% | Ed Mellinger[60%] |
| 58 | Power System presentation (PRI 2) | 5 days? | Mon 9/17/07 | Fri 9/21/07 | 5 days? | 0% | Ed Mellinger[60%] |
| 59 | Oceans 2007 (PRI 2) | 4 days | Sat 9/29/07 | Thu 10/4/07 | 0 days | 0% | Mark Chaffey,Ed Mellinger,Tom O'Reilly,Brian Kieft |
| 60 | Fabricate spare MTM4 anchor (PRI 2) | 2 days? | Tue 1/9/07 | Wed 1/10/07 | 253 days? | 0% | Andrew Hamilton[60%],Frank Flores |
| 61 | Third priority tasks (PRI 3) | 145 days? | Mon 6/11/07 | Fri 12/28/07 | 1 day? | 0% | |
| 62 | Linux Kernel source configuration (PRI 3) | 5 days? | Mon 10/15/07 | Fri 10/19/07 | 51 days? | 0% | SE unassigned |
| 63 | SideARM Coma mode bug (PRI 3) | 5 days? | Mon 10/22/07 | Fri 10/26/07 | 46 days? | 0% | SE unassigned |
| 64 | SideARM Serial over-run bug (PRI 3) | 5 days? | Mon 10/29/07 | Fri 11/2/07 | 41 days? | 0% | SE unassigned |
| 65 | Jump to boot loader on console transition bug (PRI 3) | 6.67 days? | Mon 11/5/07 | Tue 11/13/07 | 34.33 days? | 0% | SE unassigned[60%] |
| 66 | Medusa diagnostics (GUI) (PRI 3) | 10 days? | Mon 11/19/07 | Fri 11/30/07 | 21 days? | 0% | SE unassigned[60%] |
| 67 | Medusa failover on link status (PRI 3) | 10 days? | Mon 11/19/07 | Fri 11/30/07 | 21 days? | 0% | SE unassigned[60%] |
| 68 | Revise BIN 400-12 Switch board (PRI 3) | 66.67 days? | Mon 6/11/07 | Tue 9/11/07 | 79.33 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Etech[75%] |
| 69 | Replace Solar MPPT unit (PRI 3) | 33.33 days? | Mon 10/1/07 | Thu 11/15/07 | 32.67 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Jon Erickson[60%],Machine shop,Tom Marion[75%] |
| 70 | Modify Converter/GF Board (PRI 3) | 33.33 days? | Mon 11/12/07 | Thu 12/27/07 | 2.67 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Etech[75%] |
| 71 | Power system status (GUI) (PRI 3) | 5 days? | Mon 12/24/07 | Fri 12/28/07 | 1 day? | 0% | EE unassigned[60%],Ed Mellinger[60%] |
| 72 | Dummy task | 0 days? | Thu 1/11/07 | Thu 1/11/07 | 253 days? | 0% | Mark Chaffey[60%],Andrew Hamilton[60%],Ed Mellinger[60%],Tom O'Reilly[60%],Bob Herlien[60%],Kent Headley[40%],Brian Kieft[60%],Kevin Gomes[60%] |