MOOSMooringMTM4


Project Start Date: Tue 1/2/07
Project Finish Date: Mon 12/31/07

Tasks

ID
Task Name
DurationStartFinishRemaining Slack% CompleteResource
1
MOOS mooring project management
260 daysTue 1/2/07Mon 12/31/070 days47%Mark Chaffey[55%]
22
Zephyr maintenance trip (PRI 1)
6 days?Wed 6/20/07Wed 6/27/07133 days?20%Mark Chaffey,OSG[200%]
23
Pre-deployment test
3 days?Wed 6/20/07Fri 6/22/07136 days?0% 
24
Wind sensor ID 1291
3 days?Wed 6/20/07Fri 6/22/07136 days?0% 
25
GPS ID 1344
3 days?Wed 6/20/07Fri 6/22/07136 days?0% 
26
SOON PCO2 ID 1610
3 days?Wed 6/20/07Fri 6/22/07136 days?0% 
27
Heave Sensor ID 1339
3 days?Wed 6/20/07Fri 6/22/07136 days?0% 
29
Axis/Cable Electrical Short Diagnostic Cruise
14 days?Thu 8/23/07Tue 9/11/0779 days?0% 
30
Order replacement battery set for Axis BIN
1 day?Thu 8/23/07Thu 8/23/0780 days?0% 
31
Reconfigure Shelf BIN and test
5 daysFri 8/24/07Thu 8/30/0780 days0% 
32
Stage Axis BIN for cruise
2 daysFri 8/31/07Mon 9/3/0780 days0% 
33
Western Flyer Cruise Dates
5 daysWed 9/5/07Tue 9/11/0779 days0% 
35
MBARI ethernet camera integration
65 days?Thu 8/23/07Wed 11/21/0728 days?0% 
36
Digital camera PDR level review of design (PRI 1)
35 daysThu 8/23/07Wed 10/10/0728 days0%Mark Chaffey[60%],Tom O'Reilly[60%]
37
Digital camera PDR
0 daysWed 10/10/07Wed 10/10/0728 days0% 
38
Digital camera SIAM instrument service (PRI 1)
30 days?Thu 10/11/07Wed 11/21/0728 days?0%Tom O'Reilly[60%],Karen Salamy[60%]
39
Digital camera integration and test (PRI 1)
18 daysMon 10/29/07Wed 11/21/0728 days0%Mark Chaffey[60%],Tom O'Reilly[60%],Johnny Ferrira[75%],Larry Bird[75%],Karen Salamy[60%]
40
SSDS interfaces for digital camera data (PRI 1)
25 days?Thu 10/18/07Wed 11/21/0728 days?0%Kevin Gomes[60%]
41
Ken Smith camera integration
143.83 days?Sun 5/20/07Thu 12/6/0717.17 days?0% 
42
Smith camera - McGill evaluation (PRI 1)
0 days?Sun 5/20/07Sun 5/20/0785.17 days?0%Paul McGill[50%]
43
Smith camera PDR review (PRI 1)
0.83 days?Thu 8/23/07Thu 8/23/0717.17 days?0%Tom O'Reilly[60%],Mark Chaffey[60%]
44
Smith camera housing fabrication (PRI 1)
45 daysThu 8/23/07Thu 10/25/0717.17 days0% 
45
Smith camera integration and test (PRI 1)
10 daysThu 10/25/07Thu 11/8/0717.17 days0% 
46
Smith camera SIAM Instrument service (PRI 1)
20 daysThu 11/8/07Thu 12/6/0717.17 days0%Tom O'Reilly[3%]
47
SSDS interfaces for Smith camera data (PRI 1)
5 daysThu 11/8/07Thu 11/15/0732.17 days0% 
48
Zephyr maintenance trip (PRI 1)
1 dayTue 12/4/07Tue 12/4/0719 days0%Mark Chaffey,OSG
49
AXIS BIN recovery cruise (PRI 1)
5 daysFri 12/7/07Thu 12/13/070 days0%Mark Chaffey,Tom O'Reilly,Brian Kieft
50
Secondary priority tasks (PRI 2)
175 days?Mon 2/26/07Fri 10/26/0746 days?0% 
51
Recover MTM2 BIN frame from Sanctuary
1.67 days?Thu 8/23/07Fri 8/24/0791.33 days?0%Mark Chaffey[60%]
52
Portal configuration script (PRI 2)
3.33 days?Mon 7/2/07Thu 7/5/07127.67 days?0%Brian Kieft[60%],Kent Headley[40%]
53
Portal GUI (PRI 2)
8.33 days?Mon 7/16/07Thu 7/26/07112.67 days?0%Bob Herlien[60%]
54
SIAM Node configuration tool (PRI 2)
8.33 days?Mon 7/30/07Thu 8/9/07102.67 days?0%Kent Headley[40%],Brian Kieft[60%]
55
PUCK configuration tool upgrade (PRI 2)
16.67 days?Mon 8/20/07Tue 9/11/0779.33 days?0%Tom O'Reilly[60%],Andrew Chase,Karen Salamy[60%]
56
Documentation for SIAM users (PRI 2)
10 days?Mon 10/8/07Fri 10/19/0751 days?0%Karen Salamy[60%],Tom O'Reilly[60%]
57
Documentation for SIAM programmers (PRI 2)
10 days?Mon 10/15/07Fri 10/26/0746 days?0%Karen Salamy[60%],Tom O'Reilly[60%]
58
WIFI communications for rapid data downloading (PRI 2)
8.33 days?Mon 7/30/07Thu 8/9/07102.67 days?0%Mark Chaffey[60%],Bob Herlien[60%],Etech[75%]
59
Improve onboard data archiving for higher data volumes (PRI 2)
25 days?Mon 7/2/07Fri 8/3/07106 days?0%Brian Kieft[60%]
60
SIAM, refine interface with SSDS (PRI 2)
3.33 days?Wed 7/11/07Mon 7/16/07120.67 days?0%Tom O'Reilly[60%],Kevin Gomes[60%]
61
SSDS Query dev. for access to MSE data (PRI 2)
15 days?Tue 7/17/07Mon 8/6/07105 days?0%Kevin Gomes[60%]
62
Telemetry-Implement dual modem architecture (PRI 2)
16.67 days?Mon 8/13/07Tue 9/4/0784.33 days?0%Tom O'Reilly[60%],Kent Headley[40%],Bob Herlien[60%],Brian Kieft[60%]
63
Telemetry-Install high gain antenna (PRI 2)
3.33 days?Mon 2/26/07Thu 3/1/07217.67 days?0%Mark Chaffey[60%],Johnny Ferrira[75%]
64
Oceans 2007 Vancouver abstract deadline
0 daysFri 3/30/07Fri 3/30/0758.5 days0% 
65
MOOS mooring system paper (PRI 2)
11.67 days?Thu 6/28/07Sun 7/15/070 days?0%Mark Chaffey[60%]
66
MOOS mooring system presentation (PRI 2)
5 days?Mon 9/17/07Fri 9/21/075 days?0%Mark Chaffey[60%]
67
SIAM Oceans paper (PRI 2)
17.5 days?Wed 6/20/07Sun 7/15/070 days?0%Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%]
68
SIAM Oceans presentation (PRI 2)
7.5 days?Mon 9/17/07Wed 9/26/072.5 days?0%Tom O'Reilly[60%],Brian Kieft[60%]
69
Power System oceans paper (PRI 2)
11.67 days?Thu 6/28/07Sun 7/15/070 days?0%Ed Mellinger[60%]
70
Power System presentation (PRI 2)
5 days?Mon 9/17/07Fri 9/21/075 days?0%Ed Mellinger[60%]
71
Oceans 2007 (PRI 2)
4 daysSat 9/29/07Thu 10/4/070 days0%Mark Chaffey,Ed Mellinger,Tom O'Reilly,Brian Kieft
72
Fabricate spare MTM4 anchor (PRI 2)
2 days?Thu 3/22/07Fri 3/23/07201 days?0%Andrew Hamilton[60%],Frank Flores
73
Third priority tasks (PRI 3)
145 days?Mon 6/11/07Fri 12/28/071 day?0% 
74
Linux Kernel source configuration (PRI 3)
5 days?Mon 10/15/07Fri 10/19/0751 days?0%SE unassigned
75
SideARM Coma mode bug (PRI 3)
5 days?Mon 10/22/07Fri 10/26/0746 days?0%SE unassigned
76
SideARM Serial over-run bug (PRI 3)
5 days?Mon 10/29/07Fri 11/2/0741 days?0%SE unassigned
77
Jump to boot loader on console transition bug (PRI 3)
6.67 days?Mon 11/5/07Tue 11/13/0734.33 days?0%SE unassigned[60%]
78
Medusa diagnostics (GUI) (PRI 3)
10 days?Mon 11/19/07Fri 11/30/0721 days?0%SE unassigned[60%]
79
Medusa failover on link status (PRI 3)
10 days?Mon 11/19/07Fri 11/30/0721 days?0%SE unassigned[60%]
80
Revise BIN 400-12 Switch board (PRI 3)
66.67 days?Mon 6/11/07Tue 9/11/0779.33 days?0%Ed Mellinger[60%],SE unassigned[60%],Etech[75%]
81
Replace Solar MPPT unit (PRI 3)
33.33 days?Mon 10/1/07Thu 11/15/0732.67 days?0%Ed Mellinger[60%],SE unassigned[60%],Jon Erickson[60%],Machine shop,Tom Marion[75%]
82
Modify Converter/GF Board (PRI 3)
33.33 days?Mon 11/12/07Thu 12/27/072.67 days?0%Ed Mellinger[60%],SE unassigned[60%],Etech[75%]
83
Power system status (GUI) (PRI 3)
5 days?Mon 12/24/07Fri 12/28/071 day?0%EE unassigned[60%],Ed Mellinger[60%]