Project Start Date: Tue 1/2/07
Project Finish Date: Mon 12/31/07
| ID | Task Name | Duration | Start | Finish | Remaining Slack | % Complete | Resource |
|---|---|---|---|---|---|---|---|
| 1 | MOOS mooring project management | 260 days | Tue 1/2/07 | Mon 12/31/07 | 0 days | 47% | Mark Chaffey[55%] |
| 22 | Zephyr maintenance trip (PRI 1) | 6 days? | Wed 6/20/07 | Wed 6/27/07 | 133 days? | 20% | Mark Chaffey,OSG[200%] |
| 23 | Pre-deployment test | 3 days? | Wed 6/20/07 | Fri 6/22/07 | 136 days? | 0% | |
| 24 | Wind sensor ID 1291 | 3 days? | Wed 6/20/07 | Fri 6/22/07 | 136 days? | 0% | |
| 25 | GPS ID 1344 | 3 days? | Wed 6/20/07 | Fri 6/22/07 | 136 days? | 0% | |
| 26 | SOON PCO2 ID 1610 | 3 days? | Wed 6/20/07 | Fri 6/22/07 | 136 days? | 0% | |
| 27 | Heave Sensor ID 1339 | 3 days? | Wed 6/20/07 | Fri 6/22/07 | 136 days? | 0% | |
| 29 | Axis/Cable Electrical Short Diagnostic Cruise | 14 days? | Thu 8/23/07 | Tue 9/11/07 | 79 days? | 0% | |
| 30 | Order replacement battery set for Axis BIN | 1 day? | Thu 8/23/07 | Thu 8/23/07 | 80 days? | 0% | |
| 31 | Reconfigure Shelf BIN and test | 5 days | Fri 8/24/07 | Thu 8/30/07 | 80 days | 0% | |
| 32 | Stage Axis BIN for cruise | 2 days | Fri 8/31/07 | Mon 9/3/07 | 80 days | 0% | |
| 33 | Western Flyer Cruise Dates | 5 days | Wed 9/5/07 | Tue 9/11/07 | 79 days | 0% | |
| 35 | MBARI ethernet camera integration | 65 days? | Thu 8/23/07 | Wed 11/21/07 | 28 days? | 0% | |
| 36 | Digital camera PDR level review of design (PRI 1) | 35 days | Thu 8/23/07 | Wed 10/10/07 | 28 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%] |
| 37 | Digital camera PDR | 0 days | Wed 10/10/07 | Wed 10/10/07 | 28 days | 0% | |
| 38 | Digital camera SIAM instrument service (PRI 1) | 30 days? | Thu 10/11/07 | Wed 11/21/07 | 28 days? | 0% | Tom O'Reilly[60%],Karen Salamy[60%] |
| 39 | Digital camera integration and test (PRI 1) | 18 days | Mon 10/29/07 | Wed 11/21/07 | 28 days | 0% | Mark Chaffey[60%],Tom O'Reilly[60%],Johnny Ferrira[75%],Larry Bird[75%],Karen Salamy[60%] |
| 40 | SSDS interfaces for digital camera data (PRI 1) | 25 days? | Thu 10/18/07 | Wed 11/21/07 | 28 days? | 0% | Kevin Gomes[60%] |
| 41 | Ken Smith camera integration | 143.83 days? | Sun 5/20/07 | Thu 12/6/07 | 17.17 days? | 0% | |
| 42 | Smith camera - McGill evaluation (PRI 1) | 0 days? | Sun 5/20/07 | Sun 5/20/07 | 85.17 days? | 0% | Paul McGill[50%] |
| 43 | Smith camera PDR review (PRI 1) | 0.83 days? | Thu 8/23/07 | Thu 8/23/07 | 17.17 days? | 0% | Tom O'Reilly[60%],Mark Chaffey[60%] |
| 44 | Smith camera housing fabrication (PRI 1) | 45 days | Thu 8/23/07 | Thu 10/25/07 | 17.17 days | 0% | |
| 45 | Smith camera integration and test (PRI 1) | 10 days | Thu 10/25/07 | Thu 11/8/07 | 17.17 days | 0% | |
| 46 | Smith camera SIAM Instrument service (PRI 1) | 20 days | Thu 11/8/07 | Thu 12/6/07 | 17.17 days | 0% | Tom O'Reilly[3%] |
| 47 | SSDS interfaces for Smith camera data (PRI 1) | 5 days | Thu 11/8/07 | Thu 11/15/07 | 32.17 days | 0% | |
| 48 | Zephyr maintenance trip (PRI 1) | 1 day | Tue 12/4/07 | Tue 12/4/07 | 19 days | 0% | Mark Chaffey,OSG |
| 49 | AXIS BIN recovery cruise (PRI 1) | 5 days | Fri 12/7/07 | Thu 12/13/07 | 0 days | 0% | Mark Chaffey,Tom O'Reilly,Brian Kieft |
| 50 | Secondary priority tasks (PRI 2) | 175 days? | Mon 2/26/07 | Fri 10/26/07 | 46 days? | 0% | |
| 51 | Recover MTM2 BIN frame from Sanctuary | 1.67 days? | Thu 8/23/07 | Fri 8/24/07 | 91.33 days? | 0% | Mark Chaffey[60%] |
| 52 | Portal configuration script (PRI 2) | 3.33 days? | Mon 7/2/07 | Thu 7/5/07 | 127.67 days? | 0% | Brian Kieft[60%],Kent Headley[40%] |
| 53 | Portal GUI (PRI 2) | 8.33 days? | Mon 7/16/07 | Thu 7/26/07 | 112.67 days? | 0% | Bob Herlien[60%] |
| 54 | SIAM Node configuration tool (PRI 2) | 8.33 days? | Mon 7/30/07 | Thu 8/9/07 | 102.67 days? | 0% | Kent Headley[40%],Brian Kieft[60%] |
| 55 | PUCK configuration tool upgrade (PRI 2) | 16.67 days? | Mon 8/20/07 | Tue 9/11/07 | 79.33 days? | 0% | Tom O'Reilly[60%],Andrew Chase,Karen Salamy[60%] |
| 56 | Documentation for SIAM users (PRI 2) | 10 days? | Mon 10/8/07 | Fri 10/19/07 | 51 days? | 0% | Karen Salamy[60%],Tom O'Reilly[60%] |
| 57 | Documentation for SIAM programmers (PRI 2) | 10 days? | Mon 10/15/07 | Fri 10/26/07 | 46 days? | 0% | Karen Salamy[60%],Tom O'Reilly[60%] |
| 58 | WIFI communications for rapid data downloading (PRI 2) | 8.33 days? | Mon 7/30/07 | Thu 8/9/07 | 102.67 days? | 0% | Mark Chaffey[60%],Bob Herlien[60%],Etech[75%] |
| 59 | Improve onboard data archiving for higher data volumes (PRI 2) | 25 days? | Mon 7/2/07 | Fri 8/3/07 | 106 days? | 0% | Brian Kieft[60%] |
| 60 | SIAM, refine interface with SSDS (PRI 2) | 3.33 days? | Wed 7/11/07 | Mon 7/16/07 | 120.67 days? | 0% | Tom O'Reilly[60%],Kevin Gomes[60%] |
| 61 | SSDS Query dev. for access to MSE data (PRI 2) | 15 days? | Tue 7/17/07 | Mon 8/6/07 | 105 days? | 0% | Kevin Gomes[60%] |
| 62 | Telemetry-Implement dual modem architecture (PRI 2) | 16.67 days? | Mon 8/13/07 | Tue 9/4/07 | 84.33 days? | 0% | Tom O'Reilly[60%],Kent Headley[40%],Bob Herlien[60%],Brian Kieft[60%] |
| 63 | Telemetry-Install high gain antenna (PRI 2) | 3.33 days? | Mon 2/26/07 | Thu 3/1/07 | 217.67 days? | 0% | Mark Chaffey[60%],Johnny Ferrira[75%] |
| 64 | Oceans 2007 Vancouver abstract deadline | 0 days | Fri 3/30/07 | Fri 3/30/07 | 58.5 days | 0% | |
| 65 | MOOS mooring system paper (PRI 2) | 11.67 days? | Thu 6/28/07 | Sun 7/15/07 | 0 days? | 0% | Mark Chaffey[60%] |
| 66 | MOOS mooring system presentation (PRI 2) | 5 days? | Mon 9/17/07 | Fri 9/21/07 | 5 days? | 0% | Mark Chaffey[60%] |
| 67 | SIAM Oceans paper (PRI 2) | 17.5 days? | Wed 6/20/07 | Sun 7/15/07 | 0 days? | 0% | Tom O'Reilly[60%],Brian Kieft[60%],Kent Headley[40%] |
| 68 | SIAM Oceans presentation (PRI 2) | 7.5 days? | Mon 9/17/07 | Wed 9/26/07 | 2.5 days? | 0% | Tom O'Reilly[60%],Brian Kieft[60%] |
| 69 | Power System oceans paper (PRI 2) | 11.67 days? | Thu 6/28/07 | Sun 7/15/07 | 0 days? | 0% | Ed Mellinger[60%] |
| 70 | Power System presentation (PRI 2) | 5 days? | Mon 9/17/07 | Fri 9/21/07 | 5 days? | 0% | Ed Mellinger[60%] |
| 71 | Oceans 2007 (PRI 2) | 4 days | Sat 9/29/07 | Thu 10/4/07 | 0 days | 0% | Mark Chaffey,Ed Mellinger,Tom O'Reilly,Brian Kieft |
| 72 | Fabricate spare MTM4 anchor (PRI 2) | 2 days? | Thu 3/22/07 | Fri 3/23/07 | 201 days? | 0% | Andrew Hamilton[60%],Frank Flores |
| 73 | Third priority tasks (PRI 3) | 145 days? | Mon 6/11/07 | Fri 12/28/07 | 1 day? | 0% | |
| 74 | Linux Kernel source configuration (PRI 3) | 5 days? | Mon 10/15/07 | Fri 10/19/07 | 51 days? | 0% | SE unassigned |
| 75 | SideARM Coma mode bug (PRI 3) | 5 days? | Mon 10/22/07 | Fri 10/26/07 | 46 days? | 0% | SE unassigned |
| 76 | SideARM Serial over-run bug (PRI 3) | 5 days? | Mon 10/29/07 | Fri 11/2/07 | 41 days? | 0% | SE unassigned |
| 77 | Jump to boot loader on console transition bug (PRI 3) | 6.67 days? | Mon 11/5/07 | Tue 11/13/07 | 34.33 days? | 0% | SE unassigned[60%] |
| 78 | Medusa diagnostics (GUI) (PRI 3) | 10 days? | Mon 11/19/07 | Fri 11/30/07 | 21 days? | 0% | SE unassigned[60%] |
| 79 | Medusa failover on link status (PRI 3) | 10 days? | Mon 11/19/07 | Fri 11/30/07 | 21 days? | 0% | SE unassigned[60%] |
| 80 | Revise BIN 400-12 Switch board (PRI 3) | 66.67 days? | Mon 6/11/07 | Tue 9/11/07 | 79.33 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Etech[75%] |
| 81 | Replace Solar MPPT unit (PRI 3) | 33.33 days? | Mon 10/1/07 | Thu 11/15/07 | 32.67 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Jon Erickson[60%],Machine shop,Tom Marion[75%] |
| 82 | Modify Converter/GF Board (PRI 3) | 33.33 days? | Mon 11/12/07 | Thu 12/27/07 | 2.67 days? | 0% | Ed Mellinger[60%],SE unassigned[60%],Etech[75%] |
| 83 | Power system status (GUI) (PRI 3) | 5 days? | Mon 12/24/07 | Fri 12/28/07 | 1 day? | 0% | EE unassigned[60%],Ed Mellinger[60%] |