Project Manager: Mark Chaffey
2004 Meeting
Minutes |
2004 Project
Documents |
|
|
- MTM#2
Mooring MMC/SIAM Final Checklist (DRAFT)
(April 9,
2004)
- MTM#2
Mooring MMC/SIAM Test Plan (DRAFT)
(March 18,
2004)
- MOOS
Power System Converter Feed/GF
Board CDR (January
22, 2004)
- MOOS
BIN PDR
(January 15, 2004)
- MOOS
Power System P2 Board CDR
(January 8, 2004)
- MOOS
Mooring Deployment Winch CDR
(December 23,
2003)
- MMC
Communications PCB CDR
(December 18, 2003)
- MMC
SideARM Rev. 4 CDR
(December 15, 2003)
- MOOS
Mooring System Naming Conventions
(December 11,
2003)
- MMC
RF Interface Preliminary Design Review
(November 14,
2003)
- MOOS
Mooring MMC RF Interface Board Preliminary Design
Review
(November 14, 2003)
- MOOS
Mooring Cable and Flotation Review (November 13, 2003)
- MOOS Mooring System
Computing Architecture Review
- MOOS
Systems Architecture CDR and MMC, Power, Time
Distribution, Communications and RF Interface Subsystems
PDR
(August 12, 2003)
- MOOS
Communications Controller Requirements Specification
(.pdf)
(April 15, 2003, Wayne Radachonski)
- MOOS
Mooring Controller Requirements Specification
(.pdf)
(December 31, 2002,
Wayne Radachonski)
- SideARM
Requirements Specification (.pdf)
(December 19, 2002, Wayne Radachonski)
-
MMC
Scrum / System Architecture Meeting Notes (August 7,
2003)
-
TMT-
Dissection of riser at optical break (May 20, 2003, Andy
Hamilton)
-
Power
Management Implementation Plan (May 19, 2003, Bob
Herlien)
-
TMT Meeting
notes (April 14, 2003)
-
Surface Architecture Brainstorming
Notes (March 25,
2003)
-
MOOS
Mooring Subsystem List (March 6, 2003)
-
MOOS
Brainstorm Inter-node Comms Notes (February 13,
2003)
-
Post
Recovery Task List Rev 1.0 (December 27, 2002)
-
MOOS
Test Mooring Deployment Float Locations & Cable Length rev
2.5 (November 14, 2002)
-
Riser
Termination Critical Design Review Notes (November,
2002)
-
MOOS
Mooring Float Configuration & Anchor Design PDR Notes
(October 23, 2002)
-
Pager
Reset CDR Notes (October 16, 2002)
-
Riser
Cable Termination Design PDR (October 15, 2002)
-
Power
Board CDR notes (October 8, 2002)
-
Cerfboard Documentation (.pdf) (September, 2002)
-
Mooring
Tower & Float CDR (May, 2002)
-
Test Deployment Controller PDR (May, 2002)
-
Block Diagram Rev. XA
-
MOOS
Interfaces Rev. C.1
-
Wireless
Communications Requirements - Executive Summary
-
MOOS Timing Concept Topology Diagram
-
MBARI Wireless Network
Topology Diagram
-
Interfaces on the initial MOOS deployment, Rev.
B (April, 2002)
-
MOOS Mooring Riser Cable and Snubber Assembly
PDR(March, 2002)
-
MOOS Mooring Float-Tower-Bridle PDR Notes
(pdf) (March, 2002)
-
MOOS Mooring Buoy Structure PDR (ppt) (March,
2002)
-
MOOS Mooring 2001 Project (ppt)
-
Oceans 2001 Presentation (ppt) (November
2001)
-
MOOS
mooring Oceans 2001 paper (October, 2001)
-
A Study of Copper Communication
Protocols (August,
2001)
-
MOOS
Mooring System Configuration Options (Rev. April 16,
2001)
-
WHOI
Proposal 2-011 (Numerical Modeling and Mooring Material
Support for the MBARI MOOS Program)
-
MOOS
Test Mooring Document Rev. 2 (02/28/01)
-
Design
Trade-off Concept A (Dec. 12, 2000)
-
Design
Trade-off Concept B (Dec. 12, 2000)
-
SDR
Review Slides (ppt) (Nov. 17, 2000)
|
This page is
maintained by Mandy Allen. Questions about its content should be
directed to Mark Chaffey. |