| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | DORISS/PUP Overview | 185 days? | Thu 1/15/04 | Wed 9/29/04 | | 0% |
| 2 | Current Work / Repairs | 61.5 days? | Thu 1/15/04 | Fri 4/9/04 | | 0% |
| 3 | | | | | | |
| 4 | DORISS | 23 days? | Mon 1/19/04 | Wed 2/18/04 | | 0% |
| 5 | Networking | 11 days? | Thu 1/22/04 | Thu 2/5/04 | Karen Salamy,Sheri White | 0% |
| 6 | Fix LRS Client-single IP | 12.5 days? | Mon 1/26/04 | Wed 2/11/04 | Karen Salamy,Rich Henthorn | 0% |
| 7 | Alternatives to Net Meeting | 18 days | Mon 1/26/04 | Wed 2/18/04 | Karen Salamy,Rich Henthorn | 0% |
| 8 | Clean up wiring in Housing | 7 days | Mon 1/19/04 | Tue 1/27/04 | Alana Sherman,EE Tech | 0% |
| 9 | repair camera cable | 8 days | Wed 1/21/04 | Fri 1/30/04 | Alana Sherman,Sheri White? | 0% |
| 10 | | | | | | |
| 11 | PUP | 61.5 days? | Thu 1/15/04 | Fri 4/9/04 | | 0% |
| 12 | Check for Electronic room for Z-axis | 6.67 days | Thu 1/15/04 | Fri 1/23/04 | Alana Sherman[15%],Scott Jensen[15%] | 0% |
| 13 | Switch Dovetail assemblies | 4 days? | Mon 1/19/04 | Thu 1/22/04 | ON HOLD for Now | 0% |
| 14 | Test in pressure chamber | 1 day? | Mon 1/19/04 | Mon 1/19/04 | On Hold | 0% |
| 15 | Test in cold room | 1 day? | Tue 1/20/04 | Tue 1/20/04 | On Hold | 0% |
| 16 | Test in test tank | 1 day? | Wed 1/21/04 | Wed 1/21/04 | On Hold | 0% |
| 17 | Test at Sea | 1 day? | Thu 1/22/04 | Thu 1/22/04 | On Hold | 0% |
| 18 | Fix Z-axis Limit Switch | 49.5 days? | Thu 1/22/04 | Wed 3/31/04 | | 0% |
| 19 | check current limit switch | 5 days | Thu 1/22/04 | Wed 1/28/04 | Alana Sherman,EE Tech | 0% |
| 20 | check spare limit switch | 8.5 days? | Thu 1/29/04 | Tue 2/10/04 | Alana Sherman,EE Tech | 0% |
| 21 | check wiring | 7.5 days? | Tue 2/10/04 | Thu 2/19/04 | Alana Sherman,EE Tech | 0% |
| 22 | test in lab | 14.5 days? | Fri 2/20/04 | Thu 3/11/04 | Alana Sherman,EE Tech | 0% |
| 23 | test in cold room | 8.5 days? | Thu 3/11/04 | Tue 3/23/04 | Alana Sherman,EE Tech | 0% |
| 24 | test in test tank | 5.5 days? | Wed 3/24/04 | Wed 3/31/04 | Alana Sherman,EE Tech | 0% |
| 25 | Theta axis | 54.83 days? | Fri 1/23/04 | Fri 4/9/04 | | 0% |
| 26 | design | 15.33 days? | Fri 1/23/04 | Fri 2/13/04 | Mark Brown | 0% |
| 27 | review | 1 day? | Mon 2/16/04 | Mon 2/16/04 | Mark Brown | 0% |
| 28 | build | 5.5 days? | Tue 2/17/04 | Tue 2/24/04 | Mark Brown,Johnny F | 0% |
| 29 | assemble / install | 6.5 days? | Tue 2/24/04 | Wed 3/3/04 | Mark Brown,Johnny F | 0% |
| 30 | test in lab | 4 days? | Thu 3/4/04 | Tue 3/9/04 | Mark Brown,Johnny F | 0% |
| 31 | test in tank | 7 days? | Wed 3/10/04 | Thu 3/18/04 | Mark Brown,Johnny F | 0% |
| 32 | test in cold room | 7 days? | Fri 3/19/04 | Mon 3/29/04 | Mark Brown,Johnny F | 0% |
| 33 | At sea testing | 8.5 days? | Tue 3/30/04 | Fri 4/9/04 | | 0% |
| 34 | Install new LED light | 40 days? | Mon 1/19/04 | Fri 3/12/04 | | 0% |
| 35 | purchase LEDs | 15 days? | Mon 1/19/04 | Fri 2/6/04 | Scott Jensen | 0% |
| 36 | pot LEDs | 14 days? | Mon 2/9/04 | Thu 2/26/04 | Scott Jensen,Jim Scholfield | 0% |
| 37 | test in test tank | 11 days? | Fri 2/27/04 | Fri 3/12/04 | Scott Jensen,Alana Sherman,Jim Scholfield | 0% |
| 38 | New Probe head mount | 59 days? | Mon 1/19/04 | Thu 4/8/04 | | 0% |
| 39 | Design | 20 days? | Mon 1/19/04 | Fri 2/13/04 | Mark Brown | 0% |
| 40 | Build | 15 days? | Mon 2/16/04 | Fri 3/5/04 | Mark Brown,Jonnhy F | 0% |
| 41 | Assemble | 10 days? | Mon 3/8/04 | Fri 3/19/04 | Johnny F | 0% |
| 42 | Vertical testing | 8 days? | Mon 3/22/04 | Wed 3/31/04 | Sheri White,Johnny F | 0% |
| 43 | Test in cold room | 6 days? | Thu 4/1/04 | Thu 4/8/04 | Sheri White,Johnnny F | 0% |
| 44 | Adjust camera server rate | 13.5 days? | Mon 1/19/04 | Thu 2/5/04 | | 0% |
| 45 | Reduce ethernet traffic | 13.5 days? | Mon 1/19/04 | Thu 2/5/04 | Rich Henthorn,Alana Sherman | 0% |
| 46 | Z-axis Rt Angle connector | 49.5 days? | Mon 1/19/04 | Fri 3/26/04 | | 0% |
| 47 | Order | 33.5 days? | Mon 1/19/04 | Thu 3/4/04 | Scott Jensen | 0% |
| 48 | Installation | 8.5 days? | Thu 3/4/04 | Tue 3/16/04 | EE Tech | 0% |
| 49 | Test | 7.5 days? | Wed 3/17/04 | Fri 3/26/04 | Scott Jensen,EE Tech | 0% |
| 50 | Swing Arm | 59 days? | Mon 1/19/04 | Thu 4/8/04 | | 0% |
| 51 | Consult on Design | 24 days? | Mon 1/19/04 | Thu 2/19/04 | Mark Brown | 0% |
| 52 | Build | 15 days? | Fri 2/20/04 | Thu 3/11/04 | Johnny F | 0% |
| 53 | Test | 20 days? | Fri 3/12/04 | Thu 4/8/04 | Johnny F,Buck R,Mark B | 0% |
| 54 | | | | | | |
| 55 | Upgrades | 114 days? | Mon 1/19/04 | Thu 6/24/04 | | 0% |
| 56 | Purchase new components | 46 days? | Mon 1/19/04 | Mon 3/22/04 | | 0% |
| 57 | USB CCD camera | 46 days? | Mon 1/19/04 | Mon 3/22/04 | Sheri W | 0% |
| 58 | MR Probe head | 46 days? | Mon 1/19/04 | Mon 3/22/04 | Sheri W | 0% |
| 59 | Titanium immersion probe | 46 days? | Mon 1/19/04 | Mon 3/22/04 | Sheri W | 0% |
| 60 | 532 nm laser | 45 days? | Mon 1/19/04 | Fri 3/19/04 | Sheri W | 0% |
| 61 | | | | | | |
| 62 | DORISS | 114 days? | Mon 1/19/04 | Thu 6/24/04 | | 0% |
| 63 | New optical bench | 114 days? | Mon 1/19/04 | Thu 6/24/04 | | 0% |
| 64 | design | 30 days? | Mon 1/19/04 | Fri 2/27/04 | Bill K | 0% |
| 65 | PDR | 8 days? | Mon 3/1/04 | Wed 3/10/04 | Bill K | 0% |
| 66 | build | 6.5 days? | Thu 3/11/04 | Fri 3/19/04 | ?? | 0% |
| 67 | bench assembly | 13 days? | Fri 3/19/04 | Wed 4/7/04 | Bill K,Sheri W | 0% |
| 68 | test | 10 days? | Wed 4/7/04 | Wed 4/21/04 | Sheri W,Bill K,Alana Sherman | 0% |
| 69 | housing mods | 7.5 days? | Wed 4/21/04 | Fri 4/30/04 | Bill K | 0% |
| 70 | optical sub-assembly | 9.5 days? | Mon 5/3/04 | Fri 5/14/04 | Sheri W,Alana Sherman | 0% |
| 71 | sub-system test | 9.5 days? | Fri 5/14/04 | Thu 5/27/04 | Sheri W,Alana Sherman | 0% |
| 72 | optical sys complete tets | 9 days? | Fri 5/28/04 | Wed 6/9/04 | Sheri W,Alana Sherman | 0% |
| 73 | tank test | 11 days? | Thu 6/10/04 | Thu 6/24/04 | Sheri W,Alana Sherman | 0% |
| 74 | New Housings | 90 days? | Mon 1/19/04 | Fri 5/21/04 | | 0% |
| 75 | Spectrometer housing | 52 days? | Thu 3/11/04 | Fri 5/21/04 | | 0% |
| 76 | design | 12 days? | Thu 3/11/04 | Fri 3/26/04 | Mark Brown | 0% |
| 77 | review | 14 days? | Mon 3/29/04 | Thu 4/15/04 | Mark Brown | 0% |
| 78 | build | 9 days? | Fri 4/16/04 | Wed 4/28/04 | Mark Brown,Johnny F | 0% |
| 79 | assemble | 10 days? | Thu 4/29/04 | Wed 5/12/04 | Johnny F | 0% |
| 80 | test | 7 days? | Thu 5/13/04 | Fri 5/21/04 | Mark Brown,Johnny F | 0% |
| 81 | Probe Head housing | 70 days? | Mon 1/19/04 | Fri 4/23/04 | | 0% |
| 82 | design | 24 days? | Mon 1/19/04 | Thu 2/19/04 | Mark Brown | 0% |
| 83 | review | 15 days? | Fri 2/20/04 | Thu 3/11/04 | Mark Brown | 0% |
| 84 | build | 9 days? | Fri 3/12/04 | Wed 3/24/04 | Johnny F | 0% |
| 85 | assemble | 9.5 days? | Thu 3/25/04 | Wed 4/7/04 | Johnny F | 0% |
| 86 | test | 12.5 days? | Wed 4/7/04 | Fri 4/23/04 | Mark Brown,Johnny F | 0% |
| 87 | PUP | 113 days? | Mon 1/19/04 | Wed 6/23/04 | | 0% |
| 88 | Add pan & tilt 2 degrees of freedom | 113 days? | Mon 1/19/04 | Wed 6/23/04 | | 0% |
| 89 | Verify drive electronics fit | 12.5 days? | Mon 1/19/04 | Wed 2/4/04 | Alana Sherman | 0% |
| 90 | Design | 15 days? | Wed 2/4/04 | Wed 2/25/04 | Mark Brown | 0% |
| 91 | Design Review | 16 days? | Wed 2/25/04 | Thu 3/18/04 | Mark Brown | 0% |
| 92 | Build | 10.5 days? | Thu 3/18/04 | Thu 4/1/04 | Mark Brown,Johnny F | 0% |
| 93 | Assemble | 17.5 days? | Fri 4/2/04 | Tue 4/27/04 | Johnny F | 0% |
| 94 | Lab test | 11 days? | Tue 4/27/04 | Wed 5/12/04 | Mark Brown,Johnny F | 0% |
| 95 | Tank test | 15 days? | Wed 5/12/04 | Wed 6/2/04 | Mark Brown,Johnny F | 0% |
| 96 | Cold Test | 15.5 days? | Wed 6/2/04 | Wed 6/23/04 | Mark Brown,Johnny F | 0% |
| 97 | | | | | | |
| 98 | Cruises | 142 days? | Tue 3/16/04 | Wed 9/29/04 | | 0% |
| 99 | March 17-18 - Ventana | 4 days? | Tue 3/16/04 | Fri 3/19/04 | Ventana | 0% |
| 100 | March 19-22 - Ventana | 3 days? | Fri 3/19/04 | Tue 3/23/04 | Ventana | 0% |
| 101 | July 14-26 - Tiburon / Hydrate Ridge | 13 days? | Tue 7/13/04 | Thu 7/29/04 | Tiburon | 0% |
| 102 | Spet 27-28 - Ventana | 4 days? | Fri 9/24/04 | Wed 9/29/04 | Ventana | 0% |
|