|
This page last changed on Aug 21, 2008 by jbirch.
Schedule Items
- Middle of September; Japanese visitor to work on MFB.
- End of Sept for ~3 months; Allison Haywood (New Zealand) to work on a core.
- October deployment:
- Using Shanna Rae; MOB on October 8 (Weds), deploy October 9 (Thurs).
- there are enough ISUS's for deployment; must test all.
Machine Builds
- Gripper boards are out for fabrication
- Puck sensor boards (10 made) have been modified and Scott is testing on GG in the fridge. Preliminary results look good at ambient (+/- 1 degree difference from ambient; off 3 degrees at 5d C).
- Mack and Bruce being used (today) by SC group. Should be ready for October deployment with a simple reagent refill.
- Boards:
- 50 Dwarf / 10 Sleepy / 50 R-valve boards are in. Each needs a QC checkout which Dick started on 20Aug2008.
- Much discussion on the number of boards and the NEXT round of builds; could/should we do a board/camera redesign?
- Wiring harnesses are in and QC'd. Many assembled into their 'super-harnesses'.
- Still waiting on small machine parts from El Camino
- Installation of tubing on Moe is next; should take 1 week. Still need to mount AIV on Moe, which was originally scavenged for Neo. Cheri predicts 3-4 weeks before Science gets Moe for check-out.
- Cheri will get Mike going on the small hand pieces for Moe's manipulator.
Rough calculations on Mooring Cost:
Materials/Radios/machined parts/cables/bungee/all parts == $50K + 2 mo's labor
MFB
- Grill is working! as are PCR scripts
- SPE script is close but syringe continues to have trajectory errors. Much discussion on how to address. Decision to run overnight to 'break-in' and see if sticktion issues are still a problem at slow speeds tomorrow. If that doesn't fix it, we can either gear down motor (but this has problems; fast moves would be slow, mechanical advantage makes it more likely to break something if valve gets stuck), or find a more compatible plunger/barrel combination.
- Stand-alone power boards not yet begun (Scott).
- Go/no-go on PCR for October deployment depends on how PCR does in cold.
- Mechanical changes for NEO to accomodate grill are finished, but scripts need testing. PCR/core group will meet today at 2:00pm to discuss integration.
Software
- Antenna at Novin's (Sunset Dr, Watsonville). Brent and Wayne going out today to scout and sign agreement w/ homowner.
- DWSM code
- starting to test limit-switches; development of this code is on-going
- DWSM code is to a state where we could start testing if we had an instrument.
- Brent mentioned that if the new puck thermal-sensor is super-accurate, then maybe no calibration is needed (the preferred method). Perhaps insulating sensor may add to it's stability/accuracy.
- Brent fixed a core bug. The handling of background threads by using the 'stop' command now works.
DWSM
- Doug spoke with El Camino regarding DWSM parts. Bell housing should finish this week, anodized next week.
- No DMO discussion yet on weight balance/elevator design
- Min-Cons to be ordered by Scott; may take awhile because made of titanium (or 'ti-dized')
- Pressure testing; Initially, we do NOT need to got to 4Km, thus we will send/take sphere to Port Hueneme for testing.
NEXT WEEK:
Bring Calendar for deployment planning
Must test new syringes that arrived yesterday
|