|
This page last changed on Mar 04, 2009 by jbirch.
Present: Jim, Brent, Doug, Wayne, Cheri, Chris S., Scott
Absent: Addie (maternity)
Machine Builds
- Cores: A big thanks to Cheri for all her hard work these last 4 weeks preparing and then leading the build effort while McLane was here.
- On Gordon and Betty:
- all mechanical systems built, wired, and plumbed
- all, that is, except the hands
- discovered discrepencies on both Prunella and El Camino orders; some issues are the drawings, some are their work
- we will be using one old, one new harmonic drive for the hands
- R-valves. 6 of 35 boards were bad. Dick had these marked in the Project Library, but Cheri didn't know about that spreadsheet.
- HV pucks. seems to be working well; got a nice array from 4L of fluid. If it works well for invertebrates, we might modify some of our SH1 pucks to test before we place a new puck order. Chris S. working on this.
- We need screens by end of April/May deployments. Science will inventory rings and screens so we can place new order.
- WAG: scope hardening of ESP to 200m = 1 year.
-
MFB
- Mike has finished SPE heater modifications. Only need PCR tubing to ship to McLane.
Software
- dPress code ready for testing. Wayne will load Monday AM
- Brent not started on DWSM yet.
Deep ESP
- ISUS
- Luk says they have a 4km housing; just need a new probe--a PO away.
- We WILL NOT put ISUS on elevator in June
- John Ryan is taking over ISUS work. We may eventually want a TI housing. Craig Okuda may havve one for us (or a design)
Sphere
- Spider construction. All parts are machine shop. Will be finished today.
- Frank F. will do welding week after next in the high-bay. We'll have to get the sphere bottom out of its crate for that.
Elevator
- Still 3 weeks out. They had to send it out to be heat treated as their facility wasn't big enough.
- Modem. Because of where Clague will want to go while at Axial, we will probably NOT be within 2km of our drop site (which is required w/ a 60degree modem). Doug thinks we should change to low frequency modem--still working on power calculations, but seems we will buy a Low Freq omnidirectional model.
- Will purchase for the Flyer June deployment--must order in the next 2 weeks.
- Foam. being cut. ready in 2 weeks $1400.
DWSM
- Sample bags and switches are made
- We may not have stirrer motors in both bags by April.
- Bags are being assembled
- Oil & water not being pushed yet-
still having Jose make interface boards-should be finished early next week.
Other Items:
- Van: Doug has provided sketch of outlets (16) and lights to Greg Voogd
- we will push ESP to front of van and build a false wall so only front needs cooling
- Idea to put foldable desks (like Murphy tables)
- Need to check with Chris Grech about powering the van on UNOLS ships--what do we need?
- Greg will level the van next week.
- We need to figure out ventilation issues (i.e., false doors, screen doors, louvers, etc). Check w/ Ussler's van--how does he ventilate?
- Shallow ESP lids --need modification. Original P1 connector is a threaded thing that is breaking. Needs re-machining. Scott will handle.
- Potential Institute-wide chemical inspection--should have MSDS for all chemicals in Bldg A & B labs.
|